ANNEX A: ALTERNATIvE MOUNTINg METhODS

MOUNTINg METhOD A: CLAMpINg

MOUNTINg METhOD B: INSERTION SySTEMS

MOUNTINg METhOD C: CENTER MOUNTINg METhOD 
wITh ThIRD pARTy TRACkER

|3

|3

|8

|10

ANNEX B: ALTERNATIvE gROUNDINg METhODS

|11

All the basic requirements of the main installation  

manual should apply to the alternative mounting  

methods, unless otherwise speciied.

Design load and safety factors will be determined by 

the racking suppliers or professional engineers. For 

detailed information, please follow local structural 

code or contact your professional structural 

engineer.

MOUNTINg METhOD A
CLAMpINg

·  The mounting method has been qualiied by 

Canadian Solar Inc. and certiied by VDE and CSA.

·  Top or bottom clamping methods will vary and 

are dependent on the mounting structures. Please 

follow the mounting guidelines recommended by 

the mounting system supplier.

·  Each module must be securely fastened at a 

minimum of four points on two opposite sides. 

The clamps should be positioned according to 

the authorized position ranges deined in table 
A. Install and tighten the module clamps to the 

mounting rails using the torque stated by the 

mounting hardware manufacturer. M8X1.25-
Grade8.8 bolt and nut are used for this clamping 
method. Tightening torques should be within 
17~23 Nm (12.5~17.0 ft-lbs) for M8 coarse 
thread bolts, depending on the bolt class. For 

the bolt grade, the technical guideline from the 

fastener suppliers need to be followed.Different 
recommendations from speciic clamping 
hardware suppliers should prevail. System 

designer and installer are responsible for load 

calculations and for proper design of support 

structure. 

·  Canadian Solar Inc.’s warranty may be void in cases 

where improper clamps or unsuitable installation 

methods are found. When installing inter-modules 
or end-type clamps, please take the following 

measures into account:

        Do not bend the module frame

        Do not touch or cast shadows on the front glass

        Do not damage the surface of the frame

        Ensure the clamps overlap the module frame by     

at least 5 mm (0.2 in)

        Ensure the clamps overlap length is at least 40 

mm (1.57 in)

        Ensure the clamp’s thickness is at least 3 mm

·  Clamp material should be anodized aluminum 

alloy or stainless steel.

·  Clamp positions are of crucial importance for 

the reliability of the installation. The clamp 

centerlines must only be positioned within the 

ranges indicated in table A, depending on the 

coniguration and load. 

·  For conigurations where the mounting rails run 

parallel to the frame, precautions should be taken 

to ensure the bottom lange of the module frame 
overlaps the rail by 15 mm (0.59 in) or more.

ANNEX A: ALTERNATIvE MOUNTINg METhODS

Min. 5 mm overlap

Min. 3 mm thickness

Min. overlap length 
40 mm

ANNEX C : MEChANICAL AND ELECTRICAL RATINgS

|13

ANNEX D: MODULE CLEANINg gUIDELINES

|16

AMENDED EDITIONS AND DATES

|17

6

Min. 15 mm 

overlap width

Summary of Contents for CS6P-P Series

Page 1: ...INSTALLATION MANUAL ANNEX OF STANDARD SOLAR MODULE For professional use only...

Page 2: ...0 ft lbs for M8 coarse thread bolts depending on the bolt class For the bolt grade the technical guideline from the fastener suppliers need to be followed Different recommendations from speciic clampi...

Page 3: ...50 mm Maximum Load Uplift load 2400 Pa Downforce load 5400 Pa CS6U xxxp and CS6U xxxM Use four clamps on the long side Mounting rails run perpendicularly to the long side frame A1 A1 A1 A1 Use four cl...

Page 4: ...xxxM Use four clamps on the long side Mounting rails run perpendicularly to the long side frame Use four clamps on the short side Mounting rails run parallel to the long side frame A1 range 0 239 mm M...

Page 5: ...ting system supplier Each module must be securely maintained through all its length on two opposite sides Install and tighten the insertion profiles to the support structure using the hardware and ins...

Page 6: ...be placed below the module Use two clamps on the support bar Maximum Load Uplift load 2400 Pa Downforce load 5400 Pa Use two insertion proiles running parallel to the long side frame Maximum Load Upli...

Page 7: ...Clamp installation instructions D PanelClaw Inc Standard Claw integrated grounding PanelClaw Grizzly Bear FR Gen II mounting system Grizzly Bear FR Gen II Installation Manual 9910010 Rev A E Array ech...

Page 8: ...53 15 00 Table 1 Mechanical And Electrical Ratings under STC ANNEX C MEChANICAL AND ELECTRICAL RATINgS Module Type Maximum power pmax w Operating voltage vmp v Operating current Imp A Open Circuit vol...

Page 9: ...9 8 94 39 1 9 59 15 00 CS6k 290MS 290 0 32 1 9 05 39 3 9 67 15 00 CS6k 295MS 295 0 32 3 9 14 39 5 9 75 15 00 CS6k 300MS 300 0 32 5 9 24 39 7 9 83 15 00 CS6k 305MS 305 0 32 7 9 33 39 9 9 91 15 00 This...

Page 10: ...ss surface OpERATION pREpARATION Noticeable dirt must be rubbed away by gentle cleaning implement soft cloth sponge or brush with soft bristles Ensure that brushes or agitating tools are not abrasive...

Reviews: