background image

7

 

Boiler installation

Logano GC 144 II – 6 720 808 893 (2017/02)

11

Gas carrying capacity (

 chapter 16, page 29)

1

Maximum gas supply volume in cubic feet per hour, based on 
a specific gas weight of 0.60 and a gas pressure of 0.5 psi or less 
and a pressure gradient corresponding to a water column of 
0.3 inches.

Disconnect the boiler with the manual shut-off valve and physically 
separate the boiler from the gas piping if the gas piping system is 
pressure tested with a test pressure greater than 1/2 psi.

If the gas supply pipe system is pressure tested at a test pressure of 1/2 
psi or less, it is sufficient to disconnect the boiler from the gas pipe 
system by closing the manual shut-off valve. 

Use only sealant that is resistant to corrosion by LPG for pipe 
connection. Only a small amount of sealant must be applied to the 
external thread of the pipe connections.

If you wish to convert the boiler to propane, please contact Buderus for 
the required conversion components. Do not attempt to convert the 
boiler without the approved Buderus propane conversion parts and the 
relevant technical documentation. The technical documentation is 
included with the propane conversion parts.

7.4.2

Installation at high altitudes

The boiler is designed for installation at altitudes below 8500 feet above 
sea level.

7.5

Filling heating system and checking for leaks

The boiler is tested for leaks at the factory. Before placing the heating 
system into use, check the entire system for soundness to avoid leaks 
occurring during operation.

Water treatment

Carry out the leak test at 1.5 times the normal operating pressure and as 
specified by the local codes as follows:

▶ Close connection for relief valve (

 figure 14, page 12) and all other 

open connections with plugs.

▶ Disconnect the expansion tank from the system by closing the 

expansion tank shut-off valve.

▶ Open mixing and shut-off valves on hot water side.
▶ Fill boiler slowly with water from the feed water connection.
▶ Open automatic vents slightly to allow the air to escape.
▶ Slowly fill heating system. Observe pressure display on pressure 

gauge during this process.

▶ Check connections and pipes for leaks.
▶ Bleed heating system through the bleed valves on the radiators or 

other air elimination components or high points in the system.

▶ If the pressure drops during air bleeding, water must be added.
▶ Install pressure relief valve (

 figure 14, page 12).

Nominal 
diameter 
of iron 
pipe 
(inches)

Equivalent lengths for pipe fittings in feet
Pipe fitting type
90°-
angle

T-piece

Shut-off 
valve

Gas shut-off

Equivalent lengths in feet

1/2

1.4

2.7

0.3

0.80

3/4

2.1

4.1

0.5

1.25

1

2.6

5.2

0.6

1.6

1 1/4

3.5

6.9

0.8

2.15

1 1/2

4.0

8.0

0.9

2.50

Table 6   Equivalent lengths for pipe fittings

Length of 
pipe in 
feet

Gas pipe supply volume in cubic feet of gas per hour

1

1/2

3/4

1

1 1/4

1 1/2

10

132

278

520

1060

1600

20

92

190

350

730

1100

30

73

152

285

590

890

40

63

130

245

500

760

50

56

115

215

440

670

75

45

93

175

360

545

100

38

79

160

305

480

150

31

64

120

250

380

Table 7   Gas pipe supply volume

If the installation location is over 8500 feet above sea 
level, please contact Buderus for another product option 
as the GC 144 II is not approved above 8500 feet 
operation.

NOTICE: 

System damage due to dirt.

If the boiler is assembled and not in use, note the 
following:

▶ Protect the boiler connections from dirt by closing 

the connections.

Have the water analyzed before filling the heating 
system. The water may require treatment as a result of 
the analysis. 
Please consult the local water supply company if the 
water is extremely hard or has a pH level below 7.0.

NOTICE: 

System damage due to overpressure during 

the leak test. Pressure, control or safety components 
may be damaged by high pressure.
▶ Before conducting the leak test make sure that no 

pressure, control or safety components that cannot 
be disconnected from the water compartment of the 
boiler are installed.

