BROOKS AUSTRALIA
RFP6 Installer ISSUE 4
38
INFORMATIVE EXAMPLE
RESIDENTIAL FIRE PANEL
LOG BOOK REPORT
MONTH/YEAR
INSPECTION, TESTING AND MAINTENANCE PROCEDURES
Premises
Address
Note
Give details of all unsatisfactory items in report section. Refer to owners manual for commissioning test report.
Place a tick in box where item is satisfactory Place a cross in box where item is unsatisfactory
SIX MONTHLY CHECK
CHECKED
All RFP equipment clean and operative
1
Battery condition and terminals
2
Indicator lights correct operation
3
Correct initiation of each Smoke/Heat Alarm
4
Fault condition simulation on all zones
and ensure:
. Fault annunciation operative
5
Modifications to the system -
. Smoke/Heat Alarm condition
6
. Building modifications
7
Correction of items previously recorded for action
8
CHECKED
Visual inspection of all Smoke/Heat Alarms
9
Zone facility operation
10
Correct operation of all ancillary control devices
11
Operation of manual call points
12
Spare glasses for manual call points
13
All controls returned to normal condition
14
REPORT(S)
SIGNED:
SERVICE PERSON:
For owner or his agent
Print Name
Date:
Signature