200646_01
10
1
The electrical connection to the mains supply may be made via either a fused spur or an
unswitched three-pin socket and plug. The supply must be fitted with a 3A fuse.
2
The appliance is supplied with 2.5 metres of three-core mains cable pre- wired. This
should be routed to the power point as inconspicuously as possible - i.e. chased into the
plaster.
3
The electrical connections to the switches are all pre-wired and the only other connections
required are in the fan box, which are explained in section 5 of these instructions.
11
GAS SOUNDNESS CHECK.
Once the correct operation of the controls has been proved a gas soundness test must be
carried out in accordance with BS 6891
.
12
TESTING THE OPERATION OF THE FAN
1
The following procedure tests the correct operation of the fan and pressure switch.
2
Connect the electrical mains supply to the appliance, turn on the gas supply and switch on
the fire.
3
From outside, block the flue opening on the fan unit. Initially the fan should be heard to
speed up to try and over come the blockage. After about 5 seconds the fan will switch off.
Remove the blockage, return indoors and check that the fire has gone out. The system
can now be restarted.
13
FITTING THE CERAMIC COMPONENTS
WARNING.
This product uses fuel effect pieces containing Refractory Ceramic Fibre (RCF),
which are man-made vitreous silicate fibres along with fibrous glass and mineral
wool. Excessive exposure to these materials may cause temporary irritation to
eyes, skin and respiratory tract, consequently, it makes sense to take care when
handling these articles to ensure that the release of dust is kept to a minimum.
CAUTION
All the ceramic components are fragile and should be handled with
care.
1
Fit the ceramic pieces as shown in Figure 10.
Laying the Coals (Coal only models)
FIGURE 10
FIGURE 11