background image

21

2. Before anchoring the equipment in place, the unit must be

leveled and the cabinet must be plumb and squared. The unit

may be anchored in place by bolting directly through the unit

floor or attaching to the cabinet in some location that will not

interfere with drywall or other items such as the supply grille,

thermostat, or return access panel. When attaching to the unit

cabinet,  care  must  be  taken  to  not  penetrate  the  cabinet  in

locations  that  may  damage  internal  components  or  wiring.

The mounting technique is a matter of choice; however, the

unit should always be anchored  securely  to prevent  move

-

ment during construction and riser expansion and contraction.

After anchoring the unit, it is then ready for the various ser

-

vice connections such as riser connections and electrical.

3. The  plastic  flare  caps  on  the  end  of  the  riser  ball  valves

should be removed and discarded.

4. All universal stack units use reinforced braided stainless steel

flexible hose kits for piping between field-installed risers and

unit water coils as shown in Fig. 24. The hose kit design has

threaded connections on each end. The hose kits allow for

riser fluctuations due to thermal expansion.

Fig. 23 — 42SUA Unit Riser to Unit Installation Setup

Fig. 24 — 42SUA Unit Riser to Unit Installation

Fig. 25 — 42SUA Unit Riser to Unit Installation

(Tighten Swivel Connections)

Fig. 26 — 42SUA Unit Riser to Drain Installation

5. Use a wrench to tighten the swivel connections. Use a backup

wrench  to  hold  the  riser  ball  valve  stationary  to  prevent  it

from  bending  or  twisting  during  installation  as  shown  in

Fig. 25. Be careful not to over-tighten swivel connections.

6. Locate the unit’s coil fitting.
7. The plastic flare caps on the end of the coil fitting should be

removed and discarded.

8. Use a wrench to tighten the swivel connections. The baffle

acts  as a  secondary  wrench.  Be  careful  not to  over-tighten

swivel connections.

9. Locate the p-trap drain and rubber hose factory installed to

the drain pan connection in the bottom of the unit as shown in

Fig. 26

10. Push the rubber drain hose over the riser drain stubout. Be

careful not to bend the drain stubout. 

11. Adjust the hose clamp over the riser stubout and rubber hose

to hold in place as shown in Fig. 26. 

12. Test for leaks. Any and all leaks should be repaired before

proceeding with installation. When testing with air or some

other gas, it might be necessary to tighten stem packing nuts

on some valves to maintain air pressure in the riser. Pressure

testing risers with water should be done with the unit service

valves closed to prevent flushing debris into the unit valve

packages. This will also allow risers to be drained down after

testing in the winter to avoid freeze-up problems. In the event

that leaking or defective components are discovered, the sales

representative  must  be  notified  BEFORE  any  repairs  are

attempted. All  leaks  should  be  repaired  before  proceeding

with the unit installation. 

13. After system integrity has been established, the riser insula

-

tion must be pulled back into place over the joint and glued or

sealed to prevent sweating and heat loss or gain. All of the ris

-

ers, including the riser stubouts, should be properly covered

with insulation. Internally mounted chilled water piping and

valves  are  located  over  the  drain  pan  and  need  not  be

insulated.

Any  fireproofing  requirements  where  risers  or  piping  penetrate

floors or walls  are  the  responsibility  of  the  installer. This  work

should be done only after all pressure testing is completed. The

fireproofing method used must accommodate pipe expansion and

contraction and the piping must be protected from abrasion and

chemical attack. The pipe insulation also must be maintained to

Outer 
Cabinet

Unit Insulation

Rise Stubout
Insulation

Ball 
Valve

Threaded 
Fitting

Flare 
Cap

Riser Knockout
Slot

Flexible 
Hose Kit

Riser Stubout
Insulation

Ball Valve

Riser

Coil

Baffle

Connection point to any factory
furnished and installed components.

Wrench

Swivel 
Connection

Back-up
Wrench

Ball Valve

CAUTION

Hose connection torque requirements are 350 in. lb +10/

–0 in. lb to prevent leaks.

P-Trap

Drain

Clamp

Drain Pan

Unit Insulation

Riser Knockout

Clamp

Riser 
Stubout

Unit Wall

Riser

Summary of Contents for 42S Series

Page 1: ...STRUCTION 32 APPENDIX B POTENTIOMETER ADJUSTMENT 35 APPENDIX C CONTROL OPERATIONS 36 APPENDIX D EVO ECM 4 SPEED ADJUSTMENT 41 START UP CHECKLIST FOR 42S SERIES FAN COIL AIR CONDITIONERS CL 1 SAFETY CO...

Page 2: ...angement should be verified against the order documents Should any discrepancy be found the local sales representative should be notified immedi ately so that proper action may be taken Should any que...

Page 3: ...tural support Due to variations in building construction floor plans and unit configurations each installation is different The actual step by step method of installation may vary from unit to unit H...

Page 4: ...ox lb per row of coil 1 79 2 63 3 45 4 09 4 09 4 39 COILS FPI 14 fins inch BLOWER qty 42SGA SH SU SGM SGS SM 1 1 1 1 1 1 1 1 1 42SJ 2 2 2 2 2 2 FILTERS Nominal Size in 1 in thick 12 1 2 x 24 1 4 16 1...

Page 5: ...14 356 8 203 14 356 6 152 14 356 10 254 17 432 1 1 2 38 1 1 2 38 14 356 04 12 305 06 18 457 10 254 18 457 16 406 12 305 20 508 1 25 2 51 18 457 08 12 305 10 22 559 16 406 22 559 8 203 18 457 16 406 24...

Page 6: ...6 Fig 4 Riser Chase Unit Width Riser Chase Depth All model sizes 5 1 2 141 Unit Depth Riser Chase Risers Unit Height Stack Unit...

Page 7: ...E DIMENSIONS in mm SIDE FRONT SUPPLY DOUBLE SUPPLY TOP SUPPLY SINGLE DIMENSIONS A B A B C D E F G H 03 14 356 8 203 14 356 6 152 14 356 10 254 17 432 22 1 8 562 22 1 8 562 14 3 4 375 04 12 305 8 203 0...

Page 8: ...to permit expansion and contrac tion of risers Coil connections to be at the center of the slots 11 See unit arrangements for supply and return air orientation 12 Dimensions are in inches Dimensions...

Page 9: ...1 Service Switch Optional NOTES 1 Units are fabricated of galvanized steel with a 16 gauge galvanized fan deck 2 All risers are insulated 3 Thermostats shipped loose for field installation 4 Risers ar...

Page 10: ...to permit expansion and contrac tion of risers Coil connections to be at the center of the slots 8 See unit arrangements for supply and return air orientation 9 Dimensions are in inches Dimensions in...

Page 11: ...9 Return Air Opening 10 Drain Knockout s Side Panels 11 Access Panel Control Box 12 Riser Supply and Return 13 Riser Drain 14 Isolation Ball Valves 15 Strip Heater Optional E Heat 16 Heat Limit Switch...

Page 12: ...ES 1 Units are fabricated of galvanized steel with a 16 gauge galvanized fan deck 2 All risers are insulated 3 Thermostats shipped loose for field connection 4 Risers are factory piped to coil with va...

Page 13: ...and control box are insulated 7 Riser length floor to floor 2 in 51 mm Maximum riser length is 119 in 3023 mm 8 Maximum riser size is 2 1 2 in 64 mm diameter If larger sizes are required please consul...

Page 14: ...16 406 4 102 NOTES 1 Plenum box adds 22 in 559 mm to unit height adds 26 lb 11 8 kg to unit weight and is factory installed 2 1 4 in closed cell insulation is standard for the plenum box 3 Side suppl...

Page 15: ...ensions in inches PANEL NO UNIT SIZE A 1 42SG SJ SU 03 04 15 5 06 08 19 5 10 12 23 5 42SM 14 16 20 29 5 2 42SG SJ 03 04 15 5 06 08 19 5 10 12 23 5 3 42SG SJ 03 04 15 2 06 08 19 2 10 12 23 2 PANEL NO 1...

Page 16: ...TE S a Dimensions in inches PANEL NO UNIT UNIT SIZE A 4 42SG SJ SU 03 04 15 1 06 08 19 1 10 12 23 1 5 42SG SJ 03 04 15 1 06 08 19 1 10 12 23 1 6 42SG SJ 03 04 16 7 06 08 20 7 10 12 24 7 PANEL NO 4 54...

Page 17: ...should never be lifted up or pulled down to meet the riser on the floor below or above 4 Install isolator pads beneath the four corners of unit if appli cable 5 Before anchoring the equipment in place...

Page 18: ...unit frame d After all units in a stack are anchored make unit to unit riser joints First center each coil to riser line within the expansion slot in the unit back panel Each riser joint must be in ve...

Page 19: ...dary arrangements Potential Universal Arrangement Unit Configurations Risers Three Locations The pre installed supply return and drain risers 2 pipe or 4 pipe applications can be oriented on any of th...

Page 20: ...taller Riser to Unit Installation Before making the riser joints the riser insulation must be pulled back away from the joint and protected from heat during the braz ing process Each riser joint must...

Page 21: ...bottom of the unit as shown in Fig 26 10 Push the rubber drain hose over the riser drain stubout Be careful not to bend the drain stubout 11 Adjust the hose clamp over the riser stubout and rubber hos...

Page 22: ...nly All risers are factory fabricated and shipped loose for field installation It is important that you identify all of the unit feature locations before proceeding with the installation see Fig 11 Un...

Page 23: ...ical 3 The plastic flare caps on the end of the riser ball valves should be removed and discarded 4 All mega stack units use reinforced braided stainless steel flexible hose kits for piping between fi...

Page 24: ...to withstand the total operating pressure both static and pumping head to which the system will be subjected Low temperature lead alloy solders such as 50 50 and 60 40 are normally not suitable Chille...

Page 25: ...th optional auxiliary electric heat is desired an additional aquastat is required If the valve package is field supplied the aquastat must be installed in a location where it will sense the water temp...

Page 26: ...ing However drywall secured with adhesive bonding alone is NOT recommended CONCEALED UNIT ENCLOSURE Concealed units are designed to have gypsum board or other types of wall board applied directly to t...

Page 27: ...y steam of water begins to escape close valve Vent release air slowly usually dripping water into drain pan in the process Make sure all service valves are open and that the motorized control valves i...

Page 28: ...ize themselves with the unit options and accesso ries and control sequence to understand the proper system opera tion All personnel should have a good working knowledge of general start up procedures...

Page 29: ...hould not be attempted by unqualified personnel The system must be complete and all components must be in operating condition BEFORE beginning water system balancing operations Each hydronic system ha...

Page 30: ...nd tag unit electrical service switch Check drain pan drain line and trap before initial start up and at start of each cooling season A standard type pipe cleaner for 3 4 in ID Inside Dimensions pipe...

Page 31: ...be replaced on a regular basis The time interval be tween each replacement should be established based on regular in spection of the filter and should be recorded in the log for each unit Refer to the...

Page 32: ...OUT CONSTRUCTION SIZE TYPE OF INSTALLATION TYPE 1 TYPE 2 TYPE 3e e Not recommended for Siamese Ditto Installation W x L in W x L in W x L in Single Unit and Siamese Ditto 03 04 96 5 7 8 x 15 5 1 8 x...

Page 33: ...Table D Short 79 in Cabinet 4 Pipe 42S Units a b c d NOTE S a CLEAR HEIGHT is the dimension from the floor to ceiling See Fig A of this appendix b The above charts allow 1 in tolerance in clear height...

Page 34: ...o Floor Clear Height Riser Length Block out Length Unit Unit Block out Width NOTE Riser Length Floor to floor dimensions 2 in maximum riser length of 115 in When riser length must exceed 115 in use 10...

Page 35: ...outputs high medium and low 5 High Speed Close high speed relay by applying 24 v to the high terminal Using a small screwdriver turn the VR3 poten tiometer so the meter measures 4 51 vdc This will se...

Page 36: ...REMOTE SHUTDOWN INPUT 1 Provides dry contact for signal to BAS system I O a Dry Normally Open b Wet Normally Open c Discrete Coil 2 When contact activated a Motor OFF b Actuator OFF c Electric Heat O...

Page 37: ...Fan Low Speed W1 HTG Heat Y1 CLG Cool W2 HT2 Heat Stage 2 Y2 CL2 Cool Stage 2 R 24V 24V Controller Power COS Changeover Sensor RAS Room Air Sensor Table F 0 10 Variable Airflow ECM CONNNECTION FUNCTIO...

Page 38: ...adjusted from 0 to 100 of the motor s factory programmed operating range Use voltmeter and airflow chart on control box cover to set values Adjusting the potentiometers requires the use of a Multi met...

Page 39: ...ll actuate and supply 24VAC to Pin 12 of connector CN5 When 0 10VDC is applied to HTG that control signal will passively be present at Pin 8 of the CN6 connector HTG LED shows GREEN Signal for 1st sta...

Page 40: ...40 APPENDIX C CONTROLS OPERATION CONT Fig H Typical Wiring Diagram NOTE Wiring diagram also available through QR code found on the unit serialized name plate label...

Page 41: ...lead of the meter to the high speed Flo1 terminal below the potentiometer 6 High Speed Using a small screwdriver turn the Flo1 potenti ometer so the meter measures 4 51 vdc This will set the ECM speed...

Page 42: ...s the right to discontinue or change at any time specifications or designs without notice and without incurring obligations Catalog No 04 53420024 01 Printed in U S A Form 42S 5SI Pg 42 9 22 Replaces...

Page 43: ...l supply voltage 8 Proper access provided for unit and accessories 37 Record ambient temperatures 9 Proper electrical service provided 38 Check all wiring for secure connections 10 Proper overcurrent...

Page 44: ...______________________________________________________ _________________________________________________________________________________________________________________________________________________...

Reviews: