Mastic Dispensing Operation
Loading Rock into Hopper
Cimline C1 will accept rock 1/2” or smaller.
1) Slowly pour rock into hopper.
2) Remove any rock or debris that will not fit
through hopper grate to prevent clogging.
IF HOPPER CONVEYER SCREW CLOGS SHUT
OFF ENGINE AND REMOVE KEY TO PREVENT
STARTING. ALLOW THE CONVEYER SCREW
TO COOL DOWN BEFORE REMOVING HOPPER
GRATE AND UNCLOGGING SCREW.
DO NOT LOAD ROCK INTO HOPPER WITHOUT
GRATE PROPERLY INSTALLED.
3) Once you observe rock begin
to drop into the mixing
chamber
CLOSE
the Mastic
Gate
1) Set Rotary Switch on
Mastic Control Panel
to “
ROCK ONLY
”
2)
OPEN
the Mastic
Gate to draw rock
into heat chamber
Follow Start Up Procedures 1 & 2 on Page 14 prior to using
NOTICE
Preparing Mastic Operation
CAUTION
WARNING
Summary of Contents for C1
Page 13: ...13 Sub Control Panel Controls and Their Functions 1 2 3 4 5 6 7 8 9 10 11 12 IMLINE ...
Page 31: ...31 Sealant Control Panel Wiring Diagram ...
Page 37: ...37 Tank Burner Internal Wiring Diagram ...
Page 39: ...39 Hydraulic Schematic For Compressor Hydraulics see Supplement manual ...
Page 45: ...45 Sealant Plumbing Components ...
Page 50: ...50 Mastic Mixer Assembly ...
Page 55: ...55 Miscellaneous Parts ...