background image

There are short 2x4s, that may have an angle on one end, supplied in the
kit. Use these to hold the rafters and bottom gable plate together by
temporarily screwing the blocks to the floor using 2-1/2" screws. This will
ensure that the gable frames and the trusses are identical.

3.

Secure the top of the rafters together with a 1"x4" barbed metal drive-on plate.

4.

Install (2) two 23-1/2" gable studs with angle cut at one end. Nail through the bottom

plate with 10d sinkers and secure the top with barbed metal drive-on plates.

Step 6

Assemble Roof Gables

23-1/2" Gable Stud

Bottom Gable Plate

Barbed Metal Plate

80-1/2" long 2x4

Truss Rafter

2x4 Block

2x4 Block

5.

Secure the 2x4 bottom plate to the truss rafter with a 2-1/2" wood screw on both ends.

Set gable aside.

6.

Repeat steps to assemble another gable.

1.

Cut (2) two 2x4-12' boards to a length of 144".

2.

Place one of the 144" boards on the floor along with (2) two 80-1/2" long 2x4 rafters as

shown below. Bottom 144" plate will be on edge. Rafters will lay flat.

Summary of Contents for North Dakota II

Page 1: ...ot be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2018 North Dakota II Building Size 12 x20 Revised July 19 2019 Assembly Book Manufactured by Reynolds Buil...

Page 2: ...se to build your own or pour a cement pad Windows are purchased separately Terminology Square Confirm corners are at 90 degrees Plumb Confirm walls and trusses are straight vertically Wall Plate Top a...

Page 3: ...4x8 flooring over the 2x4s Use 8d galv spiral nails spaced 8 apart Material Description 12 x 20 2x4 Treated Blocking 2 pcs 8 2x4 PT Joist Headers 2 pcs 8 2x4 PT Joist Headers 2 pcs 12 2x4 PT Floor Joi...

Page 4: ...inkers on each end 116 1 2 Wall Plate 24 19 3 4 116 1 2 Wall Plates 24 3 Repeat to assemble 3 three more 116 1 2 long wall frames 4 Set frames aside Step 2 Assemble Door Header 75 Long 2x8 48 OSB Fill...

Page 5: ...ven pre cut wall studs between the top bottom plates Nail top and bottom plates to studs using 10d sinkers 3 Square wall frame Measure the wall diagonally corner to corner Then measure the opposite co...

Page 6: ...e 2 center blocks Nail through top plate and toenail to header Use 10d sinkers Install these Studs Centered 2 Install 6 six pre cut wall studs between the wall plates where shown 33 33 8 Install a ful...

Page 7: ...l width siding panel with the LAP edge flush with the siding on back wall and flush with top plate Nail siding to back wall and all 2x4s using 6d galv nails spaced 8 apart 3 Install 4 four more siding...

Page 8: ...ngle cut at one end Nail through the bottom plate with 10d sinkers and secure the top with barbed metal drive on plates Step 6 Assemble Roof Gables 23 1 2 Gable Stud Bottom Gable Plate Barbed Metal Pl...

Page 9: ...rafter and collar tie in place See Detail B 2 Secure the 2x4 truss rafters at the top with a 8 x 20 wood gusset Apply wood glue between the 2x4s and the gusset Nail the gusset to the 2x4s with 14 four...

Page 10: ...ers Side Wall Flush with Inside of 2x4 4 Repeat to install soffit on the opposite side wall 5 Install 3 three 3 1 2 wide x 48 3 4 filler panels over the front and back wall Cut the last filler to fit...

Page 11: ...ng Use 6dgalv nails spaced 8 apart 2 Install center gable siding and right siding 3 Repeat to install siding on the other gable frame Step 11 Install 2x4 Tie Plates on Side Walls LAP Edge Flush Tongue...

Page 12: ...h 1 1 2 hanger nails The opening should line up with the X mark the bottom of the opening flush with the 2x4 tie plate Detail D 24 20 5 8 Measure from Backside of 2x4 Detail D 2x4 Tie Plate 3 Set roof...

Page 13: ...corner 3 Install a 8 1 2 long trim board called a keystone at the top of the gable flush with the top of the gable frame Use 6d galv nails 4 Gather 2 two 82 1 2 long 1x4 trim boards Butt each board ag...

Page 14: ...4 Fascia 2x4 Truss Roof Sheathing 2x4 Tie Plate 2x4 Soffit Block Detail E 1x4 6 Fascia Board Straight Edge Nail Fascia to 2x4 Block 6 1 4 1 Install 4 four 42 3 8 long 2x3 boards on the front gable flu...

Page 15: ...roof sheathing Set these boards flush with soffit panels The roof sheathing will extend 3 4 past the 2x3s to allow for trim Front Gable Nail with 6d Common 7 Wide Soffit Panels 42 3 8 Long 2x3 Sheath...

Page 16: ...Flashing 3 1 2 x5 Flashing 1 Locate in the pocket door box 2 two 3 1 2 x 5 metal flashing and bend along width to 90 degrees Install at each corner of the door opening These will be covered in the ne...

Page 17: ...spacer 2x3 Track Support Assembly 2 Install the other track support assembly 2x8 Door Header View From Inside View From Inside Screw Used as Spacer Treated Sill Board Notch in Sill Building Tip run a...

Page 18: ...the bottom of the door does not rub on the treated threshold Tighten the screws Tip Inserting a screw shown below will prevent the doors from falling through the opening between the track if the door...

Page 19: ...late to the bottom of the right door The angle end will hold the bottom in line with the left door when closed 4 Install the door handles and locking door hasp on the outside of the doors When install...

Page 20: ...Header 15 pcs Exterior Siding 4x8 4 pcs OSB Sheathing 4x8 Material Supplied by Local Supplier Qty Qty Material Shipped in 4 Extension Kit 2 2x4 Collar Ties 82 4 2x4 Truss Rafters 80 1 2 2 1x4 Side Wal...

Reviews: