Fig. 8 — Location of Notches
Fig. 9 — Horizontal Duct Panels In Place
Step 8 — Install Outside Air Hood
ECONOMIZER HOOD PACKAGE REMOVAL AND
SETUP - FACTORY OPTION
1. The hood is shipped in knock-down form and must be
field-assembled. The indoor coil access panel is used as
the hood top while the hood sides, divider and filter are
packaged together, attached to a metal support tray using
plastic stretch wrap, and shipped in the return-air com-
partment behind the indoor coil access panel. The hood
assembly’s metal tray is attached to the basepan and also
attached to the damper using two plastic tie-wraps.
2. To gain access to the hood, remove the filter access
panel. (See Fig. 10.)
Fig. 10 — Typical Access Panel Locations
3. Locate the 2 screws holding the metal tray to the basepan
and remove. Locate and cut the 2 plastic tie-wraps secur-
ing the assembly to the damper. (See Fig. 11.) Be careful
to not damage any wiring or cut tie-wraps securing any
wiring.
Fig. 11 — Economizer Hood Parts Location
4. Carefully lift the hood assembly (with metal tray)
through the filter access opening and assemble per the
steps outlined in Economizer Hood, below.
ECONOMIZER HOOD ASSEMBLY
NOTE: If the power exhaust accessory is to be installed on the
unit, the hood shipped with the unit will not be used and must be
discarded. Save the aluminum filter for use in the power exhaust
hood assembly.
1. The indoor coil access panel will be used as the top of the
hood. Remove the screws along the sides and bottom of
the indoor coil access panel. See Fig. 12.
BASEPAN
NOTCHES
NOTCHES
SCREWS
DUCT COVERS
SHEET METAL
FACE UP
BASEPAN
FILTER ACCESS PANEL
OUTDOOR-AIR OPENING AND
INDOOR COIL ACCESS PANEL
COMPRESSOR
ACCESS PANEL
Hood Parts
Plastic Tie Wrap
Qty (2)
Screws for Metal Tray
Qty (2)
Summary of Contents for 50KC*A/B0 Series
Page 4: ...4 Fig 2 Dimensional Drawing...
Page 5: ...5 Fig 2 Unit Dimensional Drawing cont...
Page 22: ...22 Fig 38 Electro Mechanical Control Wiring Diagram...
Page 23: ...23 Fig 39 Electro Mechanical Control Wiring Diagram with Humidi MiZer System...
Page 24: ...24 Fig 40 Electro Mechanical Power Wiring...
Page 25: ...25 Fig 41 PremierLink Wiring Schematic...
Page 26: ...26 Fig 42 PremierLink Wiring Schematic with Humidi MiZer System...
Page 27: ...27 Fig 43 RTU Open System Control Wiring Diagram...
Page 28: ...28 Fig 44 RTU Open System Control Wiring Diagram with Humidi MiZer System...
Page 43: ...43 Fig 57 TXV Metering Device Position in Reheat Coil Typical Diagram for Sizes 04 06 TXV...
Page 44: ......
Page 45: ......