2-15
TWO-PART LINE REEVING
For loads above 2,500 pounds (1135 kg) the sheave block must be used. The wedge
socket should be pinned to the 2-part-line lug as shown in the figure. The dead end of
the rope in the wedge socket should be clamped as shown in the figure. The clamp
must not be used on the live part of the rope. This will seriously weaken the rope by
metal fatigue over a number of cycles. The sheave block should hang straight, and the
top of the block should meet the boom sheave plates squarely when pulled up snugly.
Summary of Contents for IC-20-1J
Page 6: ...1 2 DIMENSIONS AND ORIENTATION IC 20 1J Courtesy of Crane Market...
Page 7: ...1 3 TURNING DIMENSIONS Courtesy of Crane Market...
Page 25: ...2 11 Courtesy of Crane Market...
Page 26: ...2 12 Courtesy of Crane Market...
Page 36: ...Courtesy of Crane Market...
Page 44: ...3 8 IC 20 LUBRICATION CHART Courtesy of Crane Market...
Page 48: ...3 12 JIC SCHEMATIC Courtesy of Crane Market...
Page 50: ...3 14 STEERING SYSTEM Courtesy of Crane Market...
Page 52: ...3 16 IC 20 PROPULSION SYSTEM Courtesy of Crane Market...
Page 62: ...Courtesy of Crane Market...
Page 63: ...Powered by TCPDF www tcpdf org Courtesy of Crane Market...