Maximum operating pressure

Maximum test pressure

30 psi

(based on supplied relief 
valve)

45 psi

58 psi

(with special relief valve)

75 psi

Table 8   Pressure Test

Summary of Contents for GC144/3

Page 1: ...wed precisely Contact a qualified service company service provider or the gas company if support or additional information is required CAUTION Before placing this boiler in operation observethesafetyinstructionsofthisinstalla tion and maintenance manual CAUTION The operating manual is a component of the technical documentation handed over to the operator of the heating system Discuss the instructi...

Page 2: ...ings for combustion air supply and venting 12 9 Requirements for connection to chimneys or venting systems 13 10 Flue pipe installation 13 11 Placing the heating system in operation 14 11 1 Starting up the GC 144 II 15 11 1 1 Prepare pressure measurement 15 11 1 2 Turning on heating system 16 12 Final start up procedures 16 13 Start up protocol 19 14 Taking the heating system out of operation 20 1...

Page 3: ...entilation or combustion air availability may cause dangerous flue gas leaks or formation Make sure that inlets and outlets are not reduced in size or closed If faults are not corrected immediately the boiler must not be operated until all faults have been corrected Inform the system operator and or owner of the fault and the danger in writing Whenworkingonthefluegasventingequipmentorventdamperlea...

Page 4: ... Gas Code ANSI Z 223 1 If specified by the local regulatory authorities the heating system must comply with the regulations of the Standard for Controls and Safety Devices for Automatically Fired Boilers ANSI ASME CSD 1 Carbon monoxide detectors must be installed as specified by the local regulations The boiler must be serviced annually chapter 15 page 20 2 3 Boiler Operating Conditions The hot wa...

Page 5: ...oiler 2 3 8 RK 1 VK 1 GAS EL GAS 6 720 804 440 02 1T Boiler size Boilerinput A B Vent connection II Min relief valve capacity Number of Orifices Water volume Dry weight Btu hr Inches Inches Inches lb hr Qty US Gal lbs 18 3 74000 13 1 8 8 5 62 2 2 4 228 25 4 103000 16 3 4 8 2 3 5 86 3 2 9 287 32 5 132500 20 3 8 9 1 2 6 110 4 3 4 349 5 Table 3 Dimensions specs for GC 144 II For the size and dimensio...

Page 6: ...iler cart Move boiler to desired location Component Qty Packaging method Boiler complete 1 1 palette B kit components 1 1 4 supply manifold 30 psi relief valve long shank boiler drain pressure temperature gauge 90 elbow 1 x 1 NPT 90 elbow 1 x 1 NPT 90 elbow NPT nipple nipple1 NPT nipple 1 NPT 1 1 cardboard box1 1 On Palette Vent damper 1 1 cardboard box1 Circulator 1 1 cardboard box1 Technical doc...

Page 7: ...ed on a flammable base but not on carpet Fig 7 Required clearances in the boiler room 1 Recommended service clearances 2 Required minimum clearances 3 Burner tray access door with combustion air opening as required per ANSI Z 223 1 6 2 Leveling the boiler Level the boiler in both horizontal directions Level the boiler using a level and place small wedges not supplied for leveling purposes 7 Boiler...

Page 8: ... low water cut off must be installed during installation of the boiler and placed above the water level in the boiler without any means of shutting the water off between the boiler and low water cut off figure 8 NOTICE System damage due to high temperature variations in the heating system If the boiler is operated in connection with a refrigerationsystem makesurethatthepipesforthe refrigerated liq...

Page 9: ...boiler must be grounded as specified by the regulations of the relevant local authorities otherwise follow the regulations of the National Electrical Code ANSI NFPA 70 The boiler is fully functional with the factory installed aquastat and the field installed vent damper and heating system circulation pump Power supply connection Install incoming power to the boiler per local and state codes Instal...

Page 10: ...er jacket if required by the local code We recommend installing a manual shut off valve in the main gas pipe to the boiler The gas pipe must be fastened outside the boiler The local codes must be observed during installation of the gas piping connections otherwise the regulations of the National Fuel Gas Code ANSI Z 223 1 must be followed Install gas piping without any undue stress on the piping T...

Page 11: ...feed water connection Open automatic vents slightly to allow the air to escape Slowly fill heating system Observe pressure display on pressure gauge during this process Check connections and pipes for leaks Bleed heating system through the bleed valves on the radiators or other air elimination components or high points in the system If the pressure drops during air bleeding water must be added Ins...

Page 12: ...om the outer edge of the opening The shortest dimension of all inlet and outlet openings must not be less than three inches Total air supply from outside the building Make sure that the boiler room has two permanent openings one of which must not be more than 12 inches from the ceiling and the other must not be more than 12 inches from the floor of the boiler room calculated from the outer edge of...

Page 13: ...ain turned off All unused openings of the common system must be sealed Inspect the venting system to ensure that it has the correct dimensionsandlongitudinalinclination Makesurethatthesystemis not blocked leaking corroded or has any other faults that cause it to operate improperly Ifnecessary closealldoorsandwindowsinthebuildingandalldoors between the space in which the heating systems that remain...

Page 14: ...1 Placing the heating system in operation The burner and gas train integrated in the boiler have been tested at the factory as described in ANSI Z 21 13 to ensure safe operation of the heating system and verify specific performance indicators Preparing for operation Set the room thermostat optional to the lowest setting 4 3 2 1 5 6 7 6 720 804 440 16 1T 1 2 6 720 804 440 17 2T All connection point...

Page 15: ...mentporton the gas valve Install pressure measuring nipple and attach a pressure gauge to measure the orifice pressure Open gas shut off Fig 20 Gas valve 1 ON OFF knob shown in ON position 2 Screw plug for gas pressure measurement port 3 Screw plug for orifice measurement port 4 Ignition gas line connection Main gas orifice identification Boiler size 18 25 32 Natural gas 285 275 270 LP 180 175 170...

Page 16: ... Fig 23 Gas valve 1 ON OFF knob shown in ON position Checking gas supply pressure Check the gas supply pressure while the boiler is operating The connectionpressurefornaturalgasmustbebetween4 7 and10 5 W C For propane gas LP it must be between 11 and 13 W C If thegaspressureisinthecorrectrange recordthemeasuredvaluein the start up protocol then continue with the next step If the supply pressuredoe...

Page 17: ...s shut off The main burner flame figure 25 and the ignition flame are extinguished After no more than six 6 seconds the main gas solenoid valve on the gas valve must close with an audible noise If the gas valve does not operate correctly turn ON OFF knob on the gas valve clockwise to the OFF positionimmediately Closethemaingasshut offanddisconnectthe heating system from the main power source and c...

Page 18: ...OFFposition Disconnectthe heating system from the power source and turn thermostat to its lowest setting Seal leaks Repeat all steps in this paragraph Carefully wipe away the soapy water to prevent corrosion caused by the alkaline content of the soap Check the position of the vent damper The damper must be fully open vertical When burner is on flue gases must not escape from the vent hood Fig 27 C...

Page 19: ...tion Start up procedure Remarks or measured values 1 Type of gas Natural gas LP 2 Has the leak test been completed 3 Check combustion air inlet and outlet openings and flue gas connection 4 Check the equipment correct orifices See below and convert gas type if necessary 5 Fill boiler with water and bleed complete heating system 6 Measure gas supply pressure flow pressure inches W C 7 Measure manif...

Page 20: ... 15 2 Testingthefluesystem includingcombustionair air inlets and Ventilation openings Check the venting system including the combustion air inlet and outlet openings All faults must be repaired immediately Make sure that the combustion air feed and the inlets and outlets are not blocked at any point 15 3 Inspection of the boiler and burner Visually check the boiler and burner for external dirt If ...

Page 21: ...1 Flame rises to 1 above sensor 2 Ignition flame Remove the safety screw on the adjustment screw for the igniter figure 24 page 17 Turn the inner adjustment screw clockwise to reduce the size of the ignition flame and counterclockwise to increase it After completed adjustment replace the safety screw figure 24 page 17 If the flame is too small the pilot orifice needs cleaning figure 39 page 23 If ...

Page 22: ... 1 Screw nuts two 2 Screws on gas manifold on top of gas valve four Remove four 4 screws from gas manifold on top of gas valve Remove two 2 screw nuts on burner tray and take out the tray Fig 36 Remove top cover Remove 4 screws on sides of the top cover and lift off Remove top boiler insulation Unscrew cleaning cover from the venting manifold Cover control with foil to prevent entry of metal dust ...

Page 23: ...ontinue to ventilate boiler room well Install burner Reattach boiler jacket Fig 37 Clean out the gas passages 1 Cleaning brush 2 Insulation 3 Foil Fig 38 Wet cleaning boiler 15 6 Cleaning the burner Remove burner chapter 15 5 1 page 22 Check burner rods for dirt If necessary clean burner as described below Unscrew ignition burner unit from burner Disconnect ignition gas line from ignition burner u...

Page 24: ...g final checks Placeboilerinoperationasdirectedin Placingtheheatingsystemin operation chapter 11 page 14 Follow instructions in Final start up procedures Test low water alarm Check area around boiler for hazards Completethemaintenanceprotocoltoconfirmthatallmaintenacework has been conducted Sign the maintenance protocol and discuss it with the owner of the heating system Be careful not to damage t...

Page 25: ...er page 20 4 Cleaning of boiler page 21 5 Cleaning of burner page 23 6 Measuring gas supply pressure page 16 inches W C inches W C 7 Measuring orifice pressure page 16 inches W C inches W C 8 Checking for leaks in operating condition page 14 9 Checking pilot burner flame page 21 ff 10 Checking main burner flame page 16 11 Check the vent damper page 18 12 Check high temperature limit control page 1...

Page 26: ...and maintenance Logano GC 144 II 6 720 808 893 2017 02 26 Date Date Date Date Date inches W C inches W C inches W C inches W C inches W C inches W C inches W C inches W C inches W C inches W C Table 13 Maintenance protocol ...

Page 27: ...ssembly You can t get the If everything is OK replace pilot assembly No Heat requirement ended system switches off flue baffle closes End of troubleshooting Repeat procedure until heating system operates properly On models with vent damper check that it operates and limit switches are present If necessary replace vent damper Check ignition wiring ceramic insulator of ignition electrode and ignitio...

Page 28: ...ignition flame Specified thermostat value control reached Main and ignition gas valves close gas burners ex tinguished vent damper if installed closes Ignition burner operation Ignition flame burns automatic ignition signals steady ignition flame or ignition flame does not burn pilot assembly starts ignition at tempt switches off after 90 seconds END PHASE 1 Ignition attempt PHASE 2 Main burner op...

Page 29: ...y valid in the U S A and only for elevations from 0 8500 ft Boiler size Number of orifices Main gas orifice identification for elevations from feet in ft3 h inch W C 0 8500 ft 1 1 installation attitude 18 3 2 180 29 6 8 8 25 4 3 175 41 2 8 6 32 5 4 170 53 8 7 Table 15 Main gas orifice identification and manifold pressure for Natural gas at 60 F 30 inch HG These values are only valid in the U S A a...

Page 30: ... orange yellow black 4 R W L2 Plug Plug PV Intermittent pilot control module S8600H Connecting terminals for thermostat 2 Burner assembly Terminals on boiler block Main supply power use circuit breaker as required by code 1 Intermittent pilot dual valve combination gas control VR8204 Pilot burner Honeywell Main valve Pilot valve green blue white red GND MV MV PV GND PV MV PV MV 24V 24V 3 2 1 yello...

Page 31: ...Burner Spark Gas valve Main Pilot PV PV MV GND MV S8600H GND PV PV MV MV 24V 24VGND K1 TR High Limit Flame roll out safety shutoff switch K2 B2 L2 N L 24V AWG 18 WIRE 120 VAC Wiring Schematic GC 124 GC 144 Wire nut Wire nut Wire nut Circuit breaker Emergency shut off switch Fuse 1 25AT Page 2 2 Wiring diagram gas boiler GC124 USA GC 144 USA Intermittent ignition 8469 8718588198 2012 11 GAW 032 USA...

Page 32: ......

Reviews: