2-4
9. Crane may tip at less than rated loads if the surface is uncompacted, or if there is wet
dirt, soft soil with frozen crust, thin or cracked pavement, or surface near a hole or
ledge. Always use adequate outrigger floats and/or cribbing. See page 2-13.
10. The operator shall not leave the controls while the load is suspended.
11. Always use adequate parts of load hoist line for lifting heavy loads.
12. Always be sure the rope is properly seated and wound level on hoist drum.
13. Keep hands away from load hoist rope when hoist is being operated.
14. Be sure at least five wraps of rope are left on the hoist drum to insure against rope
pulling out of its anchor.
15. Never wrap the hoist rope around a load. Always use approved rigging.
16. Avoid pinch points such as between a rotating turret & the cab or operator guard ,or
in access holes of a telescoping boom.
17. Avoid two-blocking.
A. Stop raising hoist line before downhaul or hook block strikes boom tip plates.
B. Pay out hoist line while extending boom.
C. Maintain clearance between downhaul weight or hook block and boom tip
while booming down.
CAUTION
Keep hands out of Anti-Two-Block mechanism. Serious injury can result from
moving parts.
DANGER
Two-blocking will abruptly stop boom lowering, as well as hoist and extend. If
the boom is moving fast, this will cause the load to bounce or swing, which
could cause loss of control of load or tipping.
Summary of Contents for IC-20-1K
Page 6: ...1 2 DIMENSIONS AND ORIENTATION IC 20 1K...
Page 7: ...1 3 TURNING DIMENSIONS...
Page 25: ...2 11...
Page 26: ...2 12...
Page 36: ......
Page 45: ...3 9 IC 20 LUBRICATION CHART...
Page 49: ...3 13 JIC SCHEMATIC...
Page 51: ...3 15 STEERING SYSTEM...
Page 53: ...3 17 IC 20 PROPULSION SYSTEM...
Page 63: ......
Page 64: ......
Page 65: ......