background image

22

Fig. 4.17

Fig. 4.18

Fig. 4.19

Fig. 4.20

DOUBLE BOILER

At the output of the lines, the distributor will be put in condition 
of FIRST INSTALLATION. As it reaches the location the operator 
will link only water (both in the case of linking to the mains and  
autonomous tanker) and the mains.

The distributor, in condition of resistances OFF, will automatically 
require water and will open the electrovalve 2 to vent the air which 
is in the stainless boiler. This condition will last 200 seconds. At 
the end of this timeout, the distributor will close the electrovalve 
2 and the  water input ev for 20 sec. After this time water loading 
will continue until the micro lack of water is N.C. for a time excee-
ding 5 sec (this operation is linked to a second timeout of 200 
seconds). In this condition the D.A. activates the electrovalve 2 
and will supply 20 sec of water. At the end of the supply, the micro 
lack shall return to N.C. After 10 sec D.A. activates the expresso 
pump, and, on condition of resistance OFF, it will supply 20 cc of 
water through the coffee ev (measured through the fan). After 
this procedure, the distributor installation date is stored. When 
the date is confi rmed, D.A. waits 10 seconds and soon after it will 
start to heat up water in the 2 boilers. 

4.5.3 Filling the cooling unit

Where foreseen , for the fi lling of the cooling unit operate as fol-
lows: 

–  Remove the cap positioned on the top plate of the cooling unit 

and insert the instant boiler drain hose which is positioned along 
the liquid waste chute.(Fig.4.18). 

–  Position the reservoir drain hose in the liquid waste bin, in the 

(Fig.4.19). 

–  Insert the key in the door switch  (see Fig.4.12) and wait until 

water fl ows out of the drain hose.

– Remove the door switch key

–  Disconnect the instant boiler tube and replacing the cap and 

position again along the chute.

–  Connect the refrigerating group electrically (insert into the 

junction box the blue wire n. 18) (Fig. 4.20)

–  Wait for the soluble produce heater to fi ll up

–  Make the necessary selections in order to fi ll the hydraulic cir-

cuits

–  Wait for  thirty minutes until the temperature of the refrigerating 

group reaches regime and i.e.: 

–  The thermostat has already been calibrated by the manufacturer 

in order to obtain the following temperatures:

  water in the reservoir about +4°C

  drinks about +6/ 8°C

At the end of the water 
fi lling, effect a cleaning 
cycle of the mixer group 
so as to fi ll all the circui-
ts and remove eventual 
residues from the boiler 
(Fig.4.17).

Before connecting the 
power supply, ensure 
that the distributor has 
been connected to the 
water mains and that 
the water tap has been 
turned on.

Summary of Contents for BVM951

Page 1: ...BVM971 BVM951 CERT N 9105 BNVD UNI EN ISO 9001 2000 USE AND MAINTENANCE MANUAL...

Page 2: ......

Page 3: ...ending S p A has applied the Standards for the prevention and the elimination of the radio disturbances in respect of the EEC Standards 89 336 93 68 and subsequent annexes and of the D L nr 476 and su...

Page 4: ......

Page 5: ...BIANCHI VENDING S p A Viale Parigi 5 7 9 24040 ZINGONIA DI VERDELLINO BG ITALIA Tel 035 88 22 25 ra Fax 035 88 33 04 BVM971 BVM951...

Page 6: ...ers and cups The maintenance technician is also responsible for cleaning the distributor see operations indicated in chapter 7 0 In the event of a fault the maintenance technician must call the instal...

Page 7: ...SCREWDRIVERS Small size Medium size Large size Normal cross Small cross Medium cross Large cross Of Te on small size for Trimmer re gulation RATCHET SPANNER no 14 TESTER ELECTRICIAN S SCISSORS PROGRA...

Page 8: ...u Times and thresholds 5 1 7 Menu Payment system 5 1 7 1 Coins Line 5 1 7 2 Bill Line 5 1 7 3 Enable Coin 5 1 7 4 Enable bills 5 1 8 Menu Price Table 5 1 9 Menu Price Selection 5 1 10 Menu Table disco...

Page 9: ...remain inside of the same so as to allow further consultations on the part of the various operators until the dismantlement and or scrapping of the machine In case of loss or damage of the present man...

Page 10: ...r must not in any circumstance be able accede to those parts of the automatic distributor that are protected and require a tool in order to be accessible The knowledge and the absolute respect from a...

Page 11: ...Instant cold beverages Kg 4 0 Sugar Kg 4 0 Kg 4 0 Caps N 700 500 Spoons N 540 400 cooling unit 2 Class N Class N cooling gas R134a Peso 180gr R134a Peso 180gr Type of light and power N 1 Neon light 8...

Page 12: ...tic distributor is exclusively for the dispensing of drinks prepared mixing food substances with water by infusion as far as concerns espresso coffee For this purpose use products declared as suitable...

Page 13: ...1 2 For MOD BVM971 BVM951 SUGAR DISPENSER The sugar is dispensed directly in the cup in the E versions whereas for the I versions it is pre mixed with the instant drinks The display management of the...

Page 14: ...ground coffee Fig 2 6 the pump that dispenses the quantity of programmed water and that is controlled by a speci c electronic device volume meter extracting the water from the coffee boiler Fig 2 7 t...

Page 15: ...d According to the type drink requested and to the distributor mo del several of the various processes described here below can be activated If present the whipper motor is activated Fig 2 11 The elec...

Page 16: ...les and by a transparent lm in polypropylene Fig 3 2 The automatic distributor will be delivered packed assuring both a mechanical protection and protection against damages from the external environme...

Page 17: ...w cup turret example in Fig 3 7 coin box sugar container weight on the spoon dispenser column coin mechanism cover Master board product containers water bin oat mechanism BVM971 BVM951 bottom skirting...

Page 18: ...irty due to accidental spilling of the products use if necessary under the distributor a protection suf ciently wide to cover the distributors operating space 6 2 Connection to the main water supply B...

Page 19: ...this reason verify the plant s earth wire connection to ascertain that it is ef cient and it answers national and European safety electric standards If necessary require the intervention quali ed per...

Page 20: ...some operations is however necessary operate with the door open but with the distributor connected It is possible for installation technician to operate in this way by inserting the special plastic k...

Page 21: ...date has been con rmed D A waits 10 seconds and soon after it will start to heat water in the boiler POLISULPHONE BOILER with LEVEL PROBES At the output of BV lines the distributor will be put in con...

Page 22: ...on after it will start to heat up water in the 2 boilers 4 5 3 Filling the cooling unit Where foreseen for the lling of the cooling unit operate as fol lows Remove the cap positioned on the top plate...

Page 23: ...tes water funnels mixing bowls and whippers and silicone tubes and dip these parts also in the prepared solution Fig 4 23 with a cloth soaked with the solution clean the whipper assembly base Fig 4 24...

Page 24: ...d its aging in relation to the consumption forseen in the time period between two loadings Check the container product capacity in the section TECHNICAL CHARACTERISTICS Connect the payment system Fig...

Page 25: ...tomatic vending machines check the relevant features by consulting the chapter 1 2 Technical Speci cations avoid compressing the cups between themselves during the loading Don t try to rotate the turr...

Page 26: ...remove the wrapping Fig 4 35 once the loading is completed put the weight back in the spoon dispensing column Check that the spoon are cut burr free that they are not bent and that they are all place...

Page 27: ...aximum sequence of 3 electrovalves each electrovalve can be coupled to 3 products at most 2 products in case of 951 Esp These couplings are factory made therefore for a correct use of the distributor...

Page 28: ...on can be combined creating a maximum sequence of 3 electrovalves each electrovalve can be coupled to 3 products at most These couplings are factory made therefore for a correct use of the distributor...

Page 29: ...a maximum sequence of 3 electrovalves each electrovalve can be coupled to 3 products at most These couplings are factory made therefore for a correct use of the distributor we should keep strictly to...

Page 30: ...r delivery Powder will be then directly delivered into the third mixer and mixed with water of EV 3 BVM971 Instant With the new dose menu we have the possibility to create selections with the required...

Page 31: ...for more than 5 seconds the machine will show on the display the date If not the installation procedure will be repeated This means that surely we will have water in the boiler at the end of this proc...

Page 32: ...e serial number 0 999999 Displayed only if there is the slave machine 1 SN slave 2 Slave 2 machine serial number 0 999999 Displayed only if there is the slave machine 2 SN slave 3 Slave 3 machine seri...

Page 33: ...ng the code A 98 or B 98 on the keyboard The temperature alarm will be disabled for the programmed safety time when such time expires the safety temperature control will be enabled If on the detected...

Page 34: ...XX Selection of the push button to con gure 1 30 for linear key board 1 32 for Multibrand keyboard Drink Enable drink On Off Drink Code XXX the user can select the selection code for the heat distribu...

Page 35: ...hird E V 0 25 5 Ton product X T on motoreducer third product 0 25 5 s Toff product X T off motoreducer third product 0 25 5 s T Sugar Expresso X T sugar expresso 0 25 5 s Double Product 1 Parameters p...

Page 36: ...Delay Mixer coupled with second E V 0 25 5 s T product X T 1st box coupled with second E V 0 25 5 s D product X Delay 1st box coupled with 2nd E V 0 25 5 s Ton product X T on motoreducer rst product...

Page 37: ...ettingofthevalueofToken3 000 00 999 99 Enabled only if Abil Token On Change x Token Enables change if the value of token is than selection Y N Enabled only if Enabl Token On Re charhe Token Enables th...

Page 38: ...y Hour 3 OFF o XX Happy Hour 4 OFF o XX Happy Hour 5 OFF o XX By shifting the cursor UP DOWN it is possible to select the number of the day when happy hour is to be enabled OFF 01 31 Start 1 Set switc...

Page 39: ...Bianchi it will be possible to enable or disable the possibility to block or signal the single Preventive Action decounters If the customer takes through master slave If in the PHASE 2 the user does n...

Page 40: ...relevant to coffee in grain 0 1677721s 5 1 14 Menu Sales Tot collected hot Unresettable Hot total amount 0 16777215 Total collected Resettable hot total amount 0 16777215 Total Collected Cool U n r e...

Page 41: ...16777215 Tot jug test Resettable tot jug test 0 16777215 Jug test sel 01 Drink jug test counter 1 0 65535 Test jug sel 30 Drink jug test counter 30 0 65535 5 1 14 1 System audit Aut Tub Value of coins...

Page 42: ...switch on time 1 00 00 23 59 Stop 1 Set switch off time 1 00 00 23 59 D A Off 1 If ON it switch off the whole distributor if OFF let in St by only the system On Off It is linked to slot 1 Start 2 Set...

Page 43: ...temperature and in line 2 the possible detected alar ms Pressing twice the key Service the stand by heating phase will be bypassed allowing you to perform test selections even on non regimen temperat...

Page 44: ...aster performs a BEEP con rming its operation Test w o Sugar It performs an option drink without sugar Full test After pressing this key in line 2 the word test is displayed and the machine is in stan...

Page 45: ...ith the provisions listed below 6 1 3 Daily cleaning recommended The objective is that to avoid the creation of bacteria in the food zone areas For all cleaning operations follow the instructions indi...

Page 46: ...necessary Monthly effect the debacterisation of all the parts in contact with food substances using chlorine based solutions following the operations already described under chapter 5 5 Every six 6 m...

Page 47: ...aintenance is in progress it is important that the person responsible for cleaning never has to interrupt his work in order to operate the machine For internal cleaning use clean cloths better if disp...

Page 48: ...1 Dosage and grinding regulations Coffee temperature in the cup between 70 and 80 Temperature of soup products in the cup between 70 C and 80 C Grammage of coffee powder between 6 and 8 grams grams o...

Page 49: ...hen check that doses are reliable Fig 6 11 Automatic adjustment of grinding Fig 6 10 It allows in the expresso versions to keep grinding steady irrespective of the percentage of moisture temperature a...

Page 50: ...ced by the coconut shells which are charred and activated in oven The activation process gives an exchange surface whose GAC can by alloying organic impurities to it such as disinfectants chlorine and...

Page 51: ...ket can be used The operation can be effected on the distributor as follows switch off the machine turn the lower faucet being careful to put the relative hose in a bucket or better in a drain Fig 6 1...

Page 52: ...distributor power supply is disconnected Mod BVM971 Extract the sugar delivery unit releasing its geared motor Fig 6 15 e Fig 6 16 Unscrew the six trilobate screws located inside the door and remove...

Page 53: ...connect the machine electrically and hydraulically empty completely the instant boiler and the oater reservoir removing the plug located on the hose along the drain chute Fig 6 21 Put the plug back in...

Page 54: ...n dose menu Main cold Water Valve Always to be setted as the EV Cold 4 3 or 2 Without setting the cold water will be not charged and delivered for the selection 6 8 BVM951 Hot Cold version BVM951 Inst...

Page 55: ...old valve menu Chocolate Milk EV Cold 1 In main dose menu Main cold Water Valve Always to be setted as the EV Cold 4 3 or 2 Without setting the cold water will be not charged and delivered for the sel...

Page 56: ...56 6 8 1 BVM951 INSTANT Version HOT COLD Selection BVM951 Instant H C Programmation BVM951 Instant H C...

Page 57: ...57 Sevice BVM951 Instant H C 6 8 2 BVM951 ESPRESSO Version HOT COLD Selection BVM951 Espresso H C...

Page 58: ...58 Sevice BVM951 Espresso H C Programmation BVM951 Espresso H C...

Page 59: ...nd timeout for the cup release expires EDP Water level It expires after 2 seconds from the detection of the micro lack of water It switches off the resistor and reinitializes the time out for E12 and...

Page 60: ...pen When it is switched on a 30 second delay is expected before the alarm X is checked X indicates A B C EJL Sensor X It occurs if the BVM600 card does not de tect the product fall sensor for 5 second...

Page 61: ...Milk Chocolate Instant Lyo coffee Instant Milk Chocolate Coffee Tea Milk Chocolate Tea Tea Instant Lyo coffee Instant Hot water Hot water Instant coffee Instant coffee Hot water Instant coffee Milk Ch...

Page 62: ...LAMP LINKINGS TO BOILER RESISTORS sugar motoreducer Motoreducer 7 or Machines Code Code Machines Code Machines Code Machines Codice Machines Code Machines Machines Code Beccalli Disegn Data Cod M M M...