background image

22

prevent sweating and must be protected from wear or erosion at

the joint between the insulation and the fireproofing material.

When no risers are ordered for the universal stack unit, it is the re

-

sponsibility of the installer to make sure that an isolation ball valve

is installed between each supply and return piping connection to

the unit. Flare fittings are factory provided to allow connection be

-

tween the ball valves and the hoses.

Supply Air Installation

Each side of the unit has one supply air knockout as well as a sup

-

ply air knockout on the top of the unit (see Fig. 20)

1. Determine  which  supply  air  opening/openings  are  required

for your application. 

NOTE: The supply air opening on the riser side of the unit should

not be used. 

2. Use a sharp retractable knife to trim insulation using center

knockout slot/trim line as pattern (see Fig. 27). 

3. Use a sharp standard needle nose pliers and grab knockout

tab (see Fig. 27)

Fig. 27 — 42SUA Unit Supply Air Knockout Tab

Location

4. Twist or pry pliers back and forth until knockout tab breaks

away from unit. 

5. Repeat for all supply air tabs until all have been broken. 
6. Discard center knockout piece. Be careful of sharp edges. 
7. Use  a  sharp  retractable  knife  to  trim  any  excess  insulation

using knockout hole as pattern.

8. Use duct pliers (hand seamers) to fold duct flange out of the

unit 90 degrees for each side of the supply air opening along

duct break (see Fig. 27). The 90-degree flanges can now be

used as drywall stops to prevent coverage of discharge open

-

ing (see Fig. 28).

Fig. 28 — 42SUA Supply Air Installation

9. Use adhesive or glue to re-attach insulation that has pulled

away from the unit during knockout removal process. 

10. For  ducted  applications  tape  should  be  applied  along  and

around all of the supply air opening knockouts to prevent air

leakage. 

All installations should be made in compliance with all governing

codes and ordinances. Compliance with all codes is the responsi

-

bility of the installing contractor.
42SMA FURRED-IN MEGA UNITS
The unique design of the mega stack fan coil unit allows for field-

configuration of each unit. Risers, shown with unit, are for refer

-

ence only. All risers are factory-fabricated and shipped loose for

field installation. It is important that you identify all of the unit

feature  locations  before  proceeding  with  the  installation  (see

Fig. 11).

Unit orientation is determined based on the location of the risers in

the building. Risers can only be installed on the rear side of the

unit and always determine the rear of the mega stack unit. The re

-

turn air is always on the front (see Fig. 29).

Fig. 29 — 42SM Unit Installation

Supply, Return, and Drain Risers

NOTE: Submittals and product literature detailing unit operation,

controls,  and  connections  should  be  thoroughly  reviewed

BEFORE  beginning  the  connection  and  testing  of  risers  and

piping.

The supply and return connections are marked on the coil stubouts

and  the  valve  package  depending  on  your  configuration.  “CS”

means cold water supply, “CR” means cold water return, “HS”

means hot water supply, and “HR” means hot water return to indi

-

cate  flow  direction  to  and  from  the  coil.  Blue  letters  mark  the

chilled water connections and red letters mark the hot water con

-

nections.

The unit internal piping is designed to accommodate a total riser

vertical movement of ±1-1/2 in., due to thermal expansion and/or

contraction, when positioned properly at the jobsite. Risers must

be anchored to the building structure to limit riser expansion and

contraction movement to a maximum of 3 inches. Riser anchoring

and expansion compensation is not included in the factory-sup

-

plied unit and must be field-provided. While some special riser

features are available from the factory, riser end caps, air vents,

and/or  flushing  loops  are  normally  provided  on  the  job  by  the

installer. 

Knockout Tab
(10 Places)

Duct Break
(4 Places)

Knockout Tab
Trim Line

Duct Flange

90°

Unit Wall

Unit
Installation

CAUTION

Toxic residues and loose particles resulting from manufactur

-

ing and field piping techniques such as joint compounds, sol

-

dering flux, and metal shavings may be present in the unit and

the piping system. Special consideration must be given to sys

-

tem cleanliness when connecting to solar, domestic or potable

water systems. Coil not rated for portable use.

RETURN AIR

42SMA 14-20

CABINET

HR

CR

D

HS

CS

HR =

HOT WATER RETURN

HS =

HOT WATER SUPPLY

D

=

DRAIN

CR =

COLD WATER RETURN

CS =

COLD WATER SUPPLY

D

CR

HS

CS

HR

R =

RETURN

D =

DRAIN

S =

SUPPLY

R

D

S

2- or 4-PIPE

RIGHT

LEFT

REAR

FRONT

Summary of Contents for 42S Series

Page 1: ...STRUCTION 32 APPENDIX B POTENTIOMETER ADJUSTMENT 35 APPENDIX C CONTROL OPERATIONS 36 APPENDIX D EVO ECM 4 SPEED ADJUSTMENT 41 START UP CHECKLIST FOR 42S SERIES FAN COIL AIR CONDITIONERS CL 1 SAFETY CO...

Page 2: ...angement should be verified against the order documents Should any discrepancy be found the local sales representative should be notified immedi ately so that proper action may be taken Should any que...

Page 3: ...tural support Due to variations in building construction floor plans and unit configurations each installation is different The actual step by step method of installation may vary from unit to unit H...

Page 4: ...ox lb per row of coil 1 79 2 63 3 45 4 09 4 09 4 39 COILS FPI 14 fins inch BLOWER qty 42SGA SH SU SGM SGS SM 1 1 1 1 1 1 1 1 1 42SJ 2 2 2 2 2 2 FILTERS Nominal Size in 1 in thick 12 1 2 x 24 1 4 16 1...

Page 5: ...14 356 8 203 14 356 6 152 14 356 10 254 17 432 1 1 2 38 1 1 2 38 14 356 04 12 305 06 18 457 10 254 18 457 16 406 12 305 20 508 1 25 2 51 18 457 08 12 305 10 22 559 16 406 22 559 8 203 18 457 16 406 24...

Page 6: ...6 Fig 4 Riser Chase Unit Width Riser Chase Depth All model sizes 5 1 2 141 Unit Depth Riser Chase Risers Unit Height Stack Unit...

Page 7: ...E DIMENSIONS in mm SIDE FRONT SUPPLY DOUBLE SUPPLY TOP SUPPLY SINGLE DIMENSIONS A B A B C D E F G H 03 14 356 8 203 14 356 6 152 14 356 10 254 17 432 22 1 8 562 22 1 8 562 14 3 4 375 04 12 305 8 203 0...

Page 8: ...to permit expansion and contrac tion of risers Coil connections to be at the center of the slots 11 See unit arrangements for supply and return air orientation 12 Dimensions are in inches Dimensions...

Page 9: ...1 Service Switch Optional NOTES 1 Units are fabricated of galvanized steel with a 16 gauge galvanized fan deck 2 All risers are insulated 3 Thermostats shipped loose for field installation 4 Risers ar...

Page 10: ...to permit expansion and contrac tion of risers Coil connections to be at the center of the slots 8 See unit arrangements for supply and return air orientation 9 Dimensions are in inches Dimensions in...

Page 11: ...9 Return Air Opening 10 Drain Knockout s Side Panels 11 Access Panel Control Box 12 Riser Supply and Return 13 Riser Drain 14 Isolation Ball Valves 15 Strip Heater Optional E Heat 16 Heat Limit Switch...

Page 12: ...ES 1 Units are fabricated of galvanized steel with a 16 gauge galvanized fan deck 2 All risers are insulated 3 Thermostats shipped loose for field connection 4 Risers are factory piped to coil with va...

Page 13: ...and control box are insulated 7 Riser length floor to floor 2 in 51 mm Maximum riser length is 119 in 3023 mm 8 Maximum riser size is 2 1 2 in 64 mm diameter If larger sizes are required please consul...

Page 14: ...16 406 4 102 NOTES 1 Plenum box adds 22 in 559 mm to unit height adds 26 lb 11 8 kg to unit weight and is factory installed 2 1 4 in closed cell insulation is standard for the plenum box 3 Side suppl...

Page 15: ...ensions in inches PANEL NO UNIT SIZE A 1 42SG SJ SU 03 04 15 5 06 08 19 5 10 12 23 5 42SM 14 16 20 29 5 2 42SG SJ 03 04 15 5 06 08 19 5 10 12 23 5 3 42SG SJ 03 04 15 2 06 08 19 2 10 12 23 2 PANEL NO 1...

Page 16: ...TE S a Dimensions in inches PANEL NO UNIT UNIT SIZE A 4 42SG SJ SU 03 04 15 1 06 08 19 1 10 12 23 1 5 42SG SJ 03 04 15 1 06 08 19 1 10 12 23 1 6 42SG SJ 03 04 16 7 06 08 20 7 10 12 24 7 PANEL NO 4 54...

Page 17: ...should never be lifted up or pulled down to meet the riser on the floor below or above 4 Install isolator pads beneath the four corners of unit if appli cable 5 Before anchoring the equipment in place...

Page 18: ...unit frame d After all units in a stack are anchored make unit to unit riser joints First center each coil to riser line within the expansion slot in the unit back panel Each riser joint must be in ve...

Page 19: ...dary arrangements Potential Universal Arrangement Unit Configurations Risers Three Locations The pre installed supply return and drain risers 2 pipe or 4 pipe applications can be oriented on any of th...

Page 20: ...taller Riser to Unit Installation Before making the riser joints the riser insulation must be pulled back away from the joint and protected from heat during the braz ing process Each riser joint must...

