Foundation plate installation
Option 1: Cast foundation plate into
concrete
2A.Bend the anchor brackets outwards
as shown in Figure 11.
1. The foundation plate can either be set
into a concrete foundation, as in Figures
11 to 17, or bolted down onto an
existing concrete plinth as shown in
Figure 18 and 19.
If the
D2 Turbo
is being used to replace
a D3 gate operator, refer to Figures 21 to
27.
When using a concrete foundation
it is recommended that the
foundation plate is welded to the
rail/track of the gate using short
length of flat bar, as in Figure 16.
This makes it possible to complete
the whole mechanical and
electrical installation, without
having to wait for the concrete to
set. After completing the
installation the concrete can be
poured and the operator left in the
Manual Mode until the concrete has
set.