Assembly - Gas Connection & Pressure Testing 

 
A minimum 15mm-diameter gas supply pipe must be used to within 1 metre of the 
installation with the final connection to the stove to be completed with the suitable 8mm 
semi-rigid gas pipe. The 8mm pipe should be connected to the inlet of the gas valve 
using the nut and 8mm olive provided. Support the control whilst finally tightening the 
supply pipe.  
 
The gas supply connection to the appliance is located at the right hand side rear of the 
stove. The connection requires an 8mm-diameter semi-rigid pipe, not more than 1 meter 
in length. 
 

Pressure Testing 

 
Always make sure that there is adequate gas pressure and volume to the stove. The 
relevant pressures are on the ID plate on the gas control knob. 
 

1. 

For propane gas, this is 37mbar 

measured at the inlet connection to the stove 

with the appliance in the full rate position. 

2.  Ensure that the gas pressure to the stove is maintained when it is operating at 

the same time as other appliances in the building and that a suitable pressure 
gauge is used i.e. a manometer. If the gas pressure is not as per above it will be 
the sole responsibility of the fitter to rectify and Broseley Fires will not be liable for 
any associated costs. 

3.  All figures obtained during pressure testing should be recorded on the 

commissioning form found at the end of these instructions. 

 

Ventilation (GB only) 

 
The gas stove is rated at less than 7kw and therefore does not normally require 
additional ventilation in the room (BS5871 – part II). 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Summary of Contents for DESIRE 5

Page 1: ...IRE 5 GAS STOVE SD1 Manual Control Conventional Top or Rear Flue LPG Gas Stove PLEASE LEAVE THESE INSTRUCTIONS WITH THE END USER Please note Gas installations MUST only be carried out by installers wh...

Page 2: ...ation 7 Mica Board Installation 8 Connecting the TTB Sensor 9 Ceramics Index 10 Positioning the logs Fitting the Decorative Log Retainer 11 13 Gas Connection Pressure Testing 14 Spillage Testing 15 Ma...

Page 3: ...missioning of gas stoves is carried out by a professionally qualified and accredited gas fitter listed on the Gas Safe register THE INSTALLATION MUST BE IN ACCORDANCE WITH THE GAS SAFETY INSTALLATION...

Page 4: ...ciency Class Class 2 Nominal Output 3 5kW NOx Class 4 Top Flue 5 Rear Flue Please note this product is designed to only use LPG Gas G31 Propane Dimensions Ignite CD1 Q5 WEIGHT 61 Kg Hereford CD2 Q5 WE...

Page 5: ...mended that the specific minimum clearances are maintained irrespective of the materials used in the construction of the opening This has been tested and approved to allow adequate air flow and access...

Page 6: ...have a maximum of four bends in the run each bend must not exceed 45 and an additional metre of vertical flue should be provided for each bend Ideally you should have a minimum vertical section of 60...

Page 7: ...d The handle acts like a nut on a thread and once removed will allow the door to open fully 3 Insert the burner end with the control knob first followed by the other end of the burner locating the bur...

Page 8: ...top mica board onto Finally fit the reaming side mica the side board this board will board and allow the top board to need supporting whilst the final rest down onto it the top board side board is fi...

Page 9: ...ner installed thread the TTB connection cable from the interrupter to the TTB sensor mounted on the rear panel of the stove TTB sensor located just below the rear flue outlet Thermo Couple To Gas Valv...

Page 10: ...Fires Ltd accepts no responsibility for any injury sustained whilst handling hot ceramics Ceramics which are placed other than in accordance with these instructions will be the sole responsibility of...

Page 11: ...sition as below Using the 2 off M5 C Sunk Bolts provided locate the decorative trim behind the stove opening as shown and secure in position Although it is possible to position all of the ceramics fir...

Page 12: ...tioning of the Logs STEP 2 Place the front log with the two cut outs in on the front of the main base so it touches the rear of the log retainer STEP 3 Place the large rear log in position across the...

Page 13: ...tilted back over The left hand side of the log needs to be placed between the two stand offs as shown STEP 5 Finally place the last log in the rear right hand corner of the stove as below Any soot ac...

Page 14: ...re and volume to the stove The relevant pressures are on the ID plate on the gas control knob 1 For propane gas this is 37mbar measured at the inlet connection to the stove with the appliance in the f...

Page 15: ...ng spillage monitoring system in the form of an oxygen depletion sensing pilot This is designed to shut down the fire within a safe period if there is an excessive build up of products of combustion w...

Page 16: ...nd side is not compressed DESIRE SD1 AND IGNITE CD1 MODELS ONLY Ensure that the stove is cold before proceeding Remove the door by lifting the door off the hinges Loosen the Hinge Locking nut inside t...

Page 17: ...ess the control knob fully 2 Whilst depressed turn knob sharply 90 degrees anti clockwise to pilot setting You should feel some resistance and hear a click Repeat until pilot light is visibly lit You...

Page 18: ...It is possible to touch up the paint using the original black stove paint however this new paint will then need to cure Curing the paint It is important to note that upon initial lighting of the stov...

Page 19: ...circuit will cause the pilot not to stay alight as the electrical charge from the thermos couple needs to arrive at the valve to keep it lit Take care not to overtighten the interrupter unit into the...

Page 20: ...cross the surface of the burner by removing all of the ceramics Only do this once pressures and flow rates are confirmed as being correct Double check all ceramics are re positioned correctly Ensure y...

Page 21: ...dental damage A clean soft brush can also be used Take care not to brush any debris towards the pilot as this may cause an obstruction in the jet Clean any dust debris from each individual ceramic usi...

Page 22: ...age __________Is the draught excessive __________ Is there any permanent ventilation in the room ____________________ Is the TTB connected correctly both ends ______________ Is the aeration of the pil...

Page 23: ...led and operated in accordance with our instructions or Repairs or modifications have been carried out by the purchaser or any third party not authorised by us or The appliance has been misused or acc...

Reviews: