IV.

PURGE GAS LINES

If not previously done, purge the lines after all connections have
been made and check for leaks.

WARNING:

Never purge a gas line into a combustion

chamber. Never use matches, candles, flame, or other
sources of ignition for the purpose of checking leakage.
Use a soap-and-water solution to check for leakage.
Failure to follow this warning could result in fire,
explosion, personal injury, or death.

V.

ADJUSTMENTS

A.

Set Gas Input Rate

Furnace gas input rate on rating plate is for installations at altitudes
up to 2000 ft.
In the U.S.A., the input rating for altitudes above 2000 ft must be
reduced by 2 percent for each 1000 ft above sea level.
In Canada, the input rating must be derated by 5 percent for
altitudes of 2000 ft to 4500 ft above sea level.
Furnace input rate must be within

±

2 percent of input on furnace

rating plate.

1. Determine natural gas orifice size and manifold pressure for

correct input.
a. Obtain yearly heat value average (at installed altitude)

from local gas supplier.

b. Obtain yearly specific gravity average from local gas

supplier.

c. Verify furnace model. Table 12 can only be used for

model 355MAV Furnaces.

d. Find installation altitude in Table 12.

NOTE:

For Canada altitudes of 2000 to 4500 ft, use U.S.A.

altitudes of 2001 to 3000 ft in Table 12.

e. Find closest natural gas heat value and specific gravity in

Table 12.

f. Follow heat value and specific gravity lines to point of

intersection to find orifice size and low- and high-heat
manifold pressure settings for proper operation.

EXAMPLE: (0—2000 ft altitude)
Heating value = 1050 Btu/cu ft
Specific gravity = 0.62
Therefore: Orifice No. 45

Manifold pressure: 3.6-in. wc for high heat

1.5-in. wc for low heat

* Furnace is shipped with No. 45 orifices. In this example,
all main burner orifices are the correct size and do not need
to be changed to obtain proper input rate.

g. Check and verify burner orifice size in furnace. NEVER

ASSUME ORIFICE SIZE; ALWAYS CHECK AND
VERIFY.

2. Adjust manifold pressure to obtain input rate.

a. Remove burner enclosure front.

NOTE:

Manifold pressure MUST always be measured with the

burner box cover REMOVED.

b. Remove caps that conceal adjustment screws for low-

and high-heat gas valve regulators. (See Fig. 48.)

c. Turn setup switch SW-2 on control center to ON

position. (See Fig. 25.) This keeps furnace locked in
low-heat operation.

d. Jumper R and W/W1 thermostat connections on control

center to start furnace.

e. Turn low-heat adjusting screw (5/64 hex Allen wrench)

counterclockwise (out) to decrease input rate or clock-
wise (in) to increase input rate.

NOTE:

DO NOT set low-heat manifold pressure less than 1.3-in.

wc or more than 1.7-in. wc for natural gas. If manifold pressure is
outside this range, change main burner orifices.

CAUTION:

DO NOT bottom out gas valve regulator

adjusting screw. This can result in unregulated manifold
pressure and result in excess overfire and heat exchanger
failures.

NOTE:

If orifice hole appears damaged or it is suspected to have

been redrilled, check orifice hole with a numbered drill bit of
correct size. Never redrill an orifice. A burr-free and squarely
aligned orifice hole is essential for proper flame characteristics.

f. Turn setup switch SW-2 to OFF position after complet-

ing low-heat adjustment.

g. Jumper R and W2 thermostat connections on control

center. (See Fig. 25.) This keeps furnace locked in
high-heat operation.

h. Turn high-heat adjusting screw (5/64 hex Allen wrench)

counterclockwise (out) to decrease input rate or clock-
wise (in) to increase rate.

NOTE:

DO NOT set high-heat manifold pressure less than 3.2-in.

wc or more than 3.8-in. wc for natural gas. If manifold pressure is
outside this range, change main burner orifices.

i. When correct input is obtained, replace caps that conceal

gas valve regulator adjustment screws. Main burner
flame should be clear blue, almost transparent. (See Fig.
49.)

3. Verify natural gas input rate by clocking gas meter.

NOTE:

Be sure all pressure tubing, combustion-air and vent

pipes, and burner enclosure front are in place when checking input
by clocking gas meter.

a. Calculate high-altitude adjustment (if required).

UNITED STATES

Fig. 48—Redundant Automatic Gas Valve

A97386

ON/OFF
SWITCH

INLET
PRESSURE
TAP

ON

O

F

F

BURNER

ENCLOSURE

REFERENCE

PRESSURE TAP

MANIFOLD

PRESSURE

TAP

LOW-FIRE
ADJUSTMENT
ALLEN SCREW
(UNDER CAP)

HIGH-FIRE
ADJUSTMENT
ALLEN SCREW
(UNDER CAP)

—37—

Summary of Contents for 355M-40-4

Page 1: ...26 29 Multiventing and Vent Terminations 29 CONDENSATE DRAIN 29 General 29 Application 29 Condensate Drain Protection 29 SEQUENCE OF OPERATION 31 34 Self Test Mode 31 Heating Mode 31 32 Heating Mode T...

Page 2: ...TLET 26 15 16 28 1 2 22 5 16 19 13 16 5 8 5 16 1 39 7 8 22 1 4 TYP 11 16 7 16 24 3 16 BOTTOM INLET 18 1 4 22 11 16 2 IN COMBUSTION AIR CONN 1 2 IN DIA GAS CONN 7 8 IN DIA POWER CONN 1 2 IN DIA THERMOS...

Page 3: ...CONNECTED TO THE CONTROL PRIOR TO DISCHARGING YOUR BODY S ELECTROSTATIC CHARGE TO GROUND 2 Firmly touch a clean unpainted metal surface of the furnace chassis which is close to the control Tools held...

Page 4: ...rican Gas Association 1515 Wilson Boulevard Arlington VA 22209 or from Literature Distribution Before installing the furnace in Canada refer to the current edition of the NSCNGPIC Contact Standards De...

Page 5: ...ation An alternate location for the condensate trap is the left hand side of casing See Fig 2 and 6 NOTE If the alternate left hand side of casing location is used the factory connected drain and reli...

Page 6: ...ck for proper connections G Upper Collector Box and Inducer Housing Unused Drain Connections UPPER COLLECTOR BOX DRAIN CONNECTION Attached to the UPPER collector box drain connection is a factory inst...

Page 7: ...nnected to condensate trap c Connect LOWER collector box drain connection to condensate trap 1 Condensate Trap Located on Left Side of Casing a Connect LOWER collector box drain tube blue and white st...

Page 8: ...ction E Condensate Trap Freeze Protection Refer to Condensate Drain Protection section for recommenda tions and procedures IV HORIZONTAL LEFT SUPPLY AIR DISCHARGE APPLICATIONS A horizontal left furnac...

Page 9: ...ace blower is located to the left of combustion and controls section of furnace and conditioned air is discharged to the right CAUTION Local codes may require a drain pan under entire furnace and cond...

Page 10: ...sure tube pink label is factory connected to the pressure switch for use when furnace is installed in UPFLOW or HORIZONTAL LEFT applications This tube MUST be dis connected and used for the condensate...

Page 11: ...lution or ventilation air This furnace must be installed so electrical components are protected from water Locate furnace as close to center of air distribution system as possible Locate furnace so co...

Page 12: ...rtant for low fire only installation III FURNACE LOCATION RELATIVE TO COOLING EQUIPMENT The cooling coil must be installed parallel with or on downstream side of furnace to avoid condensation in heat...

Page 13: ...talled from Table 1 2 Construct hole in floor per dimensions specified in Table 1 and Fig 13 3 Construct plenum to dimensions specified in Table 1 and Fig 13 4 If downflow subbase KGASB is used instal...

