
Carmanah Technologies Corp. | 250 Bay St, Victoria, BC V9A 3K5, Canada | 1.250.380.0052 |
35
SPEEDCHECK-15/18 USER MANUAL
6.0 COMMISSIONING CHECKLIST
6.0 Commissioning Checklist
After installing and programming the system using SpeedCheck Manager software, the following commissioning
verification checklist helps ensure that everything is working as it should be and that your flashing beacon is ready
to serve the public for many years of reliable and sustained operation.
For All Versions:
All settings are correct using the SpeedCheck Manager Software, including slow down options, external
beacon options, calendar-based scheduler, and data logging settings.
“Roll up” sequence occurs and LEDs light upon startup. External output loads such as beacons power up
as expected.
SpeedCheck enclosure is aimed properly in the correct direction toward oncoming traffic lanes.
For Solar Versions:
Before installing battery, confirm it is in a good state of health.
The solar panel is securely mounted with hardware fully tightened.
Ensure there is a green light showing on the charge controller to confirm solar charging is taking place.
System has clear sky access and no removal of obstructions is required.
Note the possibility for nearby foliage to eventually shade the solar panel. If so, set a reminder to inspect
later.
Solar panel pointed south (or wherever custom instructions indicate).
Cabinet door is fully closed
with an audible “click”.
For AC Versions:
If present, cabinet door is fully closed.
Verify all fuses are intact.
For
StreetHub™ remote connectivity versions:
Remote systems are visible in web interface.