4. Installation   

 

Before beginning the installation, always: 
 
Inspect the packaging for damage.    When the instrument is received, please inspect the item carefully to check for any 
potential  transit  damage.  In the event of damage, always report the damage to the shipping carrier and your local 
representative immediately.   

 

Included in the package: 

 

1. Stainless Steel Perforated shelf – 1 Pcs   
2. Power Cord – 1 Pcs   
3. Stainless Steel Water Container for humidity- 1Pc 

4. CO

  Gas Tubing with in-line CO

  Gas filter – 1Pcs 

5. Operating Manual- 1Pcs 

 

Above parts are packed inside incubator. When received, open the door of incubator and remove all parts to check 
confirm receipt.   

 
Cleaning before use 

Before conducting cell culture in this mini incubator, It is recommended to clean up entire chamber and shelves and 
water container by using soft cloth with at least 70% Ethanol mixed of 30% distilled water. 

 
 

Installation Procedure: 

 

4.1  Place the incubator at the desired location.   

Always avoid placing the incubator in:

   

- An area near equipment generating heat or cold air   
- Direct sunlight 
- An uneven surface or table. 
- A place with heavy vibration   
- A place with little air ventilation space behind the incubator.   

 

4.2 Place the shelves and water container

 

as shown in chapter “CONFIGURATION”.    If desired, place the stainless 

steel water container at bottom of chamber toward the back of incubator (in order to get it to be close to circulation fan).  
This increases the humidity.   
 
 
 

Distilled water is recommended in order to avoid contamination and corrosion. 

         If possible, use warm (~37

) distilled water for immediate humidification.       

   

4.3. Connect the CO

  Gas supply   

The Gas tubes provided is a 6mm (dia) tube. Insert the edge of tube to gas inlet port and connect it to a gas regulator 
which should be installed on the gas cylinder.    Or, install to the gas line in your lab.     

 

-Turn on the gas supply with the pressure set to 1 Bar (or 14.5 Psi)     

 

NOTE! 

To confirm that there are no leaks in the CO

  connections,  a “bubble check” is recommended. Apply soapy 

water to each fitting and check if any bubbles are generated.    If so, readjust the fitting.   
 
 
4. 

Connect the power cord. 

 

 

-Plug the power cord onto the power inlet on the back side of the incubator (refer to CONFIGURATION) 
-Plug the power plug into an outlet of the appropriate voltage. 
 

Summary of Contents for Incu-Shaker CO2 Mini

Page 1: ...1 OPERATING MANUAL...

Page 2: ...Table of Contents NO CONTENTS PAGE 1 SAFETY AND GENERAL PRECAUTION 3 4 2 FEATURES AND SPECIFICATIONS 5 3 CONTROL PANEL 6 4 INSTALLATION 7 5 CO2 INCUBATOR OPERATION 8 11 6 ORBITAL SHAKER OPERATION 11 1...

Page 3: ...he event of smoke or a burning smell immediately remove the power cord from the outlet 1 3 Precaution for use Do not attempt to disassemble this instrument If service is required please contact your l...

Page 4: ...0cm from the back wall Install the unit in the way that the power plug is easily accessible and can be easily pulled in case of danger Install the instrument on a flat and stable surface free from vib...

Page 5: ...Microprocessor On Off Control Humidity 70 80 at 37 CO2 Range 0 to 20 Accuracy 0 1 at 5 at 37 setting CO2 Increment 0 1 CO2 Sensor IR CO2 Sensor Shaker RPM 30 to 300 rpm RPM Accuracy 1 Increment 1 RPM...

Page 6: ...6 Shaker Status Pilot Lamp When Shaker is running this lamp is flashing 7 Alarm On Off Switch 8 Alarm Mute Button When pressed provides a10 minutes audible alarm delay 9 Heating Signal Shows the stat...

Page 7: ...cold air Direct sunlight An uneven surface or table A place with heavy vibration A place with little air ventilation space behind the incubator 4 2 Place the shelves and water container as shown in ch...

Page 8: ...t the desired value of Co2 density by adjusting UP or DOWN key c Press SET key again after inputting the value SAVE is shown up on LED screen as below Note Always press the SET CO2 key after adjusting...

Page 9: ...th channel the LED is back to temperature display b Second Calibration Setting Outer Door Temperature The purpose of this heater is to prevent water condensation from forming on the glass door caused...

Page 10: ...ay shows 4 then press up to set to 1 e Fifth Calibration Setting Heating control NOTE Channel 5 is to set heating control point and is designed to prevent a significant temperature overshoot This mode...

Page 11: ...nces So set the temperature at 5 higher than operating temperature or desired point If the SAFETY LED on the front panel is illuminated this switch has been activated and is limiting the temperature 6...

Page 12: ...humb screws 6 4 Shaker Error Message 1 This message rErrL represents a low speed speed error Check the platform to ensure that nothing is obstructing it s movement Check the set speed to make sure tha...

Page 13: ...l number label of the machine 5 Defective power switch check voltage at switch 6 5 Disconnecting inside Shaker Connector of the orbital shaker is located at upper right back wall of chamber see below...

Reviews: