4 / 11
FIG 4-1
AC cable stripping requirements
Step 2: Insert the conductor into the suitable ferrule and tighten them firmly, and then assemble all parts together.
NOTE: ferrule is not provided.
1.connector body;2. sleeve;3. sealing ring 2;4. sealing ring 1;5. claw;6. pressing nut.
FIG 4-2
AC Connector
NOTE
:
Please select the appropriate sealing ring according to the actual cable outer diameter and the table below
:
ModelSealing Ring 1Sealing Ring 1+ Sealing Ring 215kW / 17 kW / 20 kW18-22mm13-18mm23 kW / 25 kW18-26
mm13-18mm
Step 3: Insert the assembled plug into the AC socket on the inverter (please refer to the FIG 4-4). Tighten the connection by
aligning the arrow on the plug with the circular hole on the socket.
NOTE: Please use the hex wrench provided with the inverter to tighten it.
L3
N
PE
L2
L1
FIG 4-3
Internal structure of AC connector FIG 4-4
AC plug connection
A
B
L1
L2
L3
N
PE
C
D
D-5mm
Description
Specification
A Cable Outer Diameter
15kW / 17 kW / 20 kW:13-22mm
23 kW / 25 kW:13~26mm
B
Cross Sectional Area of Copper
Conductor
15kW / 17 kW / 20 kW :5x4~16mm
2
(REC 6mm
2
)
23 kW / 25 kW :5x6~16mm
2
(REC
10mm
2
)
C
Stripping Length of Copper
Conductor Insulation
12mm
D
Stripping Length of Cable
Sheath
75mm
Note:
The ground wire (PE) is at least 5mm longer than the phase line.