Commissioning
EL34x3
75
Version: 4.4
Fig. 62: PLC Control logged in, ready for program startup
The PLC can now be started via "Online" → "Run", F5 key or
.
5.1.2
TwinCAT 3
Startup
TwinCAT makes the development environment areas available together with Microsoft Visual Studio: after
startup, the project folder explorer appears on the left in the general window area (cf. "TwinCAT System
Manager" of TwinCAT 2) for communication with the electromechanical components.
After successful installation of the TwinCAT system on the PC to be used for development, TwinCAT 3
(shell) displays the following user interface after startup:
Summary of Contents for EL3413-0000
Page 1: ...Documentation EL34x3 3 phase power measurement terminal 4 4 2019 03 28 Version Date ...
Page 2: ......
Page 6: ...Table of contents EL34x3 6 Version 4 4 ...
Page 47: ...Installation EL34x3 47 Version 4 4 Fig 33 Other installation positions ...
Page 91: ...Commissioning EL34x3 91 Version 4 4 Fig 88 Incorrect driver settings for the Ethernet port ...