Page 14: ...lications on Combustible Flooring NOT Using KGASB Subbase Furnace with CD5 or CK5 Coil Assembly or KCAKC Coil Box 19 19 20 20 24 1 2 Upflow Applications 23 24 1 8 23 5 8 24 3 4 Downflow Applications o...

Page 15: ...on to ensure proper draining When suspended bottom brace supports sides and center blower shelf When unit is supported from the ground blocks or pad should support sides and center blower shelf area F...

Page 16: ...d in bottom return air opening This panel MUST be in place when side return air is used To remove bottom closure panel perform following 1 Tilt or raise furnace and remove 2 screws holding front fille...

Page 17: ...gas valve See Fig 48 Piping should be pressure tested in accordance with local and national plumbing and gas codes before furnace has been attached In Canada refer to current edition of NSCNGPIC If pr...

Page 18: ...n of field wiring See Fig 24 The 24 v circuit contains a 3 amp automotive type fuse located on control center See Fig 25 Any electrical shorts of 24 v wiring during installation service or maintenance...

Page 19: ...2 CIRCUIT HSI CONNECTOR PL5 6 CIRCUIT MODEL PLUG PL6 3 CIRCUIT COMM CONNECTOR PL7 12 CIRCUIT INDUCER MTR CONNECTOR PL9 2 CIRCUIT HSI CONNECTOR PL10 9 CIRCUIT BLOWER ADAPTER CONNECTOR PL11 1 CIRCUIT I...

Page 20: ...or 12 gage maximum solid or stranded wire 4 Route EAC leads through right hand wire grommet TABLE 4 ELECTRICAL DATA UNIT SIZE VOLTS HERTZ PHASE OPERATING VOLTAGE RANGE MAXIMUM UNIT AMPS UNIT AMPACITY...

Page 21: ...ppliance shall operate continuously 5 Test for draft hood equipped appliance spillage at the draft hood relief opening after 5 minutes of main burner opera tion Use the flame of a match or candle 6 Af...

Page 22: ...ckout may occur NOTE Do not count elbows or pipe sections in terminations or within furnace See shaded areas in Fig 31 32 33 34 and 35 TABLE 5 COMBUSTION AIR AND VENT PIPE TERMINATION CLEARANCES LOCAT...

Page 23: ...take housing plug fitting in appropriate unused intake housing connection c Insert perforated disk assembly factory supplied in intake housing where combustion air intake pipe will be connected d Inst...

Page 24: ...2 Pipe or 2 In Concentric 1 1 2 42 37 32 27 22 17 2 70 70 70 70 70 70 042060 2 Pipe or 2 In Concentric 1 1 2 42 37 32 27 22 17 2 70 70 70 70 70 70 042080 060080 2 Pipe or 2 In Concentric 1 1 2 25 20...

Page 25: ...7 NA NA NA 2 62 60 58 56 51 46 060100 2 Pipe or 2 In Concentric 2 27 22 17 12 7 NA 2 1 2 62 60 58 56 55 53 060120 2 Pipe or 3 In Concentric 3 43 41 39 37 35 34 ALTITUDE UNIT SIZE TERMINATION TYPE PIP...

Page 26: ...ide edge of pipe for better distribution of primer and cement 6 Clean and dry all surfaces to be joined 7 Check dry fit of pipe and mark insertion depth on pipe NOTE It is recommended that all pipes b...

Page 27: ...AIN 12 IN CLEARANCE ABOVE HIGHEST ANTICIPATED SNOW LEVEL OR GRADE WHICHEVER IS GREATER 90 VENT 12 IN SEPARATION BETWEEN BOTTOM OF COMBUSTION AIR AND BOTTOM OF VENT BRACKET COUPLING 12 MINIMUM OVERHANG...

Page 28: ...tall 90 street elbow into 90 elbow making U fitting A 180 U fitting may be used Sidewall terminations Install bracket as shown in Fig 34 or 35 For applications using vent pipe option indicated by dash...

Page 29: ...e to corrosive nature of this condensate a condensate pH neutralizing filter may be desired Check with local authorities to determine if a pH neutralizer is required II APPLICATION The furnace A C and...

Page 30: ...m Separation A93056 COMBUSTION AIR VENT VENT A Fig 40 Sidewall Termination of More Than 12 in Dimension A is Touching or 2 In Maximum Separation A96130 VENT A COMBUSTION AIR COMBUSTION AIR Fig 38 Conc...

Page 31: ...4 Ignition sequence After HSI ignitor warm up period is completed the gas valve opens permitting gas flow to burners where it is ignited After 5 sec the HSI is de energized and a 2 sec flame sensing...

Page 32: ...ame is sensed control center holds gas valve open If burner flame is not sensed control center de energizes gas valve and ignition sequence is repeated NOTE Ignition sequence repeats 3 additional time...

Page 33: ...nues to operate completing a normal blower off delay 11 Post purge The inducer continues operating for 15 sec after gas valve is de energized B Two Speed Applications For details on 2 speed heat pump...

Page 34: ...5 for all furnace model sizes This compensates for high humidity conditions during cooling operation XI ZONE MODE When setup switch SW 5 MZ is in ON position blower motor control is the same as above...

Page 35: ...med by pour ing water into the inducer drain side of condensate trap 1 Remove upper inducer housing drain connection cap See Fig 46 2 Connect field supplied 1 2 in ID tube to upper inducer housing dra...

Page 36: ...are used In this mode main blower speed is recalculated once every minute while furnace is in low heat or continuous fan mode SW 6 COMP TEST OFF Turn switch to ON to initiate component test Furnace wi...

Page 37: ...e measured with the burner box cover REMOVED b Remove caps that conceal adjustment screws for low and high heat gas valve regulators See Fig 48 c Turn setup switch SW 2 on control center to ON positio...

Page 38: ...nada U S A 775 43 3 8 1 6 42 3 2 1 4 42 3 3 1 4 42 3 4 1 4 42 3 5 1 5 Altitudes 800 43 3 5 1 5 43 3 7 1 5 43 3 8 1 6 42 3 2 1 4 42 3 3 1 4 2001 825 44 3 8 1 6 43 3 4 1 5 43 3 6 1 5 43 3 7 1 5 43 3 8 1...

Page 39: ...2 1 3 42 3 3 1 4 42 3 4 1 4 725 43 3 4 1 4 43 3 5 1 5 43 3 6 1 5 43 3 7 1 6 43 3 8 1 6 750 44 3 6 1 5 44 3 7 1 6 43 3 4 1 4 43 3 5 1 5 43 3 6 1 5 775 44 3 4 1 4 44 3 5 1 5 44 3 6 1 5 44 3 7 1 6 43 3...

Page 40: ...No Manifold Pressure High Low Orifice No Manifold Pressure High Low Orifice No Manifold Pressure High Low U S A Only 600 43 3 8 1 6 42 3 3 1 4 42 3 4 1 4 42 3 5 1 5 42 3 6 1 5 625 43 3 5 1 5 43 3 6 1...

Page 41: ...er hr k Multiply gas rate cu ft hr by heating value Btu cu ft l Turn setup switch SW 2 to OFF position and jumper R and W2 thermostat connections See Fig 25 This keeps furnace locked in high heat oper...

Page 42: ...and for varying heating cycle length NOTE When using an electronic thermostat set cycle rate for 3 cycles per hr 3 Return setup switch SW 2 to OFF position and replace thermostat on subbase CHECK SAFE...

Page 43: ...CM inducer motor is disconnected the furnace will shut itself down immediately Determine the reason pressure switches did not function properly and correct the condition 5 Turn off 115 v power to furn...

Page 44: ...nt of Rating Plate ________ Temperature Rise Adjusted Thermostat Anticipator ________ Anticipator Setting Adjusted or ________ Cycle Rate 3 Cycles per Hr Selected Safety Controls Check Operation _____...

Reviews: