1 - PRECAUTIONS

1.1 - Operating limits

1.1.1 - Cooling mode

The minimum recommended primary air supply 
temperature is 12°C when the unit is installed in a room 
with temperature 27°C (dry bulb) and 65% RH (relative 
humidity).

1.1.2 - Heating mode 

Carrier recommends that the supply air temperature is 

kept below 35°C in order to avoid the risk of stratification.

1.1.3 - Operating environment

The hybrid 36XB Air Terminal has been designed to operate 
in an ‘urban’ indoor atmosphere, which is a non-corrosive, 
dust-free and non-marine environment. The chemical 
concentrations given below must not be exceeded in any 
circumstances: 

• 

SO

2

 

< 0.02 ppm

• 

H

2

< 0.02 ppm

• 

NO, NO

2

 

< 1 ppm

• 

NH

3

 

< 6 ppm

• 

N

2

< 0.25 ppm

Do not install the unit in atmospheres which contain 

flammable gases, or acid or alkaline products. The copper/

aluminium air coil and the internal components could suffer 
irreparable corrosion. 

1.1.4 - Recommended water quality for water coils

Once installation is complete, then each year, it is 
recommend that the water is analysed for bacteria 
(detection of ferro-bacteria, H2S-producing and sulphate-
reducing bacteria) and chemicals (in order to avoid 
problems due to corrosion and scaling). 

The water circuit must include the elements required for 
water treatment: filters, additives, intermediate exchangers, 
purges, vents, isolation valve, etc., based on the results of the 
analysis.

The results of the analysis must correspond to the values 
given below:

• Total hardness in mmol/l: 

1 < mmol/l < 1.5

• Chloride [CL

-

]  

 

< 10 mg/litre

• Sulphate [SO

4

2-

 

< 30 mg/litre

• Nitrate [NO

3

-

]  

 

= 0 mg/litre

• Dissolved iron: 

 

< 0.5 mg/litre

• Dissolved oxygen: 

 

4 < [O

2

] < 9 mg/litre

• Carbon dioxide [CO

2

]   

< 30 mg/litre

•    Resistivity    

 

20 Ohm

·

m < Resistivity

 

 

   < 

50 

Ohm

·

m

•    pH   

 

 

6.9 < pH < 8

1.2 - Maintenance requirements

The installer must leave sufficient space around the unit to 

facilitate maintenance: Fig 1. The installer must also provide 
access to the control components, power connection and 
fresh air duct: Fig. 1.
Some components are accessed by opening the air diffusion 
grille.
During any intervention, it is essential that the safety system 
is put back in place: Fig. 6.

1.2.1 – Procedure for opening the grille.

The grille is held in place at two points, at each end of the 
diffuser in the supply air zone: Fig 2

•   Insert the special Carrier tool (ref: 36XB500085M-) in 

the third slot on the supply air side: Fig 10

• 

Pull downwards until the grille opens on the left-hand 

side and then carry out the same operation on the 
right-hand side: Fig 11

•   Remove the safety device.

To close the grille, the safety device must be put back in 
place and the grille pushed fully back in.

Note: The grille must only be opened with the Carrier tool 
specially provided: Fig.10 and 11.
If this instruction is not observed, Carrier cannot be held 
liable for any damage to the unit or to its appearance or 
injury to persons caused by incorrect handling.

1.3 - Delivery

Once received, check the condition of the equipment; 
if any damage caused during transport is observed, the 
resulting claims must be sent to the shipping company 

in writing. Only unpack when final installation is to take 

place, and do so as close as possible to the installation 
location. Do not place heavy tools on the package whilst 
waiting.

1.4 - Storage

The units will be delivered on a pallet, and must be stored 
in a sheltered, dry location.

1.5 - Supply voltage 230 V ± 10% - 50 Hz

Check that the supply voltage and frequency match those 
on the unit nameplate.

CAUTION: Carrier will invalidate the warranty if these 

points are not respected, or if modifications have been 

made to the original electrical connections.

2 - SAFETY CONSIDERATIONS

NOTE: before performing any work on the unit, disconnect 
the power to the unit and to any accessories.

2.1 - General

Installing, commissioning and servicing of the various 
system components (unit, control system, hot and cold 
water system, air distribution system) can be dangerous 
unless certain aspects of the installation, such as the 
presence of mains electricity or the presence of hot or cold 
water in the air treatment equipment, are taken into 

account. Only appropriately trained and qualified 

technicians and installers are authorised to install and 
commission this equipment.

During servicing work, it is essential to apply all 
recommendations and instructions given in the 
maintenance manuals, on labels or in the instructions 
delivered with the equipment, and to comply with any 
other relevant instructions.

Summary of Contents for 36XB

Page 1: ...36XB Translation of original document Hybrid Air Terminal INSTALLATION OPERATION AND MAINTENANCE INSTRUCTIONS...

Page 2: ...2 5 Conformity 8 3 InstALLAtIon oF the UnIt 8 3 1 Coordination between the unit and suspended ceiling 8 3 2 Installation procedure 9 3 3 Removal procedure 9 4 CoMPonents 9 4 1 Fan motor assemblies 9...

Page 3: ...3 1 60 cm 60 cm 3 2 4 5 6 7 9 10 8 1 3 11...

Page 4: ...4 13 14 12 15...

Page 5: ...5 16a 18 17b 17a 16b...

Page 6: ...ting multiple units to the same drainage manifold 9 Condensate drain pipe 9a Siphon height greater than 50mm 10 Procedure for opening the grille 11 Procedure for opening the grille 12 Removal of the e...

Page 7: ...ure for opening the grille The grille is held in place at two points at each end of the diffuser in the supply air zone Fig 2 Insert the special Carrier tool ref 36XB500085M in the third slot on the s...

Page 8: ...evices connected to it The wiring of the components which make up the different control systems and the communication buses must be carried out in accordance with the latest rules and regulations by p...

Page 9: ...on prepared connect the piping Carrier recommends using the flexible hoses which can be provided as accessories Each hose is fitted with a 1 2 gas union nut depending on the model Remember to fit a ga...

Page 10: ...e refit the assembly in the reverse order to removal Note To clean the condensate pan refer to the relevant local legislation 4 4 Fresh air connection spigot This is fitted in place from inside the un...

Page 11: ...e valve coupling may be fitted with a hot cold changeover switch which must not be removed Fit the new valve body to the coil fit new gaskets Refit the condensate pan coil assembly Refit the actuators...

Page 12: ...No 10005 09 2014 Replace No New Printed in the European Union The manufacturer reserves the right to change the product specifications without notice...