7.2 Assembly work
For assembly work to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must have
been completed.
Prerequisites
Tools
Material
Protective equipment
• Screwdriver - cross-head
size 2.5
mm
• Additional installation and
operating manual for the
accessories used
• Sealing materials such as e.g. PTFE
tape (EN 837-2)
•
Protective gloves (fluid-
resistant)
•
Safety goggles with side shields
•
Hearing protection
•
Respiratory protection,
protection class FFP 3
•
Safety footwear
Preparation of installation
1.
Remove the dust cap from the following threads:
•
Inlet and outlet on the filter head
•
Condensate drain on the filter base
2.
Depressurise the pipelines or relevant pipe section.
3.
Heed the filter dimensions and make sure there is sufficient space for assembly.
See “6. Dimensions” on Page 24.
4.
Pipes must be able to bear the additional weight of the filter. Additional fixings must be mounted if necessary.
5.
Pipes must be free of contamination and corrosion. Check pipe thread for damage. Defective pipes must be
replaced immediately.
6.
Pipes must be free of mechanical stress and corrosion. Compensate any vibrations which occur by using
vibration dampers.
7.
Only use fittings which are suitable for this pressure and temperature range. The pipe threads must match
those of the filter head.
8.
Execute the condensate drain in such a way that no compressed gas or condensate can escape to the
surrounding of the filter. The condensate to be discharged should be routed to a treatment system conforming
to law (e.g. ÖWAMAT
®
or BEKOSPLIT
®
).
Installation and operation manual
CLEARPOINT
®
3
eco
coalescing filter
27 | 56