Examples: Unstable ground, gate support posts or wind region C, etc.
Where a post extension is required. the 2 halves must be flexed open and sleeved over the exterior of the
post base by 200mm minimum, then fastened with the supplied tek screws
at a minimum 100mm spacings along the flange edges (see picture below).
We recommend digging your hole first, then measuring the depth of the hole and sleeving
the post extension onto the base of the post to suit the hole depth.
Before panel insertion the post must be core filled with concrete to cover the post
extension internally.
Note: The pictures below are only showing one half of the post extension being fitted,
the post should be turned over and the other half fitted also.
The 2 halves of the post extension will not quite meet in the middle of the post, this is to
allow a small amount of concrete to enter the centre of the post before actual core filling.