1. 

INTRODUCTION 

The  semiautomatic  machines  of  the  Vitro  X1  series  are  destined  for  the  elaboration  of 

espresso  coffee  and  soluble  drinks  consisting  of  the  mixing  of  warm  water  with  product  in 

powder or granulated.  

 

 

In  the  rest  of  the  book,  and  for  major  briefness,  the  elements  that  are 
indicated will be named like: 

The machines of the series Vitro X1: machine or machines. 

The coffee brewer or coffee group: group or brewer. 

The electroválvulas: EV. 

1.1.  DEFINITIONS 

Espresso coffee: Infusion of coffee elaborated according to the following conditions: 

-

 

7 g of ground coffee. 

-

 

The temperature of the infusion water between 92º C and 96º C. 

-

 

The water pressure at 8 kg/cm²La presión del agua de erogación a 9 kg/cm². 

-

 

The infusion time of the coffee between 12 and 20 seconds. 

-

 

The volume of water in the infusion 50 ml. 

Infusion:  this  is  the  name  given  to  the  process  of  passing  hot  water  through  the  ground 

coffee to extract its oils and essences. 

-

 

Volumetric  infusion:  when  the  process  of  infusion  uses  a  constant  volume  of 

water. 

Coffee tablet: the residual compressed coffee grounds after the infusion process. 

Programming mode: when the machine is ready for any of its functions or parameters to be 

programmed.  

Working mode: when the  machine is in the  working state  and ready to prepare any  of the 

services it offers. 

 

 

 

 

 

Summary of Contents for VITRO X-1

Page 1: ...Technical information VITRO X1 ...

Page 2: ... MODELS 1 3 PRINCIPAL TECHNICAL CHARACTERISTICS 2 DESCRIPTION OF COMPONENTS 2 1 PRINCIPAL COMPONENTS 2 2 HYDRAULIC CIRCUIT 3 INSTALLATION AND SWITCHING ON 3 1 INSTALLATION 3 2 WATER CONNECTION 3 3 ELECTRIC CONNECTION AND START UP 3 4 FILLING CANISTERS 3 5 FILLING BOILER 4 ERROR MESSAGES ON DISPLAY 5 CONTROL POINTS 6 CLEANING AND MAINTENANCE 7 WORKING CONDITIONS AND NORMS 8 DIMENSIONS ...

Page 3: ...Technical Principles 1ª review UK 12 2020 3 ...

Page 4: ...llowing conditions 7 g of ground coffee The temperature of the infusion water between 92º C and 96º C The water pressure at 8 kg cm La presión del agua de erogación a 9 kg cm The infusion time of the coffee between 12 and 20 seconds The volume of water in the infusion 50 ml Infusion this is the name given to the process of passing hot water through the ground coffee to extract its oils and essence...

Page 5: ...nstant It grinds the coffee when it is ordered Products that the machine can dispense Model Coffee beans Chocolate Milk Hot water X1 Espresso Yes Yes Yes Yes The water temperature is programmable The ground coffee dose is programmable between 5 g and 8 g Water pump for water pressure incorporated in the machine Volume dosage of water in the different espresso coffee services is programmable Electr...

Page 6: ...Technical Principles 1ª review UK 12 2020 6 2 DESCRIPTION OF COMPONENTS 2 1 MAIN COMPONENTS ...

Page 7: ... product is Capacity in grams Product Vitro XE 2 Milk 600 Chocolate 800 A3 Product extractor This motor will move the spindle inside the canister to move instant poder out to the mixing bowls These motors are from Componenti Motor manufacturer Componenti Voltage 24 V cc Speed 140 rpm A4 Beaters Mixers Whippers The mixing of the products with hot water from the boiler is done with these elements B1...

Page 8: ... shown in the pictures next to this text As shown in the pictures grey inside base must be moved to the motor If not the base will be in friction provoking a break in the motor The tool reference 10040130 can be used as a help A5 Extractor Extractor The steam and vapour that is generated by the beaters can reach the product containers and if they become damp they form lumps in the powder This cons...

Page 9: ...e that adjusts the grinding point will have an effect on ground coffee granulometry but also on ground coffee Flow Remember that grinder is controlled by time 3 seconds of coarse coffee will make more grams than 3 seconds of thin coffee It can be said that turning right or left the grinding point handle will vary the amount of coffee ground for your Service In that case the grinding time set in fu...

Page 10: ... it has been turned out of the machine Just put it in its place and fix its two anchor levers the engine of the group will position it correctly C1 Piston C2 Group C3 Filter C4 Holding handle C5 Position microswitch C6 Group movement handle C7 Group motor AZK 30 variable coffee brewer The AZK 30 group is variable and automatic positioning from 7 gr to 14 gr thanks to a 24 VDC position control moto...

Page 11: ...ee cakes coming from coffee group It has capacity for 60 cakes After 60 coffee services the display will show a message asking to empty the deposit If the counter want to be disabled use your laptop and the Configurator app to modify the settings cmq file Tray of liquids collects all the liquid residues that the machine generates It has capacity for 1 litre Both parts can be removed with the machi...

Page 12: ...e to pass through the compressed ground coffee in the infusion element This resistance the coffee offers makes the water pressure in the boiler increase up to a pressure of 9 Kg cm At this pressure the by pass opens allowing a small amount of water to return sufficient to prevent the water pressure from going over the 9 Kg cm The by pass is a small hole covered with a ball that is held in place by...