Page 21: ...bottom of the unit as shown in Fig 26 10 Push the rubber drain hose over the riser drain stubout Be careful not to bend the drain stubout 11 Adjust the hose clamp over the riser stubout and rubber hos...

Page 22: ...nly All risers are factory fabricated and shipped loose for field installation It is important that you identify all of the unit feature locations before proceeding with the installation see Fig 11 Un...

Page 23: ...ical 3 The plastic flare caps on the end of the riser ball valves should be removed and discarded 4 All mega stack units use reinforced braided stainless steel flexible hose kits for piping between fi...

Page 24: ...to withstand the total operating pressure both static and pumping head to which the system will be subjected Low temperature lead alloy solders such as 50 50 and 60 40 are normally not suitable Chille...

Page 25: ...th optional auxiliary electric heat is desired an additional aquastat is required If the valve package is field supplied the aquastat must be installed in a location where it will sense the water temp...

Page 26: ...ing However drywall secured with adhesive bonding alone is NOT recommended CONCEALED UNIT ENCLOSURE Concealed units are designed to have gypsum board or other types of wall board applied directly to t...

Page 27: ...y steam of water begins to escape close valve Vent release air slowly usually dripping water into drain pan in the process Make sure all service valves are open and that the motorized control valves i...

Page 28: ...ize themselves with the unit options and accesso ries and control sequence to understand the proper system opera tion All personnel should have a good working knowledge of general start up procedures...

Page 29: ...hould not be attempted by unqualified personnel The system must be complete and all components must be in operating condition BEFORE beginning water system balancing operations Each hydronic system ha...

Page 30: ...nd tag unit electrical service switch Check drain pan drain line and trap before initial start up and at start of each cooling season A standard type pipe cleaner for 3 4 in ID Inside Dimensions pipe...

Page 31: ...be replaced on a regular basis The time interval be tween each replacement should be established based on regular in spection of the filter and should be recorded in the log for each unit Refer to the...

Page 32: ...OUT CONSTRUCTION SIZE TYPE OF INSTALLATION TYPE 1 TYPE 2 TYPE 3e e Not recommended for Siamese Ditto Installation W x L in W x L in W x L in Single Unit and Siamese Ditto 03 04 96 5 7 8 x 15 5 1 8 x...

Page 33: ...Table D Short 79 in Cabinet 4 Pipe 42S Units a b c d NOTE S a CLEAR HEIGHT is the dimension from the floor to ceiling See Fig A of this appendix b The above charts allow 1 in tolerance in clear height...

Page 34: ...o Floor Clear Height Riser Length Block out Length Unit Unit Block out Width NOTE Riser Length Floor to floor dimensions 2 in maximum riser length of 115 in When riser length must exceed 115 in use 10...

Page 35: ...outputs high medium and low 5 High Speed Close high speed relay by applying 24 v to the high terminal Using a small screwdriver turn the VR3 poten tiometer so the meter measures 4 51 vdc This will se...

Page 36: ...REMOTE SHUTDOWN INPUT 1 Provides dry contact for signal to BAS system I O a Dry Normally Open b Wet Normally Open c Discrete Coil 2 When contact activated a Motor OFF b Actuator OFF c Electric Heat O...

Page 37: ...Fan Low Speed W1 HTG Heat Y1 CLG Cool W2 HT2 Heat Stage 2 Y2 CL2 Cool Stage 2 R 24V 24V Controller Power COS Changeover Sensor RAS Room Air Sensor Table F 0 10 Variable Airflow ECM CONNNECTION FUNCTIO...

Page 38: ...adjusted from 0 to 100 of the motor s factory programmed operating range Use voltmeter and airflow chart on control box cover to set values Adjusting the potentiometers requires the use of a Multi met...

Page 39: ...ll actuate and supply 24VAC to Pin 12 of connector CN5 When 0 10VDC is applied to HTG that control signal will passively be present at Pin 8 of the CN6 connector HTG LED shows GREEN Signal for 1st sta...

Page 40: ...40 APPENDIX C CONTROLS OPERATION CONT Fig H Typical Wiring Diagram NOTE Wiring diagram also available through QR code found on the unit serialized name plate label...

Page 41: ...lead of the meter to the high speed Flo1 terminal below the potentiometer 6 High Speed Using a small screwdriver turn the Flo1 potenti ometer so the meter measures 4 51 vdc This will set the ECM speed...

Page 42: ...s the right to discontinue or change at any time specifications or designs without notice and without incurring obligations Catalog No 04 53420024 01 Printed in U S A Form 42S 5SI Pg 42 9 22 Replaces...

Page 43: ...l supply voltage 8 Proper access provided for unit and accessories 37 Record ambient temperatures 9 Proper electrical service provided 38 Check all wiring for secure connections 10 Proper overcurrent...

Page 44: ...______________________________________________________ _________________________________________________________________________________________________________________________________________________...

Reviews: