5 Trouble shooting 

Problem 

Possible cause 

Approach 

no display 

auxiliary voltage missing 

check correct connection of auxiliary voltage, if neces-
sary rectify 

display "U<>LIMIT" 

measurement voltage out of 
range 

wrong settings for voltage 
measurement 

check correct connection of measurement voltage, if 
necessary rectify 

check settings in menu "SETUP / MEASUREMENT", if 
necessary rectify 

display "I<LIMIT" 

measurement current too small  check connection of CT, probably there is a break in the 

line 

CT ratio too high, if necessary replace CT 

remove short circuit link of the CT 

wrong display of cur-
rent or voltage 

wrong transformer ratio 
 
 

setting of Q offset 

check settings PT- or CT-ratio in menu "SETUP / 
MEASUREMENT", if necessary rectify 
 

correct setting of Q offset 

wrong power factor is 
displayed 

wrong settings at the regulator 
 
 
 
 

setting of Q offset 

check settings "NOMINAL VOLTAGE" and 
"CONNECTION" in menu "SETUP" and setting "PHASE 
COMPENSATION" in menu "EXTENDED", if necessary 
rectify 
 

correct setting of Q offset 

power factor doesn't 
change after switching 
on a step, step is 
switched off again 

CT mounted in wrong position 

 

check mounting position referring circuit diagram (cur-
rent of load and capacitors have to be measured!), if 
necessary rectify 

alarm "overcurrent" 

current higher than allowed 

check CT ratio, probably replace by suitable transformer 
type 

alarm "control" 

permanent overcompensation 

 

permanent undercompensation 

check settings 

check contactors, probably contact stick together 

check settings 

check capacitors, possibly fuse defective 

check dimensioning of the compensation unit 

reversed control mode  current or voltage clamps inter-

changed 

correct connection or adapt phase compensation 

single steps are not 
switched on or off 

wrong settings 

check, if referring steps are defined as fix steps (perma-
nently on or off) 

steps are detected as 
defective 

step defective 

check capacitor steps, probably fuse, capacitor or con-
tactor defective 

steps are not switched 
on 

step size  too large  

necessary reactive power smaller than switching thresh-
old of step size of the smallest step 

regulator still doesn't 
work proper 

 

contact Beluk 

 

Summary of Contents for BLR-CM

Page 1: ... BLR CM3phase Rev 08 2018 09 Beluk GmbH Taubenstrasse 1 86956 Schongau Germany Tel 49 0 8861 2332 0 Fax 49 0 8861 2332 22 E Mail blr beluk de Web http www beluk de Reference Manual Power Factor Controller BLR CM BLR CM3phase ...

Page 2: ...ocument release SW 2 5 1 19 09 08 MR 02 Editorial changings 21 07 10 MR 03 SW 2 7 0 incl datalogger 02 08 10 MR 04 AI for BLR CM3phase 13 09 10 MR 05 Editorial corrections 20 09 10 Le 06 Add menu items to Quickstart SETUP 16 07 18 SO 07 Removement of DQS Logo 26 09 18 SMi 08 Layout changes changes in the standard settings ...

Page 3: ...ll forward this battery to a recycling system Important information If the sign aside appears besides a text passage in the manual the reader is strongly advised to read the corresponding information as it is very important for the device usage It can contain safety advice or other information for the correct handling of the device If the information is disregarded the device may be inop erable or...

Page 4: ... 9 2 2 HARMONICS 10 2 3 STEPINFO 10 2 4 Quickstart SETUP 11 2 5 SETUP 14 2 6 MANUAL 27 2 7 DATALOGGER option DM 28 2 8 DEVICE INFO 29 3 Wiring diagrams BLR CM 30 3 1 BLR CM06 12R 30 3 2 BLR CM06 12T 31 3 3 BLR CM12RT 32 3 4 BLR CM06 12R 3A BLR CM3phase 33 3 5 BLR CM06 12T 3A BLR CM3phase 34 3 6 BLR CM12RT 3A BLR CM3phase 35 3 7 BLR CM06 12R HV 36 3 8 BLR CM06 12R 3AHV BLR CM3phase 36 3 9 BLR CM I ...

Page 5: ...emove short circuit links of the current transformer before commissioning 1 1 Auxiliary voltage At BLR CM auxiliary voltage has to be connected separately from measuring voltage The terminals for auxiliary voltage are marked with La Lb and 0 Terminal 0 has to be connected always La and Lb are different tapping points of the transformer to allow the usage with different voltage levels The detailed ...

Page 6: ...the functions can be found in the referring chapters 1 4 Control outputs BLR CM is available with up to 12 outputs Depending on the regulator type the outputs can be relay outputs transistor outputs or a mix between both types The indication of the type can be found on the rear sticker either with the type description or the symbols of the output clamps If you have got the regulator type with mixe...

Page 7: ... AC voltage for alarm system 50 250V AC terminals DI1 1 and DI1 2 Digital input can be active high or active low The function can be programmed in the menu SETUP ALARM DI INPUT 2 5 7 More details for the programming can be found in chapter ALARM See circuit diagram in chapter 3 9 1 6 2 Digital input for data logger synchronisation only option DM BLR CM with option DM is equipped with a digital inp...

Page 8: ...ous face indicates setting PFC OFF or PFC FREEZE Status columns left and right column are showing the status of the control exits Step 1 status off type NORMAL or FAST Step 2 status off type NORMAL blocked or FIX OFF Step 3 status off type FAULTY Step 4 status on type NORMAL or FAST Step 5 status on type FIX ON Step 6 status off type OFF not available or PFC OFF NORMAL blocked can be caused by dis...

Page 9: ... work inductive capacitive ULL voltage phase phase ULN voltage phase neutral THD U THD voltage I1 I2 I3 current THD I 1 THD I 2 THD I 3 THD current P1 P2 P3 active power for each phase Q1 Q2 Q3 reactive power for each phase S1 S2 S3 apparent power for each phase P total active power Q total reactive power S total apparent power deltaQ1 control deviation L1 in kvar deltaQ2 control deviation L2 in k...

Page 10: ...or normal regulation FIX OFF step is permanently switched off OFF step is permanently switched off an blend out FIX ON step is permanently switched in step will be switched off in critical situations like over and undervoltage overtemperature or excessive har monics FAST step is used for real time algorithm More information can be found in chapter 2 5 4 2 and 2 5 5 FAULTY the step is detected as d...

Page 11: ...inuously corrected with every switching operation A second value is saved after the first ten switch cycles of each step after a reset of step database This value indicated the original available STEPVALUE This value is used to calculate the percentage of actual step value to original step value This percentage gives very simple information about derating of the capacitor banks When automatic step...

Page 12: ...e maximum number of switching operations during AI is 10 per exit normally between 2 and 5 AI is taking care about the setting of discharge time for each exit If there is a very long discharge time necessary AI will take a certain time The following messages from AI are possible ALARM AI OK AI is finished completely Please check if all used exits are shown with their number in the display and plea...

Page 13: ...ction can be defined separatly You can select between the following functions NORMAL step is used for normal regulation algorithm OFF step is permanently switched of an blend out in step indication FIX OFF step is permanently switched off FIX ON step is permanently switched on step is supervised and also switched off in critical situations The step type Fast in only available for BLR CM with trans...

Page 14: ...ed into logical groups In these groups you can find parameters which are also in Quickstart SETUP The following points explain the settings 2 5 1 CHANGE LANGUAGE Standard version of BLR CM is supporting English German and French 2 5 2 START AI See Chapter 2 4 5 2 5 3 MEASUREMENT 2 5 3 1 CT FACTOR The CT FACTOR is the ratio of current transformer e g 1000 5 ratio 200 At BLR CM3phase the CT Factor i...

Page 15: ...d mains quality 2 5 3 6 PHASE COMPENSATION The phase compensation enables the user to connect the current and voltage measurement channels in any way This compensation angle complies with the phase angle between connected active current and voltage The following table shows the settings for some different connection types This setting has to be made correct because otherwise correct regulation is ...

Page 16: ...discharging time is a blocking time becom ing active after switching off a step As long as this time is running display of in the step indication this step is not available for the regulation Discharging time should be adapted to the capacitor discharging unit For step exits which are switching thyristor switches discharging time can be reduced to the zero 2 5 4 2 STEP TYPE For every single step i...

Page 17: ...o be programmed for each phase individually A three phase capacitor with 25kvar has to be programmed with 8 3kvar for each phase 2 5 4 5 STEP RESET Selecting this point all step sizes can be reset individually 2 5 5 CONTROL General explanations for a better understanding Target of compensation BLR CM is using two parallel working regulation algorithms The type of steps defines the algorithm by whi...

Page 18: ...vailable step the all further steps are switched in intervals of two seconds If the setting of switch interval is less two seconds all further steps are switched in intervals of one second Regulation mode real time algorithm After measuring one cycle of mains voltage the control deviation is calculated and all necessary steps are switched in one operation The time from end of measuring to generati...

Page 19: ...y have the same number of switch cycles At selection of suitable step for next switching operation the values of switch cycles which are saved in step database are compared A balanced attrition of contactors and capacitors is assured by this 2 5 5 1 CONTROL ON FREEZE OFF ON Automatic control is running FREEZE Automatic control is stopped status of exit relays is frozen OFF Automatic control is sto...

Page 20: ...c step size recognition b When recognition of defective steps is not wished c When capacitor contactors are switching with a delay of more than 200msec Step recognition ON Step sizes are detected and corrected automatically during normal operation Step recognition ON is the factory setting It allows monitoring of capacitor sizes and gives alarms when they are faulty Step sizes which are programmed...

Page 21: ...switch interval is only valid for the first switching operation and the following steps are connected in short intervals 2 5 5 13 Q OFFSET OFFSET of reactive power in kvar This feature allows compensating a permanent reactive load which cannot be meas ured e g a transformer The offset of reactive power affects the readings of the following measuring values current reactive power control deviation ...

Page 22: ...ng there is no limitation 2 5 5 18 FAST CONTROL AVERAGE Q The number of mains cycles which are used to build the average of control deviation Start for building the average is after the measuring break is finished 2 5 5 16 2 5 5 19 FAST CONTROL SYNC IMP YES the trigger pulse for switching the thyristor switches is synchronous to the zero crossing of the mains voltage rising sinus This can cause a ...

Page 23: ...uts inactive active Cos φ ΔQ Display of power factor and control deviation Cos φ valid Target cos φ 1 or 2 Showing of power factor and of the active target power factor e g tariff switching with digital input 2 5 6 2 Contrast The contrast of the LCD display can be adjusted by pushing the keys After leaving this submenu the setting is stored automatically 2 5 6 3 Password By pushing the keys the pa...

Page 24: ...D I exceeds the adjusted limit between 1 and 99 9 Overload P Trigger amount of P exceeds the adjustable limit between 1kW and 99 9MW Overload Q Trigger amount of Q exceeds the adjustable limit between 1kvar and 99 9Mvar P export Trigger alarm will be triggered as soon as kW export is recognized Temp1 Temp2 Trigger ambient temperature exceeds the adjusted limit DI Input Trigger voltage signal at te...

Page 25: ...act can be set to N O or N C function Max fuse 6A breaking capacity 250V AC 5A Display Shows Alarm in Display Control freeze All steps are frozen control is stopped Control off All steps are switched off control is stopped Cos phi 2 Fast Control immediate switching off only available for fast steps and Harmonic U alarm In the drawing stated below is showed how the enabled alarm shown on display M ...

Page 26: ...uipped with data logger To use data logger some settings are required These settings are date time storage interval synchronization to digital input and trigger of digital input 2 5 9 1 Date and time Format of date dd mm yy Format of time hh mm seconds are running in a separate line 2 5 9 2 STORAGE INTERVAL The storage interval can be set from 1 to 720 minutes A setting of 0 stops data logging of ...

Page 27: ...0 6 RESET APF Reset of average PF 2 5 10 7 RESET T MAX Reset of the temperature maximum which was measured 2 5 10 8 DATALOGGER DELETE Deletes all saved values in data logger 2 6 MANUAL To enter in manual mode please select manual in main menu and push for 3 seconds The automatic control is stopped and the exits can be switched manually By the means of the key the referring step can be selected Cha...

Page 28: ...alue in the moment when alarm comes the bottom line shows the threshold level of alarm By pushing the key again you get information about the current and voltage in the moment of alarm 2 7 3 Logging of measurements BLR CM can log up to 3072 sets of measurements with date and time The interval can be set from 1 minute to 720 minutes 0 stop logging Alternatively there can be use the digital input 3 ...

Page 29: ...Reference Manual BLR CM BLR CM3phase Rev 08 2018 09 29 2 8 DEVICE INFO Device type e g BLR CM Softwareversion e g VER 02 07 00 FLG e g 3I MB DL ...

Page 30: ...ence Manual BLR CM BLR CM3phase Rev 08 2018 09 30 3 Wiring diagrams BLR CM 3 1 BLR CM06 12R B LR CM K1 K1 B LR CM K1 L1 L2 L3 L1 L2 L3 N PE N PE Einspeisung S upply Einspeisung S upply Last Load Last Load K1 ...

Page 31: ... CM3phase Rev 08 2018 09 31 3 2 BLR CM06 12T B LR CM B LR CM T riggereingang T riggerinput BEL T SXX T riggereingang T riggerinput BEL T SXX L1 L2 L3 L1 L2 L3 N PE N PE Einspeisung S upply Einspeisung S upply Last Load Last Load ...

Page 32: ...hase Rev 08 2018 09 32 3 3 BLR CM12RT B LR CM B LR CM T riggereingang T riggerinput BEL T SXX T riggereingang T riggerinput BEL T SXX L1 L2 L3 L1 L2 L3 N PE N PE Einspeisung S upply Einspeisung S upply Last Load Last Load K1 K1 K1 K1 ...

Page 33: ...nual BLR CM BLR CM3phase Rev 08 2018 09 33 3 4 BLR CM06 12R 3A BLR CM3phase B LR CM B LR CM K1 K1 B LR CM B LR CM K1 K1 L1 L2 L3 L1 L2 L3 N PE N PE Einspeisung S upply Einspeisung S upply Last Load Last Load K1 K1 ...

Page 34: ...e Rev 08 2018 09 34 3 5 BLR CM06 12T 3A BLR CM3phase B LR CM B LR CM T riggereingang T riggerinput BEL T SXX T riggereingang T riggerinput BEL T SXX L1 L2 L3 L1 L2 L3 N PE N PE Einspeisung S upply Einspeisung S upply Last Load Last Load ...

Page 35: ... 08 2018 09 35 3 6 BLR CM12RT 3A BLR CM3phase B LR CM B LR CM T riggereingang T riggerinput BEL T SXX T riggereingang T riggerinput BEL T SXX L1 L2 L3 L1 L2 L3 N PE N PE Einspeisung S upply Einspeisung S upply Last Load Last Load K1 K1 K1 K1 ...

Page 36: ...M BLR CM3phase Rev 08 2018 09 36 3 7 BLR CM06 12R HV B LR CM K1 L1 L2 L3 N PE Einspeisung S upply Last Load K1 230V 3 8 BLR CM06 12R 3AHV BLR CM3phase B LR CM K1 B LR CM K1 L1 L2 L3 N PE Einspeisung S upply Last Load K1 230V ...

Page 37: ...Reference Manual BLR CM BLR CM3phase Rev 08 2018 09 37 3 9 BLR CM I O 3 10Synchronizing of datalogger L 10 30V DC GND pulse for synchronization ...

Page 38: ... on freeze off Cos phi 1 1 00 0 60 i 1 00 0 70c Cos phi 2 i 0 95 0 60 I 1 00 0 70c Switch interval 10s 1 0s 1200 0s Switch interval step exchange 2s 1 0s 1200 0s Asymmetry factor 1 127 to 127 Step recognition on on off Switch cycle balancing no yes no Switch cycle balancing 10 1 15 Step exchange yes yes no Control sensitivity 60 55 100 Control Auto Auto LIFO progressive combi filter Q Offset 0 kva...

Page 39: ...DO D CP O F Limit overload Q 1 00kvar 1 0 99999 9 kvar P export alarm disabled CP disabled M DO D CP O F Temp1 alarm DO disabled M DO D CP O F Limit temperature 1 25 C 20 C temp2 deltaT temp hysteresis Temp1 1 0 C 0 5 C 9 9 C Temp2 alarm M D O disabled M DO D CP O F Limit temperature 2 70 C temp2 70 C deltaT temp hysteresis Temp2 1 0 C 0 5 C 9 9 C DI Input alarm CP disabled M DO D CP O F DI trigge...

Page 40: ... menu EXTENDED if necessary rectify correct setting of Q offset power factor doesn t change after switching on a step step is switched off again CT mounted in wrong position check mounting position referring circuit diagram cur rent of load and capacitors have to be measured if necessary rectify alarm overcurrent current higher than allowed check CT ratio probably replace by suitable transformer t...

Page 41: ...nization of data logger Digital input DI1 1 DI1 2 50 250V AC programmable Digital output N O potential free programmable Max fuse 6A breaking capacity 250V AC 5A Data logger optional 2MB Interface optional RS485 Modbus RTU protocol Slave Ambient temperature operation 0 C 70 C storage 20 C 85 C Humidity 0 95 without moisture condensation Overvoltage class II pollution degree 3 DIN VDE 0110 Teil 1 I...