6.1 OPERATING
INSTRUCTION
to positioning the load on the solo gyps drywall panel hoist
make sure that:
•
the basket is at the lower position
•
the load cradle is at the lower position
•
the load is balanced,
•
the maximum weight is not exceeded.
6.2
Warning Risk of collision
During the translation and/or lifting/lowering operation, the operator must paying attention in order that
the working area on the ground and over the basket is always free from obstacles or dangers.
6.3
Drywall Panel Installation Procedure
Drive the Platform, with the Solo Gyps drywall hoist installed on board, at the desired position following
the instruction of the 6.1 of this manual. At this point the operator can operate the installation of the dry-
wall panel as described hereunder: