Installation and Operation Manual
X-VA-1305-1306-eng-eu
PN 541-C-029-AAG
April, 2008
Models GT 1305 & 1306
10
2-6 Installation
The model GT 1300 can be installed as follows:
a Carefully remove any material which could have been used to protect the
instrument for damage during shipping.
b The indicator must be installed with the inlet at the bottom and the outlet
at the top, and must be installed as near vertical as possible to maintain
indicator accuracy.
c It is strongly recommended to install a by-pass piping arrangement around
the meter. By-pass piping permits the meter to be isolated from the low line
for servicing or cleaning.
Drawing vertical/horizontal line with by-pass piping
Section 2 Installation