EXAMPLE #2: Frame Assembly (continued)
6. Verify that the rafter is plumb and secure the purlin to
each 4-Way fitting and the rafter to each post cap as
previously described using Tek screws.
7. Continue to add the remaining purlins and secure the
remaining rafters to the post caps.
NOTE:
After setting each rafter in place, verify that the
rafter is plumb
before
securing the purlins to the
4-Way fittings.
Diagram may show a different shelter length.
Consult the Side Profile diagrams at the back of these
instructions to view each shelter length.
8. Once all interior rafters are set and all purlins are
secured to the 4-Way fittings, add the last two purlins
and set the final end rafter in position.
9. Secure the last end rafter to the assembled frame as
previously described.
10. Verify that all purlin connections are secured to the
connectors with Tek screws and verify that all rafter
legs are secured to the post caps with Tek screws.
11. After checking all connections of the assembled frame,
return to each 1/2" x 4-1/2" post cap mounting bolt and
tighten each bolt if this has not been done.
12. Continue with the FINAL FRAME CHECK and then
complete the RATCHET and MAIN COVER installation
procedures.
• If you
did not
purchase an optional end panel, skip
the next procedure and attach end ratchets as
described on page 14.
• If you ordered an optional end panel, complete the
following procedure.
END PANEL INSTALLATION (
Optional purchase
required.
)
The end panels for this frame are an optional purchase and
are not included. The following steps describe one way to
attach the end panels to your assembled and anchored low
profile frame using customer-supplied end conduits, angled
brackets, Tek screws, and washers.
The main steps to install an end panel include:
1. Assemble end conduits.
2. Attach end panel at the base using conduits and
angled brackets.
3. Pull the end panel up and over the end rafter.
4. Attach the end panel to the frame using the Tek screws
and washers.
Contact your sales representative to purchase an end
panel and the necessary connecting and installation
hardware.
End wall framing is also available and is recommended for
end panel installation.
FINAL FRAME CHECK
Gather the Parts
• Duct tape
1. Verify that all connectors, purlins, and post caps are
secured with Tek screws.
2. Recheck the frame assembly for sharp edges or Tek
screws that may interfere with the installation of the
cover. Reposition Tek screws as needed.
3. Use the supplied duct tape to tape any areas of the
frame that may damage the cover.
4. After the final frame check, complete one of the
following:
Summary of Contents for 105624
Page 18: ...CLEARSPAN CARPORTS 18 Revision date 10 27 08 FRONT PROFILE ...
Page 19: ...19 CLEARSPAN CARPORTS Revision date 10 27 08 SIDE PROFILE 105624 ...
Page 20: ...CLEARSPAN CARPORTS 20 Revision date 10 27 08 SIDE PROFILE 105625 ...
Page 21: ...21 CLEARSPAN CARPORTS Revision date 10 27 08 SIDE PROFILE 105626 ...
Page 22: ...CLEARSPAN CARPORTS 22 Revision date 10 27 08 SIDE PROFILE 105627 ...
Page 23: ...23 CLEARSPAN CARPORTS Revision date 10 27 08 CONNECTIONS ...