4. Connect supply- and return-air ducts.

5. Install 24- X 24-in. sheet metal shield on platform in front of

louvered control panel as shown in Fig. 8.

Step 7—Horizontal Furnace Crawlspace Installation

Do not install the furnace on its back; safety control operation
will be adversely affected. Never connect return-air ducts to
the sides or back of the furnace. Failure to follow this warning
could result in fire, personal injury, or death.

The furnace can be installed horizontally with either the LH or RH
side up. In a crawlspace, the furnace can either be installed on
suitable blocks or pad (see Fig. 9.) or hung from the floor joist.
(See Fig. 10). The furnace can be suspended from each corner by
hanger bolts (4 each 3/8-in. all-thread rod) cut to desired length, 1
X 3/8-in. flat washer, 3/8-in. lockwasher, and 3/8-in. nut. Dimples
are provided for hole locations. (See Fig. 1.)

Since horizontal crawlspace installation is very similar to the attic
installation, refer to Step 6. The installation of a sheet metal shield
in front of the louvered control panel is covered in Step 6. For a
crawlspace installation, this same sheet metal shield must be
installed above the louvered control panel. Extend the sheet metal
shield over the furnace top far enough to cover the gas pipe entry
hole.

Step 8—Filter Arrangement

Never operate unit without a filter or with filter access door
removed. Failure to follow this warning could result in fire,
personal injury, or death.

The 2 factory-supplied filters are shipped in the blower compart-
ment. After the return-air duct has been connected to the furnace,

install the filters in a V-formation inside the return-air plenum. See
Fig. 11 and Table 4 for horizontal applications. Horizontal filter
retainers must be field supplied. See Fig. 12 for downflow
applications.

Step 9—Gas Piping

Gas piping must be installed in accordance with national and local
codes. Refer to the current edition of the NFGC.

Canadian installations must be installed in accordance with NSC-
NGPIC and all authorities having jurisdiction.

Refer to Table 5 for recommended gas pipe sizing. Risers should
be used to connect to the furnace and to the meter.

If a flexible connector is required or allowed by the authority
having jurisdiction, black iron pipe shall be installed at the
gas valve and extend a minimum of 2 in. outside the furnace
casing.

Use the proper length of pipes to avoid stress on the gas
control manifold. Failure to follow this warning could result
in a gas leak, causing fire, explosion, personal injury, or
death.

Connect the gas pipe to the furnace using a backup wrench to
avoid damaging gas controls.

Never purge a gas line into a combustion chamber. Never use
matches, candles, flame, or other sources of ignition to check
for gas leakage. Use a soap-and-water solution to check for
gas leaks. Failure to follow this warning could result in fire,
explosion, personal injury, or death.

Joint compounds (pipe dope) should be applied sparingly and only
to the male threads of the joints. This pipe dope must be resistant
to the action of propane gas.

An accessible manual shutoff valve MUST be installed upstream
of the furnace gas controls and within 72 in. of the furnace. A
1/8-in. NPT plugged tapping, accessible for test gage connection,
MUST be installed immediately upstream of the gas supply
connection to the furnace and downstream of the manual shutoff
valve. Place a ground joint union between the gas control manifold
and the manual shutoff.

Install a sediment trap in the riser leading to the furnace. The trap
can be installed by connecting a tee to the riser leading from the
furnace. Connect a capped nipple into the lower end of the tee. The
capped nipple should extend below the level of the gas controls.
(See Fig. 13.)

Piping should be pressure tested in accordance with local and
national plumbing and gas codes before the furnace has been
attached. If the pressure exceeds 0.5 psig (14-in. wc), the gas
supply pipe must be disconnected from the furnace and capped
before the pressure test. If the test pressure is equal to or less than
0.5 psig (14-in. wc), turn off electric shutoff switch located on the
gas valve before the test. It is recommended that the ground joint
union be loosened before pressure testing.

After all connections have been made, purge the lines and check
for gas leakage with regulated gas supply pressure.

A93043

FRONT

BACK

FRONT

B
A
C
K

Fig. 9—Horizontal Installation on Blocks

A95235

9

Summary of Contents for 58RAV 170 Series

Page 1: ... literature on tags and on labels attached to or shipped with the unit and other safety precautions that may apply In the United States follow all safety codes including the National Fuel Gas Code NFGC NFPA 54 1999 ANSI Z223 1 1999 and the Installation Standards Warm Air Heating and Air Condition ing Systems NFPA 90B ANSI NFPA 90B In Canada refer to the CAN CGA B149 1 and 2 M95 National Standard o...

Page 2: ...o be installed in a furnace follow items 1 through 5 before bringing the control or yourself into contact with the furnace Put all used AND new controls into containers before touching ungrounded objects 7 An ESD service kit available from commercial sources may also be used to prevent ESD damage Table 1 Dimensions In UNIT SIZE A D E VENT CONN SHIP WT LB 050 08 14 3 16 12 9 16 12 11 16 4 121 050 1...

Page 3: ...inances especially those that may not have kept pace with changing residential construction practices We require these instructions as a minimum for a safe installation Application of this furnace should be indoors with special attention given to vent sizing and material gas input rate air temperature rise and unit sizing Improper installation or misapplication of the furnace can require excessive...

Page 4: ...e ample space for servicing and cleaning Always comply with the minimum fire protection clearances shown on the unit rating plate This furnace shall not be installed directly on carpeting tile or any combustible material other than wood flooring The furnace may be installed on combustible flooring when installed with the accessory downflow subbase which is available from your distributor or branch...

Page 5: ...jacent to furnace all air for combustion must come from outdoors 2 Air from outside the structure requires 1 of the following methods a If combustion air is taken from outdoors through 2 vertical ducts the openings and ducts MUST have at least 1 sq in of free area per 4000 Btuh of total input for all equipment within the confined space See Fig 4 and Table 2 b If combustion air is taken from outdoo...

Page 6: ...The return air duct must be connected to return air opening inlet provided as shown in Fig 1 DO NOT cut into casing sides or back to attach any portion of return air duct Bypass humidifier connec tions should be made at ductwork or coil casing sides exterior to furnace Fig 3 Confined Space Air for Combustion and Ventilation from an Unconfined Indoor Space A93387 RETURN AIR 6 MIN FRONT SUPPLY AIR V...

Page 7: ...rking platform on location where all required furnace clearances are met See Fig 2 and 8 INSTALL FURNACE 1 Position furnace in desired location 2 Connect gas supply pipe See Fig 8 for typical piping entry 3 Install field supplied filter retainers as indicated in Fig 11 and Table 4 before connecting return air duct to furnace Table 3 Opening Dimensions In FURNACE CASING WIDTH APPLICATION PLENUM OPE...

Page 8: ...ed on a Combustible Floor A96284 CD5 OR CK5 COIL ASSEMBLY OR KCAKC COIL BOX FURNACE SHEET METAL PLENUM FLOOR OPENING COMBUSTIBLE FLOORING Fig 8 Typical Attic Installation A97516 30 IN MIN WORK AREA 6 MIN TYPE B VENT GAS ENTRY 24 24 SHEET METAL SEDIMENT TRAP MANUAL SHUTOFF GAS VALVE LINE CONTACT ONLY PERMISSIBLE BETWEEN LINES FORMED BY INTERSECTIONS OF THE TOP AND TWO SIDES OF THE FURNACE JACKET AN...

Page 9: ...ect to the furnace and to the meter If a flexible connector is required or allowed by the authority having jurisdiction black iron pipe shall be installed at the gas valve and extend a minimum of 2 in outside the furnace casing Use the proper length of pipes to avoid stress on the gas control manifold Failure to follow this warning could result in a gas leak causing fire explosion personal injury ...

Page 10: ...r 115 v wiring If polarity is incorrect control center status code indicator light will flash rapidly and furnace will not operate Fig 10 Horizontal Crawlspace Installation on Hanger Rods A96633 NOTES ANGLE IRON OR EQUIVALENT ROD LOCATION USING DIMPLE LOCATORS SEE DIMENSIONAL DWG FOR LOCATIONS 3 8 IN ROD 1 A 1 In clearance minimum between top of furnace and combustible material 2 The entire length...

Page 11: ... or controller manufacturer s instructions for proper connec tion A failure to follow this warning could result in fire NOTE A field supplied 115 v controlled relay connected to EAC terminals may be added if humidifier operation is desired during blower operation Step 11 Venting Refer to the national or local installation code such as NFGC in the United States or the NSCNGPIC in Canada for proper ...

Page 12: ...own for proper operation Some thermostats require a C terminal connection as shown If any of the original wire as supplied must be replaced use same type or equivalent wire W Y GND THERMOSTAT TERMINALS 1 2 3 Fig 14 Furnace Control A99255 HUMIDIFIER TERMINAL 24 VAC 0 5 AMP MAX LED OPERATION DIAGNOSTIC LIGHT HARNESS CONNECTOR 24 V TRANSFORMER SEC 2 SPARE 1 SPARE 2 EAC 1 EAC ELECTRONIC AIR CLEANER TE...

Page 13: ...t sensed the control closes the gas valve and repeats the ignition cycle NOTE Ignition sequence will repeat 3 additional times before a lockout occurs Lockout automatically resets after 3 hrs or can be manually reset by turning 115v off not at thermostat for 3 sec minimum then on again f Blower on delay Forty five sec after burner flame is proven the blower motor is energized on heating speed Simu...

