Finished Grade

3.  Install anchor plate and bolt assembly flush 

with the finished grade. 

 

1 1/2”

1.  Adjusted anchor bolts to project at least 1-1/2” 

using the four (4) 1/4-20 nuts to the top of the 

plate. The four (4) nuts can be left in place 

while concrete is poured.

4.  With the conduits in place and the anchor 

plate properly positioned, secured and leveled, 

concrete may be poured.

2.  Run conduit inside of the anchor plate center 

hole prior to pouring concrete.

YKB Anchor Kit Installation

5.  The fixture may be installed by removing the 

four (4) 1/4-20 nuts and re-using them to 

secure the fixture mounting base assembly. 

Trim conduit as needed.

 

Soil Prep

Conduit

trench

B.  Dig hole 13” wide and 24” deep.

Conduit

Trench

Excavate for 

anchor bolts

C.  Prep soil according to DIG-IT Guide.

A.  Determine Soil Type by referencing DIG-IT 

Guide. Prep soil according to DIG-IT Guide.

IMPORTANT SAFETY INFORMATION LISTED ON REVERSE

READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS

40429 Brickyard Drive • Madera, CA 93636 • USA

559.438.5800 • FAX 559.438.5900 

www.bklighting.com • [email protected]

B-K LIGHTING

RELEASED DATE

09/03/2021

REFERENCE NUMBER

INS-2850-00

Yukon Bollard

Installation Instructions

Reviews: