Figure 29. One Opening Method
Unconfined Space/Engineered Design
When determining boiler room air requirements for unconfined space, the size of the room, airflow,
and velocity of air must be reviewed as follows:
1. Size (area) and location of air supply openings in the boiler room.
A. Two permanent air supply openings in the outer walls of the boiler room are recommended.
Locate one at each end of the boiler room, preferably below a height of 7 feet. This allows air
to sweep the length of the boiler. See Figure 30.
B. Air supply openings can be louvered for weather protection, but they should not be covered
with fine mesh wire, as this type of covering has poor air flow qualities and is subject to
clogging with dirt and dust.
C. A vent fan in the boiler room is not recommended, as it could create a slight vacuum under
certain conditions and cause variations in the quantity of combustion air. This can result in
unsafe burner performance.
D. Under no condition should the total area of the air supply openings be less than one square
foot.
Summary of Contents for CFC-E 1000
Page 1: ...CFC E ClearFire Condensing Boiler Boiler Book 02 2018...
Page 52: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 52 Figure 38 Primary Secondary Single Boiler...
Page 53: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 53 Figure 39 Primary Secondary Two Boilers...
Page 54: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 54 Figure 40 Primary Secondary Three Boilers...
Page 55: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 55 Figure 41 Primary Variable Flow Single Boiler...
Page 56: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 56 Figure 42 Primary Variable Flow Two Boilers...
Page 57: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 57 Figure 43 Primary Variable Flow Three Boilers...
Page 60: ...BOILER BOOK CFC E EXAMPLE SYSTEM SCHEMATICS 60...
Page 61: ...BOILER BOOK CFC E e mail info cleaverbrooks com Web Address http www cleaverbrooks com...