4
4
4-3
4-3
Installation > Check Items when Turning OFF the Main Power
Installation > Check Items when Turning OFF the Main Power
Checking the Contents
[1] Punch unit X 1
[2] Punch dust box unit
X 1
[3] Punch dust box
frame unit X 1
[4] Operation label X 1
[5] Jam recovery label X 1
[6] Punch map label X 1
[7] Screw (RS tightening;
M4X8) X 1
Since [2] and [3] are integrated at the shipment, separate them to install when unpacking.
F-4-3
Check Items when Turning OFF the Main Power
Check that the main power is OFF.
1) Turning off the Main Power Supply Switch of the Host Machine.
2) Check that the display on the Control Panel and the Main Power Supply Lamp are turned
off before disconnecting the outlet.