3. Foundations
• Foundations prepared according to the corresponding
drawing.
- The gate may not be installed following the slope of the construction site. Make sure
that the foundation for the lock post is at the same level as the foundation for the
guiding post.
• Quality of the concrete B25 = cubic pressure resistance
25 N/mm
2
.
• Minimum 2 flexible ducts, minimum Ø 60 mm, for
electrical cables, at the position of the guiding post:
- 1 duct for the connection between the power source and the guiding post of the
gate.
- Do not put signal cables in the duct for power supply! Install an extra duct between
the gate and the point of operating.
- 1 duct for the cable connections between the guiding post and the lock post.
WARNING!
THE FOUNDATION PLANS PROVIDED ON THE NEXT PAGES SERVE ONLY AS AN
EXAMPLE! ALWAYS USE THE PLANS PROVIDED WITH THE ORDER DOCUMENT.