6. Disconnect the cables from the port blades and set them aside. The mSFP, SFP, SFP+, or XFP transceivers can be left in the
port blades or removed.
7. Disconnect all cables from the CP8 and CR8 blades.
8. Disconnect any ICL cables.
Removing components from the chassis
ATTENTION
Follow electrostatic discharge (ESD) precautions when removing components. Wear a wrist grounding strap connected to chassis ground
(if the device is plugged in) or a bench ground.
NOTE
Do not remove WWN cards from the chassis as new WWN cards are preinstalled in the replacement chassis. Do not replace the
WWN cards in the replacement chassis with the old WWN cards as this will result in licensing and return materials authorization
(RMA) issues for your product. The original license will be transferred to the replacement chassis, based on the license
identification (LID) of the new, preinstalled WWN card, through the RMA process. You should be provided a license for the new
chassis through email. If you have not received this, contact your Brocade support representative.
1. Remove the chassis door (
Removal and replacement of the chassis door
on page 83) if not already done.
2. Remove the cable management comb (
Removal and replacement of the cable management comb
3. Remove the port blades or filler panels (
Removal and replacement of the port, application, and encryption blades
and
Removal and replacement of the blade filler panel
4. Remove the core switch blades (CR8) (
Removal and replacement of the core switch blade (CR8)
5. Remove the control processor blades (CP8) (
Removal and replacement of the control processor blade (CP8)
6. Remove the power supplies or filler panels (
Removal and replacement of the power supply
on page 100).
7. Remove the blower assemblies (
Removal and replacement of the blower assembly
Installing the replacement chassis
NOTE
Use safe lifting practices when moving the product. (C015)
ATTENTION
A fully populated Brocade DCX (eight FC8-64 port cards, 512 ports) weighs approximately 159.2 kg (351 lb) and requires a
hydraulic or assisted lift to install it.
NOTE
If the Brocade DCX is installed in a cabinet, ensure that the cabinet is balanced and secured mechanically and that the removal
and installation procedure will not compromise cabinet stability.
1. If the chassis is in a cabinet, remove it from the cabinet, remove the rack mount hardware, and save the hardware for use with
the new chassis.
2. Place the chassis on a lift or on the shipping pallet provided with the original chassis.
Removal and replacement of the Brocade DCX chassis
Brocade DCX Backbone Hardware Installation Guide
130
53-1000685-24
Summary of Contents for DCX Backbone
Page 8: ...Brocade DCX Backbone Hardware Installation Guide 8 53 1000685 24...
Page 12: ...Brocade DCX Backbone Hardware Installation Guide 12 53 1000685 24...
Page 14: ...Brocade DCX Backbone Hardware Installation Guide 14 53 1000685 24...
Page 24: ...Brocade DCX Backbone Hardware Installation Guide 24 53 1000685 24...
Page 28: ...Brocade DCX Backbone Hardware Installation Guide 28 53 1000685 24...
Page 46: ...Brocade DCX Backbone Hardware Installation Guide 46 53 1000685 24...
Page 50: ...Brocade DCX Backbone Hardware Installation Guide 50 53 1000685 24...
Page 82: ...Brocade DCX Backbone Hardware Installation Guide 82 53 1000685 24...
Page 138: ...Brocade DCX Backbone Hardware Installation Guide 138 53 1000685 24...
Page 142: ...Brocade DCX Backbone Hardware Installation Guide 142 53 1000685 24...
Page 148: ...Brocade DCX Backbone Hardware Installation Guide 148 53 1000685 24...