MODULE  SELECTION

 

Please refer to the detailed electrical characteristics from the product data sheet.

 

Only wire modules of the same type and performance class. This is the only way to ensure maximum 

yields and system operation that is secure and free from disruptions.

 

 

GUIDELINES

 

Modules cannot be operated for more than 90 consecutive days under open-circuit or short-circuit 

conditions. Consult with Calyxo if you are unable to uphold this time frame.

 

 

All  of  the  components  attached  to  the  system  need  to  have  an  operating  window  that  matches  the 

‘Maximum  Power  Point’  (MPP).  The  components  need  to  be  capable  of  operating  at  the  MPP  at  all 

times.

 

 

SAFETY  FACTORS

 

Under normal conditions, a photovoltaic module is likely to experience conditions that produce more 

current and/or voltage than reported at standard test conditions.  Accordingly, the values of ISC and 

VOC marked on this module should be multiplied by a factor of 1.25 when determining component 

voltage ratings, conductor ampacities, fuse sizes, and size of controls connected to the PV output. Refer 

to Section 690-8 of the National Electrical Code for an additional multiplying factor of 125 percent (80 

percent derating) which may be applicable. 

For a module the multiplying factor at conditions of an irradiance of 125 mW/cm2, AM 1.5 spectrum, 

and a cell temperature of minus 10°C (plus 14°F) for VOC and plus 75°C (167°F) for ISC is to be 

determined and this factor is to be indicated in the instructions. Thus, it is advised to take a security 

factor of 1.25 for the parameters listed below into account, in accordance with IEC 61730-1 Paragraph 

12.7:

 

 

Determining the voltage measurement values    (V

 

) of components

 

 

Determining the current measurement values        (I

 

 

Determining fuse sizes

 

OC

 

SC

) of conductors

 

 

Measuring control systems to the outputs of the solar modules.

 

 

At any rate, the applicable national regulations for installing electrical systems need to be observed.  

 

6.5.1

 

Series connection

 

Only wire modules of the same type and performance class. Please take special note of the positive 

sorting and the tolerance ranges for V

oc  

and V

MPP  

indicated in the data sheet of the respective CX series 

module.

 

Series connection of the modules is only permitted up to the maximum system voltage provided in the 

respective currently applicable data sheet.

 

When installing the modules, take into account all working conditions and relevant technical regulations 

and standards. Doing so ensures that the maximum system voltage, including the required safety 

margins, are not exceeded.

 

When determining the string length, also take the voltage limit of the inverter into account.

 

Summary of Contents for CX1

Page 1: ...OPERATING MANUAL CX SERIES REV2 0 May 2017 EN EU USA Canada...

Page 2: ...S 7 4 MECHANICAL SPECIFICATIONANDDRAWING 10 5 ELECTRICAL SPECIFICATION 11 6 INSTALLATION 12 6 1 MOUNTING 12 6 2 MOUNTING VARIANTS 14 6 3 INSTALLATION SITE MODULE ORIENTATION 15 6 4 AVOIDINGSHADE 16 6...

Page 3: ...all the following requirements and instructions in order to be able to make full use of the performance capacity of Calyxo solar modules Ensure that the installation operational and maintenance work i...

Page 4: ...cted to a control device such as an inverter or a chargecontroller Calyxo solar modules are developed and constructed in keeping with the latest technological developments When used properly in accord...

Page 5: ...ion Physically disconnecting a closed electrical circuit could cause electrical voltage and currents such as electric arcs to arise These could result in life threatening injuries The risk increases w...

Page 6: ...concentrators such as mirrors or lenses or any other means to artificially concentrate light to increase the power output of the modules Doing so can damage the modules and shall render the extended w...

Page 7: ...key to safely handling glass is correctly selecting and using personal protective equipment Always ensure your own safety and wear safety goggles safety shoes and cut resistant gloves Gauntlet gloves...

Page 8: ...revention at constructionsites If you intend to install the modules on a rooftop or at a height observe the specialist regulations set out by the roofing trade Ensure proper fall protection since fall...

