Chemtrac UV254 Monitor
– UVM5000 v 2.1
Chemtrac, Inc.
7
5
Installation
5.1
Site Assessment
Prior to installation, the site should be assessed to collect all relevant information that may affect the installation
or operation of the system. Chemtrac has provided a checklist that can be used to ensure any installation or
operational problems can be addressed, resulting in the most efficient and effective installation and startup of
the system.
Table 2: Installation site assessment checklist and recommendations
CHECK
TIP
1
System installed outdoors?
Avoid areas with high exposure to sun and weather if possible.
2
If outdoors, system in direct
sunlight?
Select shaded area/shade hood for system or indoor location.
3
Temperature range at the
installation location?
Maximum operating temperature of 50°C.
4
Expected humidity at the
installation location?
Areas of high humidity may benefit from a spare desiccant pack.
5
Type of material the system will
be mounted on? (i.e. Concrete,
steel, railing)
Ensure the mounting hardware is appropriate and will support up to 50lbs
per component.
6
Sufficient space and clearance
to access and service the
system?
Refer to drawings in mounting section to ensure appropriate location is
selected. Minimal distance between system components is favored.
7
Power available at installation
location?
100-240VAC 50/60 Hz 4.0A input power required.
8
System location relevant to
measurement stream, what is
the distance?
Shortest possible distance minimizes measurement lag.
9
Favorable measuring
conditions? (i.e. no turbulence,
air bubbles, large suspended
solids etc.)
Select location with minimal measurement interferences.
10
Pressurized system able to
supply 300-1000 ml/min flow?
If necessary, use a needle valve to lower flow and maintain less than 20
PSI in analyzer. Splice connection from the side of the pressurized pipe, to
avoid air bubbles from top and sediment on bottom.
5.2
Unpacking and I nspection
To begin, remove the monitor from the packaging and carefully
inspect the product to ensure that no visible damage has occurred
during shipping. Next, ensure to remove the packing material that
is contained inside the cabinet. It is important to note that the
quartz flow cell and the rotating arm have been packed separately.
The following items will be:
Summary of Contents for Auto Clean UV254
Page 1: ......