4
3.2 Installation Procedure
Fig 2 illustrates the instrument installation
procedure.
a.
Remove the instrument terminal cover by
unscrewing the two captive 'A' screws.
b.
Mount the instrument on a flat surface and
secure with two M6 screws through the 'B'
holes. Alternatively use one of the mounting
kits described in section 5.3
c.
Remove the temporary dust seals from the
three cable entries and install the required
glands, conduit fittings or blanking plugs.
Note: The temporary dust seals fitted for
transit do not maintain the IP66 protection of
the BA614DF-F enclosure.
d.
Connect the field wiring to the terminals as
shown in Fig 3.
e. Replace the instrument terminal cover and
evenly tighten the two 'A' screws.
Fig 2 BA614DF-F installation procedure
3.3 EMC
The BA614DF-F complies with the requirements of
the European EMC Directive 89/336/EEC. For
specified immunity, all wiring should be in
screened twisted pairs with the screens earthed at
one point.
Fig 3 Dimensions and terminal connections