Commissioning
EL34x3
71
Version: 4.4
Select the PLC configuration "PLC_example.tpy" in the browser window that opens. The project including the
two variables identified with "AT" are then integrated in the configuration tree of the System Manager:
Fig. 56: PLC project integrated in the PLC configuration of the System Manager
The two variables "bEL1004_Ch4" and "nEL2008_value" can now be assigned to certain process objects of
the I/O configuration.
Assigning variables
Open a window for selecting a suitable process object (PDO) via the context menu of a variable of the
integrated project "PLC_example" and via "Modify Link..." "Standard":
Fig. 57: Creating the links between PLC variables and process objects
In the window that opens, the process object for the variable “bEL1004_Ch4” of type BOOL can be selected
from the PLC configuration tree:
Summary of Contents for EL3413-0000
Page 1: ...Documentation EL34x3 3 phase power measurement terminal 4 4 2019 03 28 Version Date ...
Page 2: ......
Page 6: ...Table of contents EL34x3 6 Version 4 4 ...
Page 47: ...Installation EL34x3 47 Version 4 4 Fig 33 Other installation positions ...
Page 91: ...Commissioning EL34x3 91 Version 4 4 Fig 88 Incorrect driver settings for the Ethernet port ...