Page 13: ...e outlets one through a 3 way EV for the elaboration of espresso coffee This EV has an outlet from the boiler another goes to the infusion element and the third that at rest allows the infusion element to be at atmospheric pressure G1 Solenoid G2 Valve G3 3rd outlet When the machine is in the espresso coffee making process the third is closed while the outlet from the boiler and the inlet to the i...

Page 14: ...r of 3 way EV 10 w Maximum pressure of EV 14 Kg cm Working temperature of EV 10º C a 140º C Temperature control of the water in the boiler is done with a PTC100 Default Temperature from factory is programmed to 85ºC it can be programmed up to 96ºC It must be taken into account that depending on the altitude at which the machine is installed the water can boil at a temperature below 100ºC Altitud m...

Page 15: ... 169 57 169 94 170 31 170 68 171 05 171 42 171 79 190 172 16 172 53 172 90 173 26 173 63 174 00 174 37 174 74 175 10 175 47 200 175 84 176 21 176 57 176 94 177 31 177 68 178 04 178 41 178 78 179 14 210 179 51 179 88 180 24 180 61 180 97 181 34 181 71 182 07 182 44 182 80 220 183 17 183 53 183 90 184 26 184 63 184 99 185 36 185 72 186 09 186 45 230 186 82 187 18 187 54 187 91 188 27 188 63 189 00 1...

Page 16: ...d and a key board The control unit provides the supply voltages for the rest of the components and managing the machine This board is the same of the Zen Zintro and Vitro S5 models but with a different firmware On the door and protected by a cover there is the key board wish has 8 direct products selections and 4 pre selections The activation of these selections and pre selections is done by capac...

Page 17: ... card is tied with 4 plastic nuts and protected by a plastic panel The label holders are attached to the card by pressure To access the card the cup container must be removed 2 2 Hydraulic circuit Conecction to water network JI1 Water deposit J2 Flowmeter J3 Pressure pump J4 Overpressure pump J5 Non return J6 Boiler J7 Electrovalves J8 Water inlet valve Autonomy mode I1 Water deposit I2 Flowmeter ...

Page 18: ...onnected to the hydraulic grid or with a battery unit For connection to the hydraulic mains has a 3 4 inch male socket It shall be connected to a drinking water intake supplying a minimum flow rate of 5 liters minute at a pressure between 0 5 and 10 kg cm2 The hydraulic mains connection hose is not supplied with the machine According to the low voltage regulation the distance between the water int...

Page 19: ... 4 Filling the product containers To put products in the containers you should lift the cover of the machine Otherwise it is necessary to remove the container from the machine 1 Coffee beans hopper 2 Soluble product hoppers After filling the containers for instant beverages it is advised to request a service of each as the first time it is used only a small quantity of product is served 3 5 Fillin...

Page 20: ...let shutter WASTE BIN FULL Remove the waste tray clean it and refit it LONG DISTRIBUTION Adjust the grinding time to coarser Clean the group showers Check that there is voltage to the input solenoid RESIST FAULTY Element broken or disconnected TEMP SENSOR ERR Probe broken or disconnected FAIL WATER LEVEL Check mains pressure Input solenoid or level ball broken or disconnected DOSAGE ERROR Dosser b...

Page 21: ... the control board in the conector jp10 Between pins 3 and 7 will be 220 Vca when doser is activated Grinder Meassured in the control board in the conector jp10 Between pins 4 and 7 will be 220 Vca when grinder is working Transformer Meassured in the control board in the conector JP12 Pins 1 and 2 220 Vca black looms Pins 4 and 5 24 Vca blue looms Pressure electrovalve Meassured in the control boa...

Page 22: ...c with group in charge position Residue tray microswitch Meassured in the control board in the conector jp1 Between pins 4 and 9 will be 0 Vcc when tray is in position Between pins 4 and 9 will be 5 Vcc when tray is not in its in position Floater microswitch with hydraulic connection to the mains Meassured in the control board in the conector jp1 Between pins 4 and 8 will be 5 Vcc when there is no...

Page 23: ...hine Clean the supports where the hoppers are fitted Coffee bean hopper Carry out the same as with the product hoppers Depending on the use of the machine Piston filter Every 15 000 services it is recommended to remove and clean it If necessary it can be cleaned with a non metallic brush If the holes are blocked do not introduce sharp objects into the holes to clean them It is recommended to repla...

Page 24: ...group it is recommended to support with a screwdriver the shower filter at the same time 2 Push the shaft from the bottom and remove the filter holder 3 Press on the clips one on each side shown in the picture below to release the part where the o ring gaskets 4 Once replaced the gaskets replace lids in the group ...

Page 25: ...c compatibility The mains connection cable has an earth wire as established in the electrical safety norm The boiler has a temperature sensor that controls the connection and disconnection of the heating element automatically The boiler has a temperature clixon that disconnects the heating element when it reaches 120º C EN 60335 2 63 96 EN 60 335 1 88 A2 88 A5 89 A6 89 A51 91 A52 92 A53 92 A54 92 ...

Page 26: ...Technical Principles 1ª review UK 12 2020 26 8 VOLUMÉTRIC DIMENSIONS Measurements in mm and weight in Kg Model width height depth weight Vitro X1 Se 2 672 X 337 Y 505 Z 42 kg ...

Page 27: ......

Reviews: