4.2 Installation of the ground anchors 

1. Put a tension line in the centre of the position 

where the gate must be installed. From the 
point of the lock post to the point where the rear 
support roll has to come.  

2. Position the templates of the guiding - and 

lock post as well as the template of the rear 
supporting wheels with the marked centre under 
the tension line. Take in account the inter-
distances as mentioned on the foundations plans 
provided with the order document. 

3. Mark the position of the holes with a small 

diameter concrete drill, this will help to centre 
the final drill. 

4. Drill the corresponding holes for the fixation 

according the installation instructions of the 
supplier of the chemical anchors. Drillings must 
be in good vertical position. 

5. Remove any dust and small particles from the 

drill holes using a brush and hand pump. This will 
ensure perfect adhesion between the resin for 
the ground anchor and the concrete foundation.  

6. Place the chemical anchors according to the 

instructions of the supplier. 

Drying times must be 

respected.

 

60761BM IM Ind_ENG.indd   8

60761BM IM Ind_ENG.indd   8

08-05-2006   09:11:14

08-05-2006   09:11:14

Summary of Contents for Robusta

Page 1: ...MOTORISED CANTILEVER SLIDING GATES Robusta Bekamatic Industry INSTALLATION MANUAL Ed 60761 April 2006 ENGLISH EN...

Page 2: ...5 Installation of the gate on the ground anchors 9 6 Installation of the lock post on the ground anchors 10 7 Alignment and levelling of the gate 10 8 Adjustment of the mechanical end stops 13 8 1 Ad...

Page 3: ...ser manual delivered with the gate The connection to the electrical power supply must be executed by a qualified technician and according laws and standards on electrical installations that are applic...

Page 4: ...essure resistance 25 N mm2 Minimum 2 flexible ducts minimum 60 mm for electrical cables at the position of the guiding post 1 duct for the connection between the power source and the guiding post of t...

Page 5: ...Bekamatic Industry ed April 2006 ENGLISH 5 21 3 1 Gates opening to the right...

Page 6: ...Bekamatic Industry ed April 2006 ENGLISH 6 21 3 2 Gates opening to the left...

Page 7: ...m 125 mm anchor depth and minimum 100 mm above Finished Ground Level For the connection of Guiding post 4 pieces Lock post 4 pieces Rear guiding roller set 4 pieces Chemical anchors M10 x 200 mm 4 pie...

Page 8: ...mentioned on the foundations plans provided with the order document 3 Mark the position of the holes with a small diameter concrete drill this will help to centre the final drill 4 Drill the correspon...

Page 9: ...ioned as a whole unit with the guiding post and the rear guiding wheels on their corresponding ground anchors 2 Chronological order of actions 1 Remove packaging from the guiding post Do not remove th...

Page 10: ...the tube of the lock post until the connectors are also in the tube This will protect them against water and will facilitate the uninstalling of photocells 3 Put the lock post on the ground anchors an...

Page 11: ...the base plate WARNING IN ANY CASE DO NOT ADJUST WITH THE M10 NUTS AND BOLTS FOR THE CONNECTION OF THE BASE PLATE AND THE WHEEL SUPPORT 5 After alignment of the lock post and horizontal leveling of t...

Page 12: ...he support roll as for the perpendicular of the support roll towards the under beam of the wing A support roll installed too high will add undesired friction forces on the wing which are increasing th...

Page 13: ...n or an obstacle at the rearside of the gate is preventing the wing opening over its full course then adjust according to the description below 1 Remove the lower part of the safety pressure strip fro...

Page 14: ...trongly advise to respect the dimensions of the foundation plans at all time 1 Remove the rear cover plate from the under beam by unscrewing the 4 screws 2 on both sides of the under beam 2 Close the...

Page 15: ...clockwise 3 Move the wing slightly back and forward This will prevent pushing a tooth of the dental wheel on top of a tooth of the dental rack instead of gripping in each other 4 When while turning t...

Page 16: ...OUR POSSIBLE ACCESSORIES IF YOU ARE CONNECTING MORE CONSUMERS TO IT IT MAY BE NECESSARY TO USE A BIGGER SECTION 11 Adjustment and testing safety equipment 11 1 Induction system Check if the jumpers J...

Page 17: ...up only one pair of photocells is used The receiver is placed in the guiding post and the transmitter is placed in the end post It is mainly sufficient to align the photocells this way that they look...

Page 18: ...r pair photocell set up three or four pairs of photocells are used This means that always two receivers must be placed in the same post and that both the transmitters must be placed in the opposite po...

Page 19: ...used as the motor protection The first time a time out occurs E7 will be indicated on the controller display the second time E5 will be indicated When error code E5 is indicated it is necessary to inv...

Page 20: ...ans that you are in the parameter configuration mode Remark If the procedure was not executed correctly the controller will return to normal display mode Also if you wait too long more than 25s to con...

Page 21: ...ax NL 0800 022 77 45 info benelux betafence com Betafence Italia Spa C da Salinello 59 I 64018 Tortoreto TE Tel 39 0861 7801 Fax 39 0861 780650 info italy betafence com Betafence Portugal Lda Av Almir...

Reviews:

Related manuals for Robusta