Electric Drives
and Controls
4
−
15
Bosch Rexroth AG
BT 6.00
1070080078 / 03
Operation
4.5.6
Display data of the last weld
You may have the BT 6 show
D
the schedule that performed the last weld.
D
the commanded current, actual current and heat value most recently
used by a certain schedule.
L
Proceed as follows:
1. Press
key.
2. Move the cursor to the ”LAST SEQUENCE” line with the keys
or
.
3. Press
key.
The cursor is in line 1 (schedule).
Line 3 of the display contains the schedule that was last executed.
4. In order to display the data of the last weld of a certain schedule, en-
ter the desired schedule number in line 1 and press key
.
The BT 6 will open a screen which contains the commanded current,
actual current and heat value of the last weld of this schedule.
If necessary, the sequence data can be called up individually for the
1st, 2nd and 3rd weld time by pressing the
key.
5. To display the data of other schedules:
Press the key until line 1 shows the text ”Schedule”. Proceed to 4.
In order to get back to the main menu: press
key.
.
In order to call up the lower-level LAST SEQUENCE screen (steps 1.