1.7 CONTROLS
5-pole DIP switch 
(Suppressing the link states)

With a DIP switch on the front panel of the
RS2-xTX/xFX EEC the indication of the link
states by the indicator contact can be sup-
pressed port by port. Using the switches
LA1 to LA5 (LA1 to LA4 on RS2-4TX EEC),
the indication of the link states can be sup-
pressed. 
Switch position „ON“: the indication of the
link state is not suppressed, that is the indi-
cator contact indicates the unvalid link.
State of delivery: LA1 to LA5 (LA1 to LA4 on 
RS2-4TX EEC) in position „ON“ (position 1).

Fig. 6: 5-pole DIP switch to suppress the

indication of the link states

2. Configuration

2.1 CONNECTING DTE AND OTHER
NETWORK SEGMENTS

It is possible to connect up to three DTEs or
other TP/TX network segments to the
10/100 Mbit/s ports of the RS2-3TX/2FX…
using twisted pair cabling. Two further data
terminal equipments or optical network
components can be connected at 100 Mbit/s
to the optical ports using fiber optic cable.
It is possible to connect up to four DTEs or
other TP/TX network segments to the
10/100 Mbit/s ports of the RS2-4TX/1FX…
using twisted pair cabling. One further data
terminal equipment or optical network com-
ponent can be connected at 100 Mbit/s to
the optical port using fiber optic cable. 
It is possible to connect up to four DTEs or
other TP/TX network segments to the
10/100 Mbit/s ports of the RS2-4TX EEC
using twisted pair cabling.
(ref. Fig. 4).

3. Assembly, startup procedure

and dismantling

3.1 UNPACKING, CHECKING

Check whether the package was deliver-

ed complete (see scope of delivery).

Check the individual parts for transport

damage.

z

Warning!

Use only undamaged parts!

LA1

0

1

LA3

LA2

LA4

Port 1

Port 3

Port 2

Port 4

Suppress message
about link status
via indicator contact
(RS2-4TX EEC)

LA1

0

1

LA5

LA3

LA2

LA4

Port 1

Port 5

Port 3

Port 2

Port 4

Suppress message
about link status
via indicator contact
(RS2-*TX/*FX(-SM) EEC)

3.2 ASSEMBLY

The equipment is delivered in a ready-to-
operate condition. The following procedure
is appropriate for assembly:

Pull the terminal block off the RS2-

xTX/xFX EEC and wire up the supply volta-
ge.

Fit the RS2-xTX/xFX EEC on a 35 mm

standard DIN rail to DIN EN 50 022.

Attach the upper snap-on slide bar of

the RS2-xTX/xFX EEC to the standard DIN
rail and press it down until it locks into posi-
tion.

Fit the signal lines.

Notes:

– The front panel of the RS2-xTX/xFX EEC is

 grounded via a separate ground connec-
tion.

– Do not open the housing.

– The shielding ground of the twisted pair

cables is electrically connected to the front
panel.

Fig. 7: Assembling the RS2-xTX/xFX EEC

3.3 STARTUP PROCEDURE

You start up the RS2-xTX/xFX EEC by

connecting the supply voltage via the 5-pin
terminal block.

3.4 DISMANTLING

To take the RS2-xTX/xFX EEC off the

ISO/DIN rail, insert a screwdriver horizontal-
ly under the housing into the locking slide,
pull it (without tipping the screwdriver)
downwards and lift the RS2-xTX/xFX EEC
upwards.

4. Further support

In the event of technical queries, please talk
to the Hirschmann contract partner respon-
sible for looking after your account or direc-
tly to the Hirschmann office. You can find
the addresses of our contract partners on
the Internet 
http://www.hirschmann.com

You can contact us

in the EMEA region at
Tel.: +49 (0)1805 14-1538 
E-mail: [email protected]

in the America region at
Tel.: +1 (717) 217-2270
E-mail: [email protected]

in the Asia-Pacific region at
Tel.: + 65 6854 9860
E-mail: [email protected]

www.hicomcenter.com gives you an up-to-
date overview of training courses about
technology and products.

Summary of Contents for HIRSCHMANN RS2-3TX/2FX EEC

Page 1: ...e four 10 100 MBit s twisted pair ports 10 100BASE TX RJ45 connectors and one 100 MBit s fiber optic port 100BASE FX Duplex SC connector or ST connector on R2 4TX 1FX ST EEC The RS2 4TX EEC module has...

Page 2: ...components recommen ded or approved by Hirschmann The product can only be operated correctly and safely if it is transpor ted stored installed and assembled properly and correctly Furthermore it must...

Page 3: ...Li LCable and b max Cable Length Ca Ci CCable The lower value of a and b is to apply CableL inductance per unit length of used cable CableC capacitance per unit length of used cable Other C parameters...

Page 4: ...an 119 V Connectors shall be connected or dis connected exclusively in dead voltage state DIP switches shall be switched exclusi vely in dead voltage state Safety Guidelines Environment z Warning The...

Page 5: ...a cross over or straight cable 1 3 SPECIFIC FUNCTIONS OF THE F O INTERFACE Link control The RS2 xTX xFX EEC monitors the connec ted F O line for interrupts using idle signals during frame pauses in a...

Page 6: ...wer P1 and P2 LEDs for data link status DA STAT 1 to 5 FAULT LED LEDs for power P1 and P2 LEDs for data link status DA STAT 1 to 5 on the RS2 4TX EEC FAULT LED 2 3 4 DA STAT 1 2 P 1 DA STAT FAULT 2 3...

Page 7: ...3 Port 2 Port 4 Suppress message about link status via indicator contact RS2 4TX EEC LA1 0 1 LA5 LA3 LA2 LA4 Port 1 Port 5 Port 3 Port 2 Port 4 Suppress message about link status via indicator contact...

Page 8: ...al EN 61000 4 5 Test level 2 Surge voltage asymmetrical EN 61000 4 5 Test level 3 Cable based RF faults EN 61000 4 6 Test level 3 Radiated emission EMC EN 55022 Class A CFR 47 Part 15 Class A Stabilit...

Page 9: ...FX SM EEC 943 772 001 Rail Switch RS2 4TX EEC 943 819 001 Rail Switch RS2 4TX 1FX EEC 943 773 001 Rail Switch RS2 4TX 1FX ST EEC 943 119 002 Rail Switch RS2 4TX 1FX SM EEC 943 774 001 Accessories Ethe...

Page 10: ...Automation and Control GmbH Stuttgarter Stra e 45 51 72654 Neckartenzlingen Germany Tel 49 0 1805 14 1538 Fax 49 0 7127 14 1551 E mail hac support belden com Internet http www hirschmann com 039 651 0...

Reviews: