1-1
Section 1. Preparation and Siting
These guidelines apply to several different Campbell Scientific weather stations.
1.1 Installation Tasks
1.1.1 Indoors
•
Immediately upon receipt of your shipment…
⇒
Open shipping cartons.
⇒
Check contents against invoice. Contact CSI immediately about any
shortages.
•
Several days prior to the planned installation date…
⇒
Collect tools and site information (Section 1)
⇒
Assemble datalogger, communications device, and power supply in
enclosure (Section 3)
⇒
Install datalogger support software on PC (Section 5)
⇒
Establish communications between the datalogger and the PC
(Section 5)
⇒
Program datalogger, test sensors, and retrieve data (Section 5)
⇒
Trial run the tower / tripod installation, assembling as much as
possible (Section 2)
⇒
Repackage equipment for transport to the field site
1.1.2 Outdoors
•
Locate suitable site (Section 1)
•
Prepare tower or tripod base (Section 2)
•
Tripod and UT10 (3 meter tower) tower stations:
⇒
Raise tripod or tower (Section 2)
⇒
Install instrumentation enclosure (Section 3)
⇒
Install sensors (Section 4)
Summary of Contents for ET106
Page 4: ...This is a blank page...
Page 20: ...Section 2 ET Tower Installation 2 6 This is a blank page...
Page 34: ...Section 3 ET Instrumentation Installation 3 14 This is a blank page...
Page 44: ...Section 5 ET Software Installation 5 2 This is a blank page...
Page 50: ...Section 6 Maintenance and Troubleshooting 6 6 This is a blank page...
Page 51: ...This is a blank page...