Installation Guide / PostMount 1-A for XL Panel
7
Code-Compliant Planning and Installation Guide V 1.1 - Complying with AS/NZS1170.2-2011 ADMT 4-2016
- Installation Instruction -
3) Position the PV Panel landscape by aligning the centre line
with the ECO-Rail. And fix the PV Panel to the Rails by using
Universal Clamps.
Recommended torque for M8 bolts is 18~20 N·m
There are three solutions for Grounding Lug installation.
Solution 1:
Fix the Grounding Lug at the end of Rail as shown in the figure on the right.
Solution 2:
Fix the Grounding Lug at the Rail where just under the PV Module as shown in
the figure on the right.
Solution 3:
Fix the Grounding Lug at the side channel of Rail as shown in the
figure on the right.