EN-Rev IM/GN-AM-EN/A5 Copyright © June 2016. Canadian Solar Inc.
www.canadiansolar.com
|
11
10
|
CS6X-xxxp, CS6X-xxxM, CS6U-xxxp and CS6U-xxxM
Use two insertion proiles running parallel to the long
side frame.
Maximum Load:
Uplift load ≤ 2400 Pa
Downforce load ≤ 5400 Pa
Use two insertion proiles running parallel to the
short side frame. An additional support bar should
be placed below the module. Use two clamps on the
support bar.
Maximum Load:
Uplift load ≤ 2400 Pa
Downforce load ≤ 5400 Pa
Use two insertion proiles running parallel to the long
side frame.
Use two insertion proiles running parallel to the
short side frame.
Maximum Load:
Uplift load ≤ 2000 Pa
Downforce load ≤ 2000 Pa
Maximum Load:
Uplift load ≤ 2400 Pa
Downforce load ≤ 4000 Pa
CS6k-xxxp, CS6k-xxxM, CS6p-xxxp, CS6p-xxxM, CS6v-xxxp and CS6v-xxxM
Use two insertion proiles running parallel to the
short side frame. An additional support bar should
be placed below the module. Use two clamps on
the support bar.
Maximum Load:
Uplift load ≤ 2400 Pa
Downforce load ≤ 5400 Pa
Use two insertion proiles running parallel to the long
side frame.
Maximum Load:
Uplift load ≤2400 Pa
Downforce load ≤ 2400 Pa
Use two insertion proiles running parallel to the short
side frame.
Maximum Load:
Uplift load ≤ 2400 Pa
Downforce load ≤ 4000 Pa
Use two insertion proiles running parallel to the short
side frame. An additional support bar should be placed
below the module. Use two clamps on the support bar.
Maximum Load:
Uplift load ≤ 2400 Pa
Downforce load ≤ 5400 Pa
MOUNTINg METhOD C:
CENTER MOUNTINg METhOD wITh ThIRD
pARTy TRACkER
· Canadian Solar modules can be mounted with third
party trackers as described below. All the require-
ments of the main manual and related tracker
installation manual should apply to the tracker
installation method. For detailed installation
instructions, please refer to the related third party
installation manual.
· The mounting method has been qualiied by Canadian
Solar Inc. and certiied by VDE and CSA.
CS6A-xxxp and CS6A-xxxM
Mounting Rail