Installation. 

 

Safety note: 

Installation should be performed only by suitably qualified and 

experienced personnel.

 

 

The unit should be positioned according to the installation drawing, ensuring that space is 
allowed for access to the front and to the electrical terminal box.  
 
Particular care should be taken when siting a filter fitted with an 

explosion relief panel

 so 

that it complies with national regulations. 

Please also see Appendix 1

 below. It must be 

free to open with no obstructions. A safety exclusion zone outside the relief panel must be 
established. If in doubt, please contact. 

 
 
 
 
 
 
 
 
 

If the hopper is supplied as a separate item, lift into position with a suitable crane or forklift 
onto a prepared base. If required, it may be bolted to the ground. Units fitted with 

explosion panels

 or in exposed locations should be fixed to their foundations. 

 
Add mastic sealant to the hopper top flange then position the filter top section complete 
with fan, but with the silencer removed, using a crane  or forklift truck. Refer to the 
diagram above for sling angles etc. 
Insert screws into the vertical joining flange.  
Remove the lifting eyebolts and position the silencer (if supplied). 
 

Ductwork connections.

 

Duct connections within work places  must comply with current local regulations. In some 
applications with explosive dust types, explosion vents or non-return dampers  in the inlet 
and outlet ducts may be required. 

 

 

Safety note: 

In order to prevent unintentional access to rotating parts all duct joints up 

to 1 meter from rotating elements (e.g. screw conveyor, rotary valve) should have 
flanged joints or similar so that access is only possible by using tools. 

 

 
Electrical connections. 

Normally Auto M units are supplied with a combined fan and shaker controller. 

Important: 

this controller must not be mounted directly onto the filter unit because of 

vibration during the cleaning cycle. Typically it would be mounted on an adjacent wall. 
 
 
 
 

 

Location 
inside a 
building 

Location 
outside, 
preferred 

Summary of Contents for Enviraclean Systems M Z 15

Page 1: ...e Clemco Ltd Auto MZ Filter Units Owners Manual TSOM 535 Date of Issue 13 07 04 Hodge Clemco Ltd Orgreave Drive Sheffield South Yorkshire S13 9NR Tel 0114 254 0600 Fax 0114 2540250 Email sales hodgecl...

Page 2: ...contained mechanically cleaned dust filter collector units It is designed to extract dust laden air from non continuous processes that is so that the fan can be temporarily stopped from time to time t...

Page 3: ...etween the filter body and hopper Smaller units may be manufactured and shipped as a single complete unit Unit assembly If the unit is supplied in one piece then transport upright and lift as shown be...

Page 4: ...sealant to the hopper top flange then position the filter top section complete with fan but with the silencer removed using a crane or forklift truck Refer to the diagram above for sling angles etc I...

Page 5: ...aker should then run for approximately 8 seconds Normal operation 1 Check that dustbins are not overfilled They would normally be emptied at the end of each operating period when the automatic after c...

Page 6: ...ler should be cleaned and the source of the dust leakage investigated Do not allow persistent vibration as damage will result Fan and shaker motors These motors are maintenance free For special motors...

Page 7: ...aps and dampers for operation and wear 6 1000 13 Check filter housing and hopper for leakage and wear 6 1000 14 Clean exterior of controller with a moist cloth 1 300 15 Check tightness of flange conne...

Page 8: ...2 Remove the nuts and washers from the lower bag mounting frame 3 Lift the mounting frame complete with the filter bag from the studs 4 Lift the frame and filter bag carefully out of the filter unit...

Page 9: ...ely without rubbing against anything Any defects must be corrected before the fan is put into use again Replacement of internally mounted shaker motor Removal 1 Isolate the electrical supply 2 Open fr...

Page 10: ...m works correctly Check that the dust collection bin is not full Seal filter housing Insulate the filter and hopper against condensation Reduce water content of waste Fit pre separation section after...

Page 11: ...replace inlet fitting The cleaning is not effective Filter bag blinded Shaker running slow Clean manually or replace bag Check mechanism of shaker Re location or disposal of units Safety note Stop an...

Page 12: ...the airflow volume reduces noticeably Typically this should allow at least 4 hours continuous running Operating temperature Auto M Z Series Standard Unit Gas temperature 80 C maximum 10 C minimum Ambi...

Page 13: ...nit type and serial number Electrical Controller See separate instructions supplied with controller NF Fan When ordering spare parts please state motor size in kW and the serial number of the filter T...

Page 14: ...Page 14 of 17 TS OM535 Date of Issue 13 07 04 Hodge Clemco Ltd...

Page 15: ...ombined graphically in VDI 3673 by nomographs which are then used to determine the area of the ventilation panels Unit located outdoors Unless it is technically impossible this is the preferred locati...

Page 16: ...ressure wave from the primary explosion dislodging dust from walls beams and other surfaces The result of such a secondary explosion could be catastrophic General recommendation It is always recommend...

Page 17: ...Page 17 of 17 TS OM535 Date of Issue 13 07 04 Hodge Clemco Ltd...