See Figure 3 and clearance information in Section 9
and Table 2 for additional information.
Design the duct work according to methods given by
the Air Conditioning Contractors of America (ACCA).
When duct runs through unheated spaces, it should be
insulated with a minimum of one-inch of insulation.
Use insulation with a vapor barrier on the outside of
the insulation. Flexible joints should be used to
connect the duct work to the equipment in order to
keep the noise transmission to a minimum.
A one-inch clearance to combustible material for the
first three feet of duct attached to the outlet air frame is
required. See Wall Mounting Instructions and Figures
2, 2A, 3 and 3A for further details.
Ducts through the walls must be insulated and all joints
taped or sealed to prevent air or moisture entering the
wall cavity.
Some installations may not require any return air duct.
A metallic return air grille is required with installations
not requiring a return air duct. The spacing between
louvers on the grille shall not be larger than 5/8 inch.
Any grille that meets with the 5/8 inch louver criteria
may be used. It is recommended that Bard Return Air
Grille or Return Filter Grille be installed when no
return duct is used. Contact distributor or factory for
ordering information. If using a return air filter grille,
filters must be of sufficient size to allow a maximum
velocity of 400 fpm.
NOTE: If no return air duct is used, applicable
installation codes may limit this cabinet to
installation only in a single story structure.
4.
HIGH ALTITUDE APPLICATIONS
Ratings of gas utilization equipment are based on sea
level operation and need not be changed for operation
at elevations up to 6,000 feet. For operation at
elevations above 6,000 feet and in the absence of
specific recommendations from the local authority
having jurisdiction, equipment ratings shall be reduced
as specified in Section 21.
5.
TRANSPORTATION DAMAGE
All units are packed securely in shipping container.
All units should be carefully inspected upon arrival for
damage. In the event of damage, the consignee should:
1. Note on delivery receipt of any damage to container.
2. Notify carrier promptly, and request an inspection.
3. In case of concealed damage, the carrier must be
notified as soon as possible within 15 days after
delivery.
4. Claims for any damage, apparent or concealed,
should be filed with the carrier, using the following
supporting documents:
A. Original Bill of Lading, certified copy, or
indemnity bond.
B.
Original paid freight bill of indemnity in lieu
thereof.
C.
Original invoice or certified copy thereof
showing trade and other discounts or
deductions.
D. Copy of the inspection report issued by
carrier’s representative at the time damage is
reported to carrier.
6. INSTALLATION
Size of unit for proposed installation should be based
on heat loss/heat gain calculations made according to
methods of Air Conditioning Contractors of America
(ACCA). The air duct should be installed in
accordance with the Standards of the National Fire
Protection Association for the Installation of Air
Conditioning and Ventilating Systems of Other Than
Residence Type, NFPA No. 90A, and Residence Type
Warm Air Heating and Air Conditioning Systems,
NFPA No. 90B. Where local regulations are at a
variance with instructions, installer should adhere to
local codes.
WARNING
In all cases, there must be a metal duct
connection made to the supply air flange, and
a one inch clearance to combustibles must be
maintained to this duct connection.
For free blow applications, a metal sleeve
must be used in the wall opening itself, again
maintaining a one inch clearance to
combustibles.
Failure to use the sheet metal can cause
fire resulting in property damage, injury, or
death.
Summary of Contents for WG242DA
Page 13: ...Manual 2100 376L Page 13 of 81 FIGURE 2A MOUNTING INSTRUCTIONS FOR WG42 WG48 AND WG60...
Page 16: ...Manual 2100 376L Page 16 of 81 FIGURE 6 COMMON WALL MOUNTING INSTALLATIONS...
Page 22: ...Manual 2100 376L Page 22 of 81 FIGURE 11 LOW VOLTAGE WIRING...
Page 23: ...Manual 2100 376L Page 23 of 81 FIGURE 11A LOW VOLTAGE WIRING...
Page 24: ...Manual 2100 376L Page 24 of 81 FIGURE 12 GAS PIPE CONNECTION...
Page 56: ...Manual 2100 376L Page 56 of 81 WG242DA 230 208 60 1...
Page 57: ...Manual 2100 376L Page 57 of 81 WG242DA WG362DA 230 208 60 1...
Page 58: ...Manual 2100 376L Page 58 of 81 WG242DB 230 208 60 3...
Page 59: ...Manual 2100 376L Page 59 of 81 WG242DB WG362DB 230 208 60 3...
Page 60: ...Manual 2100 376L Page 60 of 81 WG243DC 460 60 3...
Page 61: ...Manual 2100 376L Page 61 of 81 WG243DC 460 60 3...
Page 62: ...Manual 2100 376L Page 62 of 81 WG302DA 230 208 60 1...
Page 63: ...Manual 2100 376L Page 63 of 81 WG302DA WG482DA WG602DA 230 208 60 1...
Page 64: ...Manual 2100 376L Page 64 of 81 WG302DB 230 208 60 3...
Page 65: ...Manual 2100 376L Page 65 of 81 WG302DB WG482DB WG602DB 230 208 60 3...
Page 66: ...Manual 2100 376L Page 66 of 81 WG303DC 460 60 3...
Page 67: ...Manual 2100 376L Page 67 of 81 WG303DC 460 60 3...
Page 68: ...Manual 2100 376L Page 68 of 81 WG362DA 230 208 60 1...
Page 69: ...Manual 2100 376L Page 69 of 81 WG362DB 230 208 60 3...
Page 70: ...Manual 2100 376L Page 70 of 81 WG363DC 460 60 3...
Page 71: ...Manual 2100 376L Page 71 of 81 WG363DC 460 60 3...
Page 72: ...Manual 2100 376L Page 72 of 81 WG423DA 230 208 60 1...
Page 73: ...Manual 2100 376L Page 73 of 81 WG423DA 230 208 60 1...
Page 74: ...Manual 2100 376L Page 74 of 81 WG423DB 230 208 60 3...
Page 75: ...Manual 2100 376L Page 75 of 81 WG423DB 230 208 60 3...
Page 76: ...Manual 2100 376L Page 76 of 81 WG424DC 460 60 3...
Page 77: ...Manual 2100 376L Page 77 of 81 WG424DC 460 60 3...
Page 78: ...Manual 2100 376L Page 78 of 81 WG482DA WG602DA 230 208 60 1...
Page 79: ...Manual 2100 376L Page 79 of 81 WG482DB WG602DB 230 208 60 3...
Page 80: ...Manual 2100 376L Page 80 of 81 WG483DC WG603DC 460 60 3...
Page 81: ...Manual 2100 376L Page 81 of 81 WG483DC WG603DC 460 60 3...