Page 14: ...VAC CONDUCTOR ON PCB FIELD WIRING TERMINAL FIELD GROUND EQUIPMENT GROUND FIELD SPLICE PLUG RECEPTACLE L1 L2 L1 BLWR HI LO TO 115VAC FIELD DISCONNECT NOTE 4 EQUIPMENT GROUND SPARE 2 HEAT SPARE 1 COOL NOTE 7 COM HSIR EAC 1 START OL COM HI MED HI MED LO LO BLWM SCHEMATIC DIAGRAM NATURAL GAS PROPANE EAC 2 1 1 HSI 2 PL5 2 PL2 3 PL3 PR2 115VAC PR1 TRAN 24VAC 1 2 IDR TEST TWIN FU1 NOTE 6 CAP L2 PL1 8 FSE...

Page 15: ...ignal is present at control Component test sequence is as follows a Momentarily jumper TEST and COM 24V terminals until LED goes off b LED will display previous status 4 times c Inducer motor starts and continues to run for entire com ponent test d Hot surface igniter is energized for 15 sec then de energized e Blower motor operates on cooling speed for 10 sec then stops f Blower motor operates on...

Page 16: ... 43 2 8 43 2 9 43 3 0 43 3 1 4500 1025 43 2 6 43 2 6 43 2 7 43 2 8 43 2 9 ALTITUDE RANGE FT AVG GAS HEAT VALUE AT ALTITUDE BTU CU FT SPECIFIC GRAVITY OF NATURAL GAS 0 58 0 60 0 62 0 64 0 66 Orifice No Manifold Pressure Orifice No Manifold Pressure Orifice No Manifold Pressure Orifice No Manifold Pressure Orifice No Manifold Pressure U S A Only 750 42 3 4 42 3 6 42 3 7 42 3 8 41 3 5 775 42 3 2 42 3...

Page 17: ...43 2 4 43 2 5 43 2 5 43 2 6 850 43 2 2 43 2 2 43 2 3 43 2 4 43 2 5 875 43 2 0 43 2 1 43 2 2 43 2 3 43 2 3 ALTITUDE RANGE FT AVG GAS HEAT VALUE AT ALTITUDE BTU CU FT SPECIFIC GRAVITY OF NATURAL GAS 0 58 0 60 0 62 0 64 0 66 Orifice No Manifold Pressure Orifice No Manifold Pressure Orifice No Manifold Pressure Orifice No Manifold Pressure Orifice No Manifold Pressure U S A Only 625 43 3 4 43 3 6 43 3...

Page 18: ...te cu ft hr X heating value Btu cu ft using natural gas heating value from local gas utility supplier EXAMPLE 0 2000 ft altitude Btu heating input Btu cu ft X cu ft hr Heating value of gas 1050 Btu cu ft Time for 1 revolution of 2 cu ft dial 82 sec Gas rate 88 cu ft hr from Table 9 Btu heating input 88 X 1050 92 400 Btuh In this example the orifice size and manifold pressure adjustment is within 2...

Page 19: ...e blower motor has started See the thermostat manufacturer s instructions for adjusting the heat anticipator and for varying the heating cycle length Table 9 Gas Rate Cu Ft Hr SECONDS FOR 1 REVOLUTION SIZE OF TEST DIAL SECONDS FOR 1 REVOLUTION SIZE OF TEST DIAL 1 cu ft 2 cu ft 5 cu ft 1 cu ft 2 cu ft 5 cu ft 10 11 12 13 14 360 327 300 277 257 720 655 600 555 514 1800 1636 1500 1385 1286 50 51 52 5...

Page 20: ...ire harness c Turn on 115 v power to furnace d Set thermostat to call for heat and wait 1 minute When pressure switch is functioning properly hot surface igniter should NOT glow and control diagnostic light flashes a status code 31 If hot surface igniter glows when inducer motor is disconnected shut down furnace immediately Determine reason pressure switch did not function properly and correct con...

Page 21: ...cal Codes ____________ 1 4 in Upward Slope ____________ Joints Secure ____________ See Attached Vent Table Instructions CHECKLIST START UP ____________ Gas Input Rate Set Within 2 percent of Rating Plate ____________ Temperature Rise Adjusted ____________ Thermostat Anticipator Setting Adjusted or ____________ Thermostat Cycle Rate 3 cycles per Hr CHECK SAFETY CONTROLS OPERATION ____________ Prima...

Page 22: ...22 ...

Page 23: ...23 ...

Page 24: ...e Training plus hands on the products in our labs can mean increased confidence that really pays dividends in faster troubleshooting fewer callbacks Course descriptions and schedules are in our catalog CALL FOR FREE CATALOG 1 800 962 9212 Packaged Service Training Classroom Service Training Copyright 2000 CARRIER Corp 7310 W Morris St Indianapolis IN 46231 58ra16si Manufacturer reserves the right ...

Reviews: