Installation Guide /  PostMount 1-A for XL Panel

8

Code-Compliant Planning and Installation Guide V 1.1 - Complying with AS/NZS1170.2-2011 ADMT 4-2016

- Certification -

 REF: CL-10129-S 

Internal REF: 00142  

 

 

 

18

th

 April 2019 

Clenergy Australia 
1/10 Duerdin Street 
Clayton, VIC 3168 

 

Array Frame Engineering Certificate 

 

Postmount PM4-A/2100 Installation 

 

MW Engineering Melbourne Pty Ltd, being Structural Engineers within the meaning of Australian and 

NZ Building Regulations, have carried out a structural design check of the PV-ezRack Postmount PM4-

A/2100 within Australia. The design check has been based on the information in the PV-ezRack PM4-

A/2100 Planning and Installation Guide and schematic drawings of the system components, provided by 

Clenergy Australia. 

 

Part number 

Description 

ER-R-ECO/2100 

PV-ezRack ECO Rail 2100mm 

ER-RT-100/3400 

PV-ezRack PM4

Rectangular Tube-Master 

100*100*3400*T5 

ER-RT-100/576 

PV-ezRack (PM6-A,PM8-A), Adjustable Tube 
100*50*576 

ER-P-152/3000 

PV-ezRack, Pipe ø152*3000*T6 

ER-SC-PM6/PM8 

PV-ezRack PM6-A,PM8-A, Steel Cap 
Assembly 

C-U/30/46-G 

PV-ezRack, Universal Clamp for Frame 
Height 30-46mm with Grounding Clip 

 

We find the Postmount PM4-A/2100 to be structurally sufficient for Australian and New Zealand use, 

based on the following conditions: 

 

 

Wind Loads to AS/NZ1170.2:2011, Amendment 4-2016: 

o

 

Wind Terrain Category: 2; 

o

 

Wind average recurrence interval of 100 years- For ultimate state, 25 years- service-

ability; 

o

 

Wind region A, B, C & D; 

 

Max Solar Panel Length 2.1m, width 1.1m; 

 

Yield Strength: 

Certification

Summary of Contents for PV-ezRack PostMount 1-A

Page 1: ...PostMount 1 A for XL Panel Code Compliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 ADMT 4 2016 Last Updated Mar 2022...

Page 2: ...8 12 Clenergy PV ezRack PostMount 1 A for XL Panel up to 2100 x 1100 mm is a ground mounting system suitable for large scale commercial and utility scale installations PVezRack PostMount 1 A for XL Pa...

Page 3: ...ng Marker Pen Spanner Anchoring Kit Torque Wrench Mixing Nozzles 5m Tape Components C U 30 46 G Universal Clampx4 ER AP PM1 A LP PostMount 1 A Kitx1 ER P 83 2400 Polex1 EZ GL ST Grounding Lugx2 ER SC...

Page 4: ...w Side view drawing of PV ezRack PostMount 1 A for XL Panel is shown below The panels tilt angle and embedment depth below are for reference only Please refer to Certificate Letter to obatin the certi...

Page 5: ...to reduce this risk Reduce the friction coefficient 1 Ensure that the thread surface is clean no dirt or contaminant 2 Apply lubricant grease or 40 engine oil to fasteners prior to tightening to avoid...

Page 6: ...s All drawings and dimensions in this installation guide are for generic reference The PV ezRack PostMount 1 A for XL Panel is to be optimized to suit specific conditions for each project and document...

Page 7: ...in all the axles of 2 14 holes aligned 1 As show in figure on the right with M12 120 hex bolts and nuts to lock Angle Steel 63 40 1250 on the Pole And then use M12 120 hex bolts and nuts to lock suppo...

Page 8: ...fix the PV Panel to the Rails by using Universal Clamps Recommended torque for M8 bolts is 18 20 N m There are three solutions for Grounding Lug installation Solution 1 Fix the Grounding Lug at the en...

Page 9: ...ation Guide and schematic drawings of the system components provided by Clenergy Australia Part number Description ER R ECO 2100 PV ezRack ECO Rail 2100mm ER RT 100 3400 PV ezRack PM4 Rectangular Tube...

Page 10: ...ompliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 ADMT 4 2016 Certification REF CL 10129 S Internal REF 00142 Steel 300 MPa Aluminium 240 MPa Maximum tilt angle options r...

Page 11: ...Installation Guide PostMount 1 A for XL Panel 10 Code Compliant Planning and Installation Guide V 1 1 Complying with AS NZS1170 2 2011 ADMT 4 2016 Certification REF CL 10129 S Internal REF 00142...

Page 12: ...ft class soil 1 60 wet clays silty loams wet loose sands Notes 1 Terrain Category 2 TC2 refers to open terrain including grassland with well scattered obstructions having heights generally from 1 5m t...

Page 13: ...assessment is always recommended and Clenergy must be informed on the outcome of the soil report Construction is to be carried out strictly on accordance with the instruction manual This work was des...