Example showing proper placement. Always installed *before* any
loads, and *before* the G1 DHW valve (if DHW is used in the system)
or *before* any G3 valve (if used). See proper placement in the
following examples.
4
The V18 must be installed in an upright orientation (vertical) and the
water flow entry should be from the bottom. The bottom, or water entry
end, is considered to be the end closest to the removable panel as shown
in all pictures.