Page 9: ...uest documentation an acceptance report and an inspection report for the PV system with the minimum requirements set out by IEC DIN EN 62446 or VDE 0126 23 from the installer Store these reports toget...

Page 10: ...iew CX3pro Figure 3 Rear side view CX1 Figure 4 Front side view A CX3 9 0 mm CX3pro 7 0 mm CX1 9 0 mm CX4 7 0 mm Specification CX1 CX3 CX3pro CX4 Length 1200 mm Width 600 mm Weight 12 kg Structure Gla...

Page 11: ...t Current I sc A 10 Open Circuit Voltage V oc V 10 Current at Maximum Power I mp A 10 Voltage at MaximumPower V mp V 10 Maximum System Voltage 1000V IEC 600V UL Design Load 2400Pa IEC 50lb ft UL STC 1...

Page 12: ...ditions irradiance of 100 mW cm2 AM 1 5 spectrum and a cell temperature of 25 C 77 F TECHNICAL DATA Additional data including details of the electrical characteristics for the CX series power classes...

Page 13: ...cture that corresponds to the required statics and the local wind snowloads that can be properly fastened in the ground on the roof or on the facade that can transfer forces on the modules to the asse...

Page 14: ...lication The recommended minimum standoff height is 3 25 in 82 55 mm Modules used in UL Listed rooftop applications must be installed with approved mounting systems If alternate mounting means are emp...

Page 15: ...that no direct contact is made between glass and metal Use a suitable silicone free rubber support between the modules andclamps Clamp width figures 7 to 8 70 0 mm A minimum lateral distance between...

Page 16: ...ny point THEFOLLOWINGMOUNTINGVARIANTSARE POSSIBLE Substructure lateral beneath the module with two clamps per module side figure 7 Substructure diagonal beneath the longer sides with two clamps per mo...

Page 17: ...is only splash proof Solar modules are not explosion proof equipment Do not install the modules in the proximity of highly flammable gases and vapors such as gas containers petrol stations or near ope...

Page 18: ...angles of inclination less than3 longitudinal side of the module from the eave it needs to be ensured that adherent contamination is removed by sufficient precipitation or through regular manual clean...

Page 19: ...dry place The packaging is not weather resistant Ensure that even at low temperatures and or solar radiation of over 1000 W m the maximum open circuit voltage of the wired modules does not exceed the...

Page 20: ...a module the multiplying factor at conditions of an irradiance of 125 mW cm2 AM 1 5 spectrum and a cell temperature of minus 10 C plus 14 F for VOC and plus 75 C 167 F for ISC is to be determined and...

Page 21: ...rotected against reverse currents from the rest of the system with a string diode Within the scope of DIN VDE 0100 712 2016 10 diodes are no longer permitted as reverse currentprotection Usually each...

Page 22: ...ed with the module Install functional grounding for the solar power system when you are installing it in a country or a system in which functional grounding is necessary orprescribed Direct grounding...

Page 23: ...pro CX4 MC4 connectors of part numbers PV KST4 PV KBT4 CX1 feature MC3 connectors of part numbers PV KST3 PV KBT3 Please note the following when selecting connecting cables and connectors Only use pr...

Page 24: ...otected from dirt and moisture The connectors are not lying on a water collecting surface and are firmly connected toone another All necessary security and functional inspections have been carried out...

Page 25: ...te evening Do not wear any conductive pieces or clothing Never enter the installation area alone and without protection We recommend commissioning a specialist company with this work Ask your installe...

Page 26: ...om the top of the module in the following sequence Rinse off coarse soiling dust foliage etc from the modules with lukewarmwater Moisten stubborn soiling and carefully removeit Use lukewarm water and...

Page 27: ...cle and environmentally sustainable disposal of electrical and electronic devices is to be understood as a special law under the scope of the general German waste legislation which is laid out in the...

Page 28: ...information is always accessible and corresponds to the latest status However Calyxo assumes no responsibility for its use or for injuries to patentsor the rights of third parties that may result from...

Page 29: ...11 Notes...

Reviews: