Maintenance, Inspection
25
TSS – 6720887693 (2018/10)
12
Maintenance, Inspection
WARNING:
Risk to life from falling from roof!
▶ Whilst working on the roof, take all necessary precautions against a
possible fall.
▶ If there is not any independent anti-fall safety device, wear personal
protective equipment.
NOTICE:
Collector damage from evaporation in the solar circuit!
▶ Only carry out inspection or maintenance work when the sun is not
shining on the collectors or the collectors are covered.
If an immersion heater is installed:
WARNING:
Risk to life from electric shock!
Touching live electrical parts can cause an electric shock.
▶ Before working on electrical parts, disconnect all phases of the
power supply (fuse/circuit breaker) and lock the isolator switch to
prevent unintentional reconnection.
We recommend conducting the first inspection or maintenance after
2 months.
▶ Use the table as a template for further documentation.
▶ Check the system after 2 months (inspection). Then check every
1-2 years. Immediately remedy all faults (maintenance).
▶ Fill out the report and tick off the tasks performed.
Table 16
Table 17 Commissioning, inspection and maintenance tasks
User:
System location:
Commissioning, inspection and maintenance tasks
Inspection/maintenance
Date:
Visual inspection of collectors, storage tank and installation system carried
out (correct seating, visual impression, e.g. corrosion, anode)?
Visual inspection for leaks carried out at points where the mounting system
meets the roof?
Visual inspection of pipework insulation carried out?
Check function of pressure relief valves and safety equipment. Briefly open
the pressure relief valves manually.
Visual inspection of glass panes. Cleaning in the case of severe
contamination.
pH level of heat transfer medium checked? Replace heat transfer medium if
value is ≤ 7 (heat transfer medium coloured black, strong odour)
1)
1) pH value = indicator of the acid content of a fluid; indicator strips available from chemists or service cases
Frost protection to _______ °C checked and analysed?
Frost protection ensured until ________ (month/year)
(check frost protection
at least every two years
!)
Thermostatic DHW mixing valve functioning (if installed)?
Comments:
Company stamp / date / signature