ATTENTION:
For some overhead doors, the upper brackets must be mounted wider than the actual
door frame. In those instances, cut a 16" section of stock 2" x 2" door frame tubing and mount it to the
outside of each vertical door frame using the supplied carriage bolts and nuts in the locations shown
in the diagram below. (Frame shown may differ from actual frame.)
DOOR FRAME DIAGRAM: SPECIAL NOTE
ATTENTION:
Use FAH325B 5/16" x 5" carriage
bolts and FALB32B 5/16" nuts to secure the 16"
frame extensions to the vertical door frame tubes.
Position the extension as shown. Refer to the
door installation instructions that shipped with the
door to install the overhead doors.
This tube is cut
from the remainder
of end wall
framing.
Header
Jamb
Jamb