6. Verify that the power LED on the power supply displays a steady green light.
7. If you are installing two additional power supplies to bring the total power supplies up to four, perform one or both of the
following tasks to enable sending notifications if one power supply fails.
NOTE
A maxiumum of four power supplies can be installed in the chassis.
•
For Fabric Watch monitoring, change the switchStatus policy settings to the following:
switch.status.policy.PowerSupplies.down = 1
switch.status.policy.PowerSupplies.marginal = 0
For more details on executing the
switchStatusPolicyShow
and
switchStatusPolicySet
commands, refer to the
Fabric OS
Command Reference
.
•
For Monitoring and Alerting Policy Suite (MAPS) monitoring, follow procedures to update the active MAPS power supply
switchstatus policy settings for four PSU devices in the "Additional MAPS features" section of the
Brocade Monitoring and
Alerting Policy Suite Administrator's Guide
.
Removal and replacement of the blower assembly
This procedure provides instructions for removing and replacing a blower assembly.
ATTENTION
The Brocade DCX can continue operating during the replacement if the other two blower assemblies are operating,To ensure
continuous adequate cooling, maintain three operating blower assemblies at all times except for the brief period when replacing
a blower assembly.
Time and items required
The replacement procedure for each blower assembly takes less than 5 minutes. The following items are required for the blower
assembly replacement:
•
Replacement blower assembly
•
#2 Phillips screwdriver
Removing a blower assembly
1. Before removing a blower assembly, verify that the other blower assemblies are functioning correctly. The power LEDs should
be steady green.
2. Use the screwdriver to loosen the captive screws at the top and bottom of the blower assembly.
Removal and replacement of the blower assembly
Brocade DCX Backbone Hardware Installation Guide
53-1000685-24
103
Summary of Contents for DCX Backbone
Page 8: ...Brocade DCX Backbone Hardware Installation Guide 8 53 1000685 24...
Page 12: ...Brocade DCX Backbone Hardware Installation Guide 12 53 1000685 24...
Page 14: ...Brocade DCX Backbone Hardware Installation Guide 14 53 1000685 24...
Page 24: ...Brocade DCX Backbone Hardware Installation Guide 24 53 1000685 24...
Page 28: ...Brocade DCX Backbone Hardware Installation Guide 28 53 1000685 24...
Page 46: ...Brocade DCX Backbone Hardware Installation Guide 46 53 1000685 24...
Page 50: ...Brocade DCX Backbone Hardware Installation Guide 50 53 1000685 24...
Page 82: ...Brocade DCX Backbone Hardware Installation Guide 82 53 1000685 24...
Page 138: ...Brocade DCX Backbone Hardware Installation Guide 138 53 1000685 24...
Page 142: ...Brocade DCX Backbone Hardware Installation Guide 142 53 1000685 24...
Page 148: ...Brocade DCX Backbone Hardware Installation Guide 148 53 1